measure l bond update
play

MEASURE L BOND UPDATE August 14, 2018 Measure L Overview Project - PowerPoint PPT Presentation

MEASURE L BOND UPDATE August 14, 2018 Measure L Overview Project Updates FIS and Classroom Furniture Update Program Schedule Review Presentation Toyon FIS Measure L Project Updates Vinci Park Elementary School


  1. MEASURE L BOND UPDATE August 14, 2018

  2. Measure L – Overview • Project Updates • FIS and Classroom Furniture Update • Program Schedule Review • Presentation • Toyon FIS

  3. Measure L – Project Updates • Vinci Park Elementary School ‐ FIS • Phase 1 – Interior Work ‐ Complete • Phase 2 – Exterior Work • Work to be completed by 8/17, with exception of FIS fencing • Ruskin Elementary School ‐ FIS • On schedule to complete in October 2018 • Piedmont Middle School ‐ FIS • On schedule to complete in October 2018

  4. Measure L – Project Updates • Brooktree Elementary School • Modernization Project • Provide path of travel to exterior student restrooms at playground ‐ Complete • ADA upgrades to exterior student restrooms ‐ Complete • ADA drinking fountain replacement ‐ Complete • ADA upgrades to staff restrooms ‐ Complete • Exterior glazing ‐ Complete • Interior painting ‐ Complete • Flooring Project • Flooring ‐ Complete • Flexible Instruction Space is on schedule

  5. Measure L – Project Updates • Cherrywood Elementary School • Interior Painting Project • Interior painting ‐ Complete • Flooring Project • Flooring – Complete • Miscellaneous Work • Removal of casework at MPR ‐ Complete • Install tackable wall panels at MPR – Complete • Classroom whiteboards ‐ Complete • FIS • Submitted to DSA September 2018

  6. Measure L – Project Updates • Toyon Elementary School • Interior/Exterior Painting Project • Interior painting ‐ Complete • Exterior painting ‐ Complete • Flooring Project • Flooring ‐ Complete • Miscellaneous Work • Exterior door replacement ‐ Complete • Stage partition repair ‐ Complete • Sink repair at classroom 1 ‐ Complete • Tinting/Painting of Classroom windows – anticipated completion Mid‐September

  7. Measure L – Project Updates • Toyon Elementary School ‐ continue • FIS • Submitted to DSA 8/6 • Receive bids 10/30 • Recommendation of award at the November 13, 2018 meeting • Start construction November 2018 • Completion February 2019

  8. Measure L – Project Updates • Morrill Middle School • Modernization Project • Site concrete replacement at Administration entrance ‐ Complete • Site concrete replacement at northwest stairs ‐ Complete • Site concrete replacement between B & C ‐ Complete • Provide path of travel; ramp to blacktop area ‐ Complete • Upgrade to ADA parking – Complete • Minor ADA upgrades to student restrooms – Complete • ADA upgrades to staff restrooms – Complete • Concrete slab repair at buildings B, C, D and E ‐ Complete • Interior painting – Complete • Reconfigure of Library space – Complete • Fencing – Chain link fencing is complete/ornamental fencing to be complete by 8/25

  9. Measure L – Project Updates • Morrill Middle School ‐ continue • Flooring Project • Flooring ‐ Complete • Flexible Instruction Space is on schedule for completion in October • Moving • Administration spaces moves in ‐ Complete • Library/Kitchen moves will be completed by 8/8 • Classrooms moves will be completed by 8/8

  10. Measure L – Project Updates Cherrywood ‐ MPR ‐ Before

  11. Measure L – Project Updates Cherrywood ‐ MPR ‐ After

  12. Measure L – Project Updates Toyon ‐ Exterior ‐ Before

  13. Measure L – Project Updates Toyon ‐ Exterior ‐ After

  14. Measure L – Project Updates Toyon ‐ Kindergarten Classroom ‐ Before

  15. Measure L – Project Updates Toyon ‐ Kindergarten Classroom ‐ After

  16. Measure L – Project Updates Brooktree ‐ MPR

  17. Measure L – Project Updates Brooktree ‐ Work Room ‐ Before

  18. Measure L – Project Updates Brooktree ‐ Work Room ‐ After

  19. Measure L – Project Updates Morrill ‐ Main Entry ‐ Before

  20. Measure L – Project Updates Morrill ‐ Main Entry ‐ After

  21. Measure L – Project Updates Morrill ‐ Administration

  22. Measure L ‐ Furniture • Classroom Furniture ‐ 2018 Projects • Classroom furniture delivery ‐ Complete • FIS Furniture ‐ 2018 Projects • Meeting with principals

  23. Measure L – Program Schedule Construction & Furniture Projects Construction Legend Furniture Legend Design Preconstruction Furniture Desing Furniture Ordered DSA Review Construction Quote Pricing Lead Time Bid Start of School PO Generated Furniture Received and Placed Award Punch List Construction Projects 2 0 1 8 2 0 1 9 July August September October November December January February March April May June July August Week Week Week Week Week Week Week Week Week Week Week Week Week Week 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 Vinci Pa r k FI S Exterior Rusk in FI S Pie dm ont FI S Parking I m provem ents Brook tr e e Flooring Modernization FI S Che r r y wood I nterior Painting Flooring FI S/ Modernization Toy on I nterior/ Exterior Painting Flooring FI S/ Modernization Mor r ill Flooring Modernization FI S Furniture Projects FI S Furniture - Phase 4 Classroom Furniture

  24. Presentations • Toyon – Flexible Instructional Space (FIS)

  25. Toyon Elementary School Flexible Instruction Space August 14, 2018 25

  26. Team Introductions • McKim Design Group – Architect • BUSD • Kirk McKim, Principal Architect • Tony Kanastab – Director, Facilities • Todd Walter, Director/Architect and Modernization • Kitchell – Project Management • Jim Wilson – Project Director 26

  27. Toyon ES Flexible Instruction Space 1) Brief Overview of Scope 2) Q&A 27

  28. Scope Overview • Flexible Instruction Complex • Convert existing Library space to Flexible Instruction Space • Convert adjacent Offices to Maker Space • Convert adjacent Offices & Workroom to Library/Bookroom • Convert adjacent Janitor/Junk outdoor exit space to Outdoor Learning Space. • Restroom Modifications • For accessibility only • Parking & Path ‐ of ‐ Travel upgrades for accessibility • Entry concrete and walkway upgrades/replacement for accessibility & drainage • Fencing adjacent to street access 28

  29. Flexible Instructional Space – INDUSTRIAL OUTDOOR LAB Outdoor Creation Space (Messy) Display LIBRARY ‐ BOOK ROOM Investigate ‐ Research MAKER SPACE Design – Manufacture ‐ Create Design ‐ Collaborate ‐ Assemble FLEXIBLE INSTRUCTION SPACE

  30. Flexible Instructional Complex

  31. Flexible Instructional Complex

  32. Flexible Instructional Complex

  33. Library – Book Room

  34. Maker Space

  35. Maker Space

  36. Flexible Instruction Space

  37. Flexible Instruction Space

  38. Flexible Instructional Space

  39. Flexible Instruction Space

  40. Flexible Instruction Space

  41. Outdoor Lab

  42. Q&A 42

  43. Thank You

Recommend


More recommend