Orange County Public Schools Welcome! Please sign in on your mobile device: http://communitymeeting.ocps.net/ Cypress Park/Durrance Elementary School 40% Construction Community Meeting February 21, 2018 Superintendent Dr. Barbara Jenkins Chief Facilities Officer John Morris
Orange County Public Schools Orange County Public Schools Cypress Park/ Durrance Elementary School 40% Construction Meeting Meeting Agenda • Welcome : School Board Member Linda Kobert • Introductions : Meeting Organizer Lauren Roth, OCPS Communications • Project Update : Architect: Song + Associates, Inc. Contractor: Charles Perry Partners, Inc. • Questions & Answers • Adjournment 2
Orange County Public Schools Regional Overview - Existing Cypress Park Site N Feeder street is 4 th Street • Access street to school is 11 th Ave. • 3
Orange County Public Schools Existing Site Existing School Data Existing School Data Existing Loop Parking: 32 Cars Existing Site Area – 10 acres Existing Bus Drop Off on 11 th Avenue: 2 Buses Current School Population – Approx. 280 Existing Grass & Service Parking: 20 Cars Existing Streetside Sidewalks: None 4
Orange County Public Schools Existing Site Existing Classroom Buildings 11+12 (16 C.R.) Existing Covered Play Area Retention Demolition & Playground Construction Phase 2 N Demolition Existing Car Loop Queuing: ± 15 Existing Parking: ± 52 Relocate Renovation Construction Fence 5
Orange County Public Schools Orange County Public Schools Preliminary Phasing Click to edit Master title style Phase 2 Phase 2 Summer Renovation Summer Renovation Phase 1 Phase 2 Construction Zone Retention Outdoor Phase 1 Play area School Year 2017-2018 Phase 2 Parent drop off N Construction Fence Demolition Renovation Portables New Building 2/21/2018 6
Orange County Public Schools Orange County Public Schools Perspective view Click to edit Master title style 2/21/2018 7
Orange County Public Schools Orange County Public Schools Perspective view Click to edit Master title style 2/21/2018 8
Orange County Public Schools Orange County Public Schools Schedule PHASE 1 CONSTRUCTION – BUILDING 100 • July 18, 2017: Start Construction Building 100 • February 21, 2018: Construction 40% Complete • May 24, 2018: Finish Construction Building 100 9
Orange County Public Schools Orange County Public Schools Schedule PHASE 2 & 3 CONSTRUCTION BUILDINGS 200, 300, 400 & ESE BUS LOOP August 3,2018 August 13,2018 October 15, 2018 May 31, 2018 June 8,2018 PHASE 2 PHASE 2 First Day of School Move Out Existing Buildings Demo of Old Building 100 Move In New Building 100 Renovation of Buildings 200/300 Construction of Building 400 (PE) Construction of ESE Bus Loop PHASE 3 - Site Conditions and Playfields Complete 10
Orange County Public Schools Aerial Photo July 2017 Site Fence and Demo
Orange County Public Schools Aerial Photo August 2017 Building Pad and Foundations
Orange County Public Schools Aerial Photo September 2017 Concrete Slab and Walls
Orange County Public Schools Aerial Photo October 2017 Concrete Tilt Walls and Sitework
Orange County Public Schools Job Photo October 2017 Concrete Tilt Walls
Orange County Public Schools Aerial Photo November 2017 Structural Steel
Orange County Public Schools Aerial Photo December 2017 Roofing and Windows
Orange County Public Schools Aerial Photo January 2018 Exterior Paint and Interior Framing
Orange County Public Schools Current Construction Photos Walls and MEP Systems
Orange County Public Schools Thank You! Questions?