midwest geotechnical conference
play

Midwest Geotechnical Conference Columbus, Ohio September 2019 Bob - PowerPoint PPT Presentation

Midwest Geotechnical Conference Columbus, Ohio September 2019 Bob Arndorfer AASHTO Definitions: Cohesive IGMs - Exhibit Unconfined Compression Strengths Between 10-100 ksf Cohesionless IGMs - Exhibit Blow Counts (N) Greater Than 50


  1. Midwest Geotechnical Conference Columbus, Ohio September 2019 Bob Arndorfer

  2.  AASHTO Definitions:  Cohesive IGMs - Exhibit Unconfined Compression Strengths Between 10-100 ksf  Cohesionless IGMs - Exhibit Blow Counts (N) Greater Than 50 Blows/Foot Using Standard Penetration Test 2

  3.  Hole is Drilled (Pre-bored) Into the IGM Material and Bottom is Cleaned  H-Pile Is Placed Into Hole – No Driving (Seated)  Hole Is Backfilled With Concrete  Pile Extends Up Into Abutment  Is the Resulting Deep Foundation Member a Shaft or a Pile? 3

  4.  WisDOT Experience with IGM Varies  Codes Provide Limited Guidance on Design Methodology/Pile Capacity in IGM Materials  Project Used Load Test to Verify Design Assumptions For Drilled-in Piles  Lead to a Methodology Used to Design Drilled- in Piles in IGM Material  Help Eliminate Some Common Pile Installation Issues In These Situations  Goal – Save Money 4

  5.  WisDOT Often Designs MSE Walls Around Abutments  Reduce Bridge Span Lengths  Support Abutments on Piles Through MSE Backfill  Install Piles Prior to Wall Construction  IGM Materials Make Pile Length Estimates Difficult  Difficult Driving Often Leads to Pile Alignment Issues  What About Installing Pre-bored/Backfilled Piles Into the Very Dense IGM? 5

  6.  Alternative Foundations?  Why Not Use Spread Footings?  Why Not Use Drilled Shafts?  Will Address Those Later  Proper Design Methodology – Shaft or Pile?  What Corresponding Resistance Factor?  Cost Effective to Conduct a Pile Load Program? 6

  7. 7

  8.  Site Has High-strength Till Soils  Consultant-Designed Project  Multi-Year Construction  Project Had Enough Lead Time to Accommodate Load Test Program  Was an Adjacent, On-going Project We Could Add Load Test Program to  Results From Load Test Incorporated Into Project Plans (Pre-Letting) 8

  9. 9

  10. Chippewa River 10

  11. Chippewa River 11

  12. Chippewa River 12

  13.  Driven H-Piles Using Modified Gates:  Resistance Factor of 0.50  Driven H-Piles Using Pile Driving Analyzer:  Resistance Factor of 0.65  Drilled Shafts:  Resistance Factor 0.35-0.5 (No Load Test)  Bored H-Piles With Static Load Test:  Resistance Factor of 0.8 (Load Test)  Resistance Factor of 0.8 (Shaft Spacing) 13

  14.  Sometimes Piles Run Very Long (Increased Cost and Times), or Very Short (Creating a Lateral Resistance Concern)  Difficult to Achieve Necessary Alignment Above Driven Elevation – Often Not Aware of This Until After Hammer Leads are Removed  Adjacent Bridge Experienced Both of These Issues 14

  15.  Larger Diameter/Conflicts With MSE Wall  Requires Slightly Longer Bridge  Lower Resistance Factor (No Load Test), Resulting in Deeper Shafts  Secant Walls Also Considered – High Cost 15

  16.  Multi-span Bridges: WisDOT Typically Does Not Use Spread Footings on MSE Walls  Would Require Expensive Full-retaining Abutments and Wings Instead of MSE Wall  Early Cost Estimate Indicated Pre-bored Piles w/Load Test May Be Most Cost Effective Alternative  Decision: Conduct Load Test of Pre-bored Hybrid Piles to Confirm Design/Costs 16

  17.  Assume Similar Nominal Load to Driven Piles  Same Number of Support Members  Same Spacing of Members  Use to Estimate Shaft Depths Using Static Analysis  Check To Ensure No Settlement Issues  Use HP 14x74 Piles  30” Pre-bored Holes (Contractor Used 34”)  Pre-bore to 20’ Below MSE Wall Pad  Include Side Friction and End Bearing 17

  18.  Resistance Factors of 0.8 (Load Test) and 0.8 (Shaft Spacing)  Only Tested Axial  Added to Existing Adjacent-Project Contract  Jim Long Designed and Conducted Load Test  Standard Test – 1 Test Pile and 4 Reaction Piles  Load Frame Designed by Contractor  Davisson Failure Criteria Used – Pile or Shaft?  $100k Cost 18

  19. Top of Shaft Chippewa River Bottom of Shaft Settlement? 19

  20. 20

  21. 21

  22. 22

  23. 23

  24. 24

  25. 25

  26. 26

  27. 27

  28. Design Load = 500 Kips 28

  29.  Follow AASHTO For Shaft Design in IGM  Nominal Shaft Capacity of 500 Kips  Resistance Factors  0.8 For Using Load Test  0.8 For Shaft Spacing  Total Applied = 0.65 (End Bearing and Side Friction)  Equates to Factored Load of 325 Kips  Conservatively Used Design Shaft Depth From Load Test (Based on Pile Criteria) 29

  30.  Same Shaft Depths as Load Test  Use 14x73 H-Piles With 4” Shear Studs  34” Diameter Pre-bored Holes  Require Full-depth Casing  Spacing of Piles – 5.5 and 6.0 Feet  Place Piles in Hole – Firmly Seat (Do Not Drive)  Socket-in Piles With Concrete – Full Depth  Piles Extend to Abutment  No Ground Disturbance Within 10’ for 24 Hours 30

  31. 31

  32. 32

  33. 33

  34. 34

  35. 35

  36. 36

  37. 37

  38.  Pile Installation Went Well  Dry Holes, Cased All the Way Down  Good Contractor Production  Able to Keep Alignment  No Subsurface Pre-boring Surprises  No Other Issues Noted  Project Still Being Constructed, But Abutments and Walls Have Been Completed 38

  39.  Based on Comparison to Static Pile Estimates For Driven Piles and Actual Bid Costs of Pre- bored Piles  Load Test Costs Removed ($100k)  Bridge B-13-831 Savings: $200k  Bridge B-13-832 Savings: $130k  Possible Total Savings: ≈ $200-330k 39

  40. B-13-0831 $208,664.40

  41. B-13-0832 $129,336.40

  42.  Will Consider This Deep Foundation Type on Future Projects With Similar Subsurface Conditions and Designs  During Design – Will Estimate Costs to Ensure This Option is the Most Economical Foundation  Hope This May Generate Creation of More Design Guidance 42

  43. 43

Recommend


More recommend