point loma high school
play

Point Loma High School Whole Site Modernization and Athletic - PowerPoint PPT Presentation

REVISED: 5-24-16 Point Loma High School Whole Site Modernization and Athletic Facilities Upgrades Final EIR Certification and Project Approval May 24, 2016 Ove verview Proposed Project Whole Site Modernization Athletic Facilities


  1. REVISED: 5-24-16 Point Loma High School Whole Site Modernization and Athletic Facilities Upgrades Final EIR Certification and Project Approval May 24, 2016

  2. Ove verview • Proposed Project • Whole Site Modernization • Athletic Facilities Upgrades • California Environmental Quality Act (CEQA) Environmental Impact Report (EIR) Process 2

  3. Aerial Vie iew of f Project Sit ite Legend D P 3

  4. Whole Sit ite Modernization – Sit ite Masterplan 4

  5. Modernization Im Improvements 2018 • Demolish existing 800 Building (library/media center and 11 classrooms) • Construct a three-story building with a library/media center and 20 classrooms • Renovate existing two-story, 15,700 sf 200 Building • Renovate existing two-story, 19,700 sf 300 Building • Construct freestanding 150 sf building to house the campus Main Distribution Frame • Create security enclosure around the renovated 200 and 300 Buildings • Create a secure entrance portal for campus visitors from the Clove Street parking lot • Demolish unused Auto Shop • Reconfigure parking lot off Clove Street to increase on-site parking capacity • General landscape and hardscape improvements, new curbs, gutters, and sidewalks along Chatsworth Boulevard in the area fronting the 200, 300, and 800 Buildings possible curb line relocation within the intersection with Zola Street 5

  6. Modernization Im Improvements 2020 • Demolish Building 400 (13 classrooms) • Construct New Cafeteria/Food Services Building • Construct Custodial Supply Building • Modify Service Drive Between New Cafeteria and Boys’ Locker Building • Provide Basketball Courts • Demolish classroom wing of Building 600 containing seven classrooms • Construct elevator and provide stair access to upper floor of Building 600 • Construct new academic landscape/hardscape (including passive and active use areas) • Renovate Gymnasium/Boys’ Locker Room/ROTC Building • Renovate Girls’ Locker/Gymnasium • Renovate Auditorium • Renovate Administration Facilities 6

  7. Ele levation Vie iew of of Im Improvements Alo long Chatsworth 7

  8. View Across Academic Courtyard 8

  9. View from Chatsworth 9

  10. Ath thletic Facilities Component 2016-2020 2020 • Construct visitors’ side restrooms/concession building • Provide 500- seat visitors’ side aluminum bleacher seating • Install two 30-foot light poles immediately behind the aluminum bleachers • Construct 392 sf storage facility for athletic equipment • Construct 616 sf electrical unit substation and signal panel enclosure • Construct 140 sf press box at the top of existing grandstand • Provide elevator for ADA compliant access to press box • Construct electrical closet and elevator control closet • Replace existing PA system • Install four 70-foot tall field light poles on the inside of the track (with double red solid lights per FAA regulations • Install four 20-foot tall grandstand light poles on the home side bleachers • Relocate existing track amenities (long/triple jump, high jump, and pole vault) to east D-zone • Resurface track and fluff synthetic turf field • Remove two existing speaker poles/speakers on the home side of the field; replace with seven new speaker poles (three 20- foot poles on the visitors’ side and four 29 - foot poles on the home side) • Construct 125 sf ticket office (northwest end of the athletic facility) 10

  11. New Slide Proposed Changes to to th the Point Lo Loma High School Sta tadium 11

  12. New Slide Proposed Changes to to Home Sid ide Bleachers 12

  13. Community and Staff Input • Site Master Planning • Design Task Force • Field Use Policy • The intended use of the athletic facilities is limited by Administrative Procedures 9205, 9229, and the board adopted Point Loma Field Use Policy. • The Point Loma High School Field Use Policy was developed with input from students, parents, and neighbors. It was approved by the Board of Education in July 2014. • Point Loma High School facilities shall be used primarily for the benefit of students attending schools in the Point Loma Cluster. • The athletic facilities will not be commercialized by allowing rampant use of outside leagues and organizations. PLHS facilities may be made available to outside persons or community groups only when several specific conditions are met. • “Use of the stadium lighting shall be limited to eighteen (18) nighttime events, not including playoff games or the use of the lights to allow completion of games and practices which begin during daylight hours, but carry over into darkness due to Pacific Standard Time .” 13

