Northwest Water Treatment Plant Improvements Project Update Reed M. Barton, PE Brunswick County, NC August 2019
Project Timeline Preliminary Engineering & NPDES Permit Advanced Treatment Evaluation Bidding & Construction May - Aug ’18 Jan - Apr ‘18 Oct ’19 - Sep ‘22 Application Submitted Nov ‘18 LPRO Pilot Testing Final Design and Permitting Feb - Jul ’18 Extended to May ‘19 Oct ‘18 - Sep ‘19 Project Update, Northwest Water Treatment Plant Improvements, Aug. 19, 2019
Design Status Two design packages: Northwest WTP Expansion and Upgrades 90 percent submitted - July 2019 Concentrate Pipeline and Outfall 60 percent submitted – July 2019 Design remains on schedule Final design submittals - Sept 2019 3 Project Update, Northwest Water Treatment Plant Improvements, Aug. 19, 2019
NPDES Permit Status July – August 2019 – NCDEQ preparing draft permit June 2019 - Plant tour and meeting with NCDEQ Confirmed no additional information required January – May 2019 - NCDEQ comments/meetings November 2018 - Application Submitted May 2018 – October 2018 – Data collection and modeling Next step NCDEQ will issue draft permit 4 Project Update, Northwest Water Treatment Plant Improvements, Aug. 19, 2019
Project Costs Update 90% Opinion of Construction Costs prepared in August 2019 Cost opinion remains aligned with project budget Deductive bid alternates incorporated into design Assist in managing construction costs 5 Project Update, Northwest Water Treatment Plant Improvements, Aug. 19, 2019
Project Funding Update WIFIA Funding EPA engineering, environmental, and financial reviews ongoing State Level Funding State Revolving Fund (SRF) Loan Application submitted in Oct 2018 March 2019 – notified that project was not awarded SRF funding NCDEQ funding priorities for Fall 2019 have been adjusted Plan to submit a revised SRF application in Fall 2019 6 Project Update, Northwest Water Treatment Plant Improvements, Aug. 19, 2019
Upcoming Pre-Qualifications and Bidding RFQs and RFPs (August – September) General Contractor Pre-Qualification Membrane System Supplier Pre- Qualification Membrane Element Proposals Bidding for NWTP Plant and Concentrate Pipeline Advertise in October Bid Opening in December 7 Project Update, Northwest Water Treatment Plant Improvements, Aug. 19, 2019
Planned Construction Schedule Anticipated award of contracts in January 2020 NWTP Plant construction completion in September 2022 Early Milestone of RO system use by December 2021 Concentrate Pipeline construction complete in June 2021 8 Project Update, Northwest Water Treatment Plant Improvements, Aug. 19, 2019
Upcoming Milestones Advertise Project for Bid 100% Design Milestone 90% Design Milestone Oct ’19 Sept ’19 Jul ‘19 Remaining Permit Pre-Qualification Submittals for Contractors and Membrane Aug – Sep ‘19 Supplier Aug – Sept ‘19 Project Update, Northwest Water Treatment Plant Improvements, Aug. 19, 2019
Reed M. Barton, PE bartonr@cdmsmith.com 10 Project Update, Northwest Water Treatment Plant Improvements, Aug. 19, 2019