measure a
play

Measure A Pedestrian & Bicycle Program Update April 4, 2019 - PowerPoint PPT Presentation

Measure A Pedestrian & Bicycle Program Update April 4, 2019 Board of Directors Agenda Item #10 (b) Overview Program background Program allocations & delivery status Feature Project: California Drive Roundabout


  1. Measure A Pedestrian & Bicycle Program Update April 4, 2019 Board of Directors Agenda Item #10 (b)

  2. Overview • Program background • Program allocations & delivery status • Feature Project: California Drive Roundabout (Burlingame) 2

  3. Program Background • 3% of Measure A Program • Purpose: to fund capital projects that encourage and improve walking and bicycling conditions • 2004 Transportation Expenditure Plan includes a list of bikeways and overcrossings but other projects can be considered • Funding awarded on a discretionary Call for Projects process 3

  4. Project Allocations Award Award Number of Cycle Date Amount Projects Special 2010/2011 $0.7M 2 Circumstances First July 2011 $4.5M 16 Second April 2014 $5.9M 11 Third March 2016 $5.0M 10 Fourth March 2018 $5.7M 10 TOTAL $21.8M 49 4

  5. Program Delivery Status Number of Project Status Projects Planning/Preliminary Engineering/ 3 Environmental 14 Final Design 6 Construction 24 Awarded project scopes complete 2 Sponsor rescinded projects 49 TOTAL  Sponsors submit quarterly progress reports on project status.  To date, 12 awarded projects needed time extensions. 5

  6. Distribution of Project Awards Total: $21.8M County Funding North County: $3.9M Sub-area Awards North 10 County Mid County: $8.5M Mid County 17 Coastside: $1.9M South 17 County South County: $7.5M Coastside 5 Total 49 6

  7. California Drive Roundabout Overview • Existing Conditions • Project Goals • Funding • Schedule • Construction Staging • Challenges • Lessons Learned 7

  8. Project Location California 8

  9. Existing Conditions Major through movements on California Drive needs to Conflicting movements creates be accommodated. confusing conditions for pedestrians and cyclists. Four-lane mid-block crosswalk with flashing beacon. Stopped vehicles impact traffic on the Bellevue and Lorton approaches . Weaving, merge and diverge movements create a confusing situation. 9

  10. Project Goals Improve the California Drive, Bellevue Avenue and Lorton Avenue intersection by: • Improving safety and flow of all modes (pedestrians, bicyclists, and vehicles) • Incorporating Green Streets and Complete Streets components • Enhancing bicycle and pedestrian access • Minimizing construction and parking impacts 10

  11. Project Funding Project Funding - Design 2015: Burlingame received $1.0M (Design Contract: $293 K) Measure A Ped/Bike Program allocation, matched with $200k of City funds. 40% Total original project budget: $1.2M. Total project cost upon completion in 60% 2019: $4.3M. Measure A City of Burlingame Project Funding - Construction (Construction Contract: $2.9 MIL) Rationale for added costs: • Added design elements from project outreach & increase in 28% construction costs - $2.9M • Construction admin. & 72% Measure A management - $900K City of Burlingame • Upgrade of utilities/facilities in roundabout vicinity - $500K

  12. Conceptual Design

  13. Project Schedule DESIGN PHASE October May October January Jan/Feb May 2018 2015 2016 2016 2017 2018 • Begin Construction • 1 st public • 2 nd public • 3 rd public • Design • Advertise outreach outreach outreach Process project for meeting meeting meeting construction • City bids Council 13

  14. Project Schedule CONSTRUCTION PHASE September October 2018 January March 2019 May 2018 Feb 2019 2018 2019 • Stage 3 • Stage 4 • Begin • Stage 4 Construction • Approx. 3 month • Temperatures • Stage 2 • Completing • Postponed • Stage 1 duration above 50 Stage 3 due to rain • Approx. 1 degrees • Major work and freezing • Approx. 4 month • Landscaping, month suspended temperatures duration electrical, duration between Holidays lighting 14

  15. Construction Stage 1 15

  16. Construction Stage 2 16

  17. Construction Stage 3 17

  18. Construction Photos

  19. Completed Project Photos

  20. Construction Challenges • Maintaining access on California Drive • Impacts to adjacent businesses • Educating community during construction, especially when portions of the new alignment opened up in different stages • Weather, as final stage was anticipated during winter • Utility improvements 20

  21. Lessons Learned/Closing Thoughts • Conform roadway grades • Existing Utilities • Construction Manager/Outreach • Constant Communication/Notification 21

  22. Roundabout Informational Video Click to start video

  23. Questions/Comments 23

Recommend


More recommend