  14. Project Phases 1 ‐ Athletic Facilities Upgrades (Field Lighting/PA) • Summer 2016 (9 months) 2 ‐ Whole Site Modernization Phase 1 • Summer 2018 (24 months) 3 ‐ Athletic Facilities Upgrades Phase 2 • Summer 2020 (9 months) 4 ‐ Whole Site Modernization Phase 2 • Summer 2020 (24 months) 14

  15. Califo fornia Environmental Quali lity ty Act (C (CEQA) • Informs the public and decision makers about the project • Identifies feasible ways to avoid or reduce potential impacts • Discloses significant and unavoidable impacts • Provide an opportunity for the public and local/state agencies to comment on the environmental issues 15

  16. PLH PLHS ‐ CEQA Process NOTICE OF NOTICE OF EIR SCOPING NOTICE OF PREPARATION #1 PREPARATION #2 PREPARATION #3 MEETING May 3, 2013 October 30, 2015 December 10, 2015 May 22, 2013 (30 Day Public Review) (30 Day Public Review) (30 Day Public Review) Prepare DEIR SCHOOL Prepare Response to CIRCULATE DEIR BOARD Comments/FEIR (45 Day Public Review) HEARING February 29 – May 13, 2016 APPROVE PROJECT DECISION • Comments from 2 agencies, 4 community groups, and 64 members of public CERTIFY ON PROJECT EIR • All comments in FEIR along with responses DENY PROJECT • FEIR was available for public review 5 places including district website 16

  17. Project Lo Location Point Loma (Peninsula) Point Loma is a large longitudinal hill projecting into the Pacific Ocean from the north end of San Diego Bay, and as such is a major protective feature of the harbor. The Peninsula is a highly urbanized community, comprised of a number of relatively distinct residential neighborhoods. Point Loma High School was built in 1925 and is located in the Loma Portal neighborhood. This neighborhood is one of the older areas of the Peninsula and, as such, is characterized by substantial amounts of landscaping, small winding concrete streets and old street lights, many of which are located in the middle of street intersections. Source: Peninsula Community Plan 1991 17

  18. FEIR FEIR Fin Findings: En Environmenta tal l Im Impacts ts • Aesthetics and Light/Glare • Land Use and Planning • Ag and ForestResources • Mineral Resources • Air Quality • Noise • Biological Resources • Population and Housing • Cultural Resources • Public Services • Geology and Soils • Recreation • Greenhouse Gas Emissions • Transportation and Traffic • Hazards and Haz Materials • Utilities and Service Systems • Hydrology and Water Quality 18

  19. Revised: 5-24-16 Feasible Mit itigation Measures Paleontology – Monitoring of undisturbed rock formations, recovery and curation of accidental discoveries, finalize report Geology – Compliance with geotechnical recommendations for design and construction Hazardous Materials – Management and safety handling of accidentally identified hazardous soil materials Traffic/Transportation – Traffic management of events with more than 327 296 spectators 19

  20. Significant (O (Operation) ) Im Impacts ts Noise • People arriving and departing event • Crowd cheering • PA sound system • Band Traffic • 6 intersections • 11 roadway segments 20

  21. Publi lic Co Comments ts – Li Light/Glare Evolution of Field Lighting Technology Significantly less light spill 21

  22. Project Li Lighting Design Field Lighting Model FAA Required Light in Pt. Loma 22

  23. Publi lic Co Comments ts – Sky Sky Glo low • Comments • Currently no light and glare • Response • Project will contribute to urban glow, but not significant 23

  24. Publi lic Co Comments ts – View iew/V /Vis isual Quali lity ty 24

  25. Publi lic Co Comments ts ‐ Nois ise Mitigation Measures considered, but determined infeasible 1. Construct a 30‐foot high wall and reduce speaker height 2. Depress football field by 25 feet 3. Depress football field by 25 feet and construct an 8‐foot wall 4. Enclose sports field entirely 5. Construct concrete bleachers 6. Replace neighbor’s windows and install HVAC 25

  26. Public Comments - Parking PH 1 PH 2 PH 3 PH 3 PARKING SUPPLY On‐Site 168 148 180 180 Off‐Site (Unoccupied street within 1/3 mi) 968 968 968 968 Off‐Site (Nearby District schools) 255 255 255 255 1,391 1,371 1,403 1,403 Subtotal PARKING DEMAND Homecoming Football Game 1159 1159 1230 1,230 Non‐Homecoming FootballGame 783 783 908 908 PARKING SURPLUS Homecoming Football Game 232 212 173 173 Non‐Homecoming FootballGame 608 588 495 495 26

Recommend


More recommend