Status of DryPorts Development in Nepal Gopal Prasad Sigdel, Joint secretary, Ministry of Physical Planning and Transport Nepal New Delhi ,Aug 1-2, 2018 1
NEP AL CHINA Area : 147,181 Sq. Km. Population: 27.8 Mill. GDP Per capita : US$865 Kathmandu 2
Major Trade & Transit Points of Nepal Pulan Second Phase(MOU) Yari Th Third Phase(MOU) hird (Humla) Hyazimang ICD (Under Construction) Mugu (First Phase) (Mugu) L izi Survey DesigningStage Dodhara Chadani (Kanchanpur) Nechung NORTH (Mus tang) Larke (Gorkha) Rasuwa R iwu (R asuwa) Olang chung ola CFS/ICD (T aplejung) Kimathanka (Sankhuwasabha) Integrated Check Posts (ICPs)Proposed Inland ClearanceDepots (ICDs) Under Operation Nepal Intermodal Transport Development Board, Kathamndu, Nepal, Phone: +977-1-4440936, 4439664, Email: nitb@wlink.com.np
Status of Railway Connectivity Pulan Yari (Humla) Hyazimang Mugu (Mugu) L izi Dodhara Chadani (Kanchanpur) Nechung NORTH (Mus tang) Larke (Gorkha) Rasuwa R iwu (R asuwa) CFS/ICD Olang chung ola Kimathanka (T aplejung) (Sankhuwasabha) Proposed Railway Connectivity Existing Railway Connectivity Nepal Intermodal Transport Development Board, Kathamndu, Nepal, Phone: +977-1-4440936, 4439664, Email: nitb@wlink.com.np
T RANSPORT INFRASTRUCTURE(2016 ) ROADS LENGTH STRATEGIC ROAD NETWORK 12498 KM LOCAL ROAD NETWORK 57632 KM RAILWAYS J AYNAGAR(INDIA)-J ANAKPUR 51 KM RAXAUL(INDIA)- BIRGUNJ ICD 5 KM AIRFIELDS INTERNATIONAL 1 NO DOM ESTIC 48 NOS DRY PORTS ROAD BASED 4 NOS RAIL BASED 1 NO
ROADS CONNECTING DRY PORTS DRY PORTS ROADS LENGTH CONNECTING STATUS AND FUTURE PLANS BIRGUNJ ICD 29Km E/ W HIGHWAY 6 Lane road under construction ICD under Pathalaiya Operation BIRATNAGAR ICD 31KM E/ W HIGHWAY 6 Lane Road under construction ICD under Itahari consideration KAKARBHITTA ICD 1 KM E/ W HIGHWAY Under Operation Kakadbhitta BHAIRAHAWA ICD 24 KM E/ W HIGHWAY 6 Lane Road under construction Butwal TATOP ANI ICD 114 KM Kathmandu UNDER CONSTRUCTION RASUAWAGADI 84 KM Galchhi Prithvi UNDER CONSTRUCTION Highway DODHARA 9 KM M ahendranagar E/ W UNDER CONSTRUCTION CHANDINI HIGHWAY KOROLLA 110 KM Jomsom Planned KATHM ANDU 9 KM Kathmandu UNDER CONSTRUCTION CHOBHAR
FOREIGN TRADE SITUATION Status of Nepal as perDoing Business Report 2015 Export Cost per container US$ 2545 Export Time 40 days Import cost per container US$ 2650 Import Time 39 days Stream Share of Total Trade(2016/17) Export 6.9 % Import 93.09% 100% India 64.92% Overseas 35.08% 100% 4 Source: WB & GON
Transport Infrastructure (2016) Roads Local Roads (57,632 Km) Strategic Roads (12,473 Km) Railways Jayanagar (India) - Janakpur (Nepal) Raxaul (India) – Birgunj (Nepal) (51 KM) (5 KM) Airfields 48 Nos. (registered) Dryports Road based (3+1) Rail based(1) 8
DRY PORTS(RAIL BASED)
Dry Ports (Roadbased) BHAIRAHA W A BIRA TNAGAR K A K A RBHITT A T A T OP ANI 10
Dry Ports (Roadbased) • BIRATNAGAR BHAIRAHAWA
Dry Ports (Roadbased) KAKARHITTA TATOP ANI
13
UNES C A P Kakarbhitta Bhairahawa DRY PORTS Biratnagar Birgunj Tatopani (Under Construction) 20
Future Dryports Under Construction: • - Tatopani ICD - Source: PR China (Turn Key) - Connectivity: Asian Highway 42 (AH42) (Construction period is extended due to earthquake) • Proposed: Rasuwa: (Assistance : PRChina) – Detail Design is about tofinalize. - Construction contract will be awarded soon. - – CFS/ICD at Kathmandu Valley (Assistance: WB): - Awaiting for Construction Tender Process. – Korola (Mustang): - Pre-feasibility study has been completed. – Dodhara Chadani (Kanchanpur)-AH2: - Feasibility study is ongoing. 15
Rescue Project Tatopani Dry Port (Under Construction) 23
Rasuwa Dry Port � Layout Design Warehouse Parking Area for 350 Admin Building 750 Sq.M. trucks 5000 Sq.M Appraisal Shed 2nos. Total 2080 Sq.M.
Kathmandu CFS/ ICD (Google View ) 18
Korola (M ustang) 19
Dodhara Chadani (Kanchanpur) 20
Challenges • Geological status of Roadsand Infrastructure International Recognition of Dryports • • Transshipment facility and additional Port Connectivity • International Guidelines for leasingout of ports • Road carriage act and Regulation • Rail carriage act and regulation Dry Port Management issues • (Managerial/Technical/Awareness) • Reduction in Import/ExportProcess 30
Way Forward: • Cost of logistics and transit transportation for landlocked countries is > 15% than coastal countries • UNESCAP needs to address capacity building activities for managerial, technical and awareness issues regarding dry port taking in mind of its importance Should conduct national levelactivities also • • International agency should focus on bringing out guidelines related to transshipment, port leasing, Registration of LOCODE, Locate dry port on the international shipping map, etc. • Ratification of Intergovernmental Agreement on Dry ports 31