PILLAR POINT HARBOR RESTAURANT/RETAIL SIDEWALK EXPANSION PROJECT 7/19/17 CSG CONSULTANTS INC. SAN MATEO COUNTY HARBOR DISTRICT
PROJECT SCOPE • EXTEND CONCRETE PROMENADE IN FRONT OF BUSINESSES • REPAIR BASE FAILURES IN PARKING LOT • RE-SEAL PARKING LOT • UPDATE NON- COMPLIANT CURB RAMPS • RECONFIGURE PARKING TO COMPLY TO ADA STANDARDS
PROMENADE • PROMENADE EXTENDS FROM 11 FT TO 25 FT WIDE • 5 FT OF SIDEWALK WILL BE INCLUDED FOR PEDESTRIAN USE • ACCESS RAMPS ARE ADDED PER ADA REQUIREMENTS • PARKING STALLS DIRECTLY IN FRONT OF PROMENADE WILL BE REMOVED
PAVEMENT REPAIRS • APPROXIMATELY 20 AC DIGOUTS TO BE PERFORMED IN PARKING LOT • PARKING LOT WILL ALSO BE RESEALED VIA SLURRY SEAL • ALL ASPHALT WORK WILL BE PERFORMED IN 2 PHASES TO ALLOW IN AND OUT ACCESS AT ALL TIMES
CURB RAMPS & SID IDEWALKS • 13 NEW CURB RAMPS • VALLEY GUTTERS TO BE REPLACED ALONG UPPER LOT • ALL TRUNCATED DOMES TO BE YELLOW • NEW SIDEWALK AND RAMPS TO BE CONSTRUCTED BETWEEN THE RESTAURANT AND HARBORMASTERS OFFICE
PARKING STALL LAYOUT • 6 NEW ACCESSIBLE STALLS FOR PROMENADE AREA • EACH LANDING ZONE HAS A CROSSWALK TO LEAD TO RAMP • BOAT STALLS TO BECOME STANDARD PARKING STALLS • CREATES A +2 NET IN PARKING FOR SOUTHERN PART OF LOT • 2 NEW ACCESSIBLE STALLS FOR HARBORMASTER OFFICE/PIER VIEW