Northumberland Reconstruction Project SR 147, Sec 110 & SR 11, Sec 113 Northumberland Borough Northumberland County ~ PennDOT District 3-0 February 13, 2019
Agenda • Purpose and Need of Project – Ted Deptula, P.E., PennDOT Assistant Construction Engineer • Construction 2018 Review • 2019 Construction and Detours – Joe Whitcomb, New Enterprise Project Manager – Mindy Foresman, PennDOT Project Manager • Conclusion SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 2
Why Now? 3
Why Now? 4
Project Scope of Work • Roadway Reconstruction • Drainage • ADA Ramps, Curb, & Sidewalk • Intersection Improvements • Utilities SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 5
Northumberland Reconstruction Project • Construction Status – Work started June 5, 2017 – Contractor = New Enterprise Stone and Lime Co., Inc. – Cost = $14 M – Contract completion date is Summer 2020 SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 6
Project Limits & Schedule 11 • 2017 Construction – Phase 1-3 • Duke Street • 2018 Construction – Phase 4-9 • Duke Street – Phase 14 & 15 • Front Street • 2019 Construction – Phase 10 – 13 • Water Street • King Street • 2020 Construction – Clean up LOCATION MAP SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 7
Traffic Phasing • Maintain access to businesses and residents • Maintain bicycle/pedestrian traffic • Pineknotter Days – Week of July 4th each year • Detour traffic using borough streets • Restrict non-local truck traffic (>36’) SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 8
No Parking Area During Detour No Parking Areas LEGEND Parking Lane Existing Condition Travel Lane Travel Lane Proposed Detour Condition SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 9
Local Detour Condition King, Queen and Orange Streets Existing Condition Proposed Detour Condition SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 10
2018 Review • Duke Street Reconstructed – 5 th Street to Front Street • Utilities – Duke, Front and Water Streets • Temporary Wearing Course • Car and Truck Detours • Front Street Reconstructed 11
2Roadway 2018 Completed Work 2012Reconstruction Completed 2017 P A T 1 O 4 7 M I L T O N PA 147 TO SUNBURY LEGEND Completed Roadway Work Area SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 12
Truck Detour & Truck NEW Alternate Routes COLUMBIA PROJECT LOCATION Detour SR 147 WEST MILTON MILTON MONTANDON LEWISBURG NORTHUMBERLAND WINFIELD LEGEND Work Area Detour (SR 147) SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 13
2019 Construction Season Joe Whitcomb, New Enterprise Project Manager Mindy Foresman, PennDOT Project Manager • Scope – Duke Street , Front Street to Water Street – Water Street , King Street to Rail Road Underpass – Front Street , Old Danville Hwy to Wallace Avenue – Traffic signals , King & Water, Duke & Water • Work shifts • Detours 14
2019 Roadway Reconstruction Phasing PA 147 TO SUNBURY 15
Duke Street Project Roadway Reconstruction Traffic Control Plan Pink Phase TEMPORARY TRAFFIC SIGNAL LEGEND ROADWAY WORK X DETOUR NORTH X DETOUR SOUTH X B N X CLOSED S E P 1 B O 1 N D R E S 1 S 1 O R L S C 16
Duke Street Project Roadway Reconstruction Traffic Control Plan Blue Phase PA 147 TO MILTON TEMPORARY TRAFFIC SIGNAL LEGEND PA 147 X TO SUNBURY WORK AREA X X DETOUR NORTH SR 11 SB OPEN DETOUR SOUTH SR 11 NB CLOSED X X CLOSED 17
Duke Street Project Roadway Reconstruction Traffic Control Plan Green Phase LEGEND SR 147 NB OPEN WORK AREA NB X WORK AREA SB X DETOUR SOUTH SR 11 SB CLOSED TO P CLOSED T A X O 1 SR 147 SB S 4 7 U N B U R Y SR 11 SB TO SR 147 SB SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 18
Duke Street Project Roadway Reconstruction Traffic Control Plan Purple Phase TEMPORARY TRAFFIC SIGNAL X X X X X X LEGEND X X PA 147 TO SUNBURY WORK AREA DETOUR NORTH & SOUTH TEMPORARY TRAFFIC SIGNAL X O CLOSED N T I K 1 O 1 M B M A N A P A D N 1 H 1 E S P R O S SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 19
Duke Street Project Roadway Reconstruction Traffic Control Plan Orange Phase TEMPORARY TRAFFIC SIGNAL LEGEND X X X WORK AREA PA 147 TO SUNBURY DETOUR NORTH & SOUTH X TEMPORARY X CLOSED TRAFFIC SIGNAL PA 11 TO SHAMOKIN DAM SR 11 NB OPEN SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 20
Railroad Underpass Reconstruction • Contractor: Kriger Construction, Inc. – Southbound lane completed – Northbound lane under construction • Bridge repairs • Remove sidewalk • Reconstruct concrete pavement • Mill and overlay between river bridge and concrete pavement – Complete before Pineknotter Days 21
Northumberland Reconstruction Project • Conclusion – Duke Street, Front Street, Water Street & King Street – 2019 • Water Street and King Street • Railroad Underpass • Front Street completion – 2020 • Final Paving and Project completion SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 22
Northumberland Reconstruction Project • Communication – Website: www.penndot.gov/dukestreet – E-mail: DukeStreet@pa.gov – 24-Hour Hotline: 855-336-8698 – Community Roundtables SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 23
NORTHUMBERLAND RECONSTRUCTION PROJECT www.penndot.gov/dukestreet SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 24