may 2015
play

May 2015 13 hydro schemes in Yorkshire area currently ongoing - PowerPoint PPT Presentation

Sam ONeill Telecoms Manager May 2015 13 hydro schemes in Yorkshire area currently ongoing Changes to Feed In Tariff; further reduction prompting a height of activity Limited amount of suitable assets that are viable: Flow and head


  1. Sam O’Neill Telecoms Manager May 2015

  2. • 13 hydro schemes in Yorkshire area currently ongoing • Changes to Feed In Tariff; further reduction prompting a height of activity • Limited amount of suitable assets that are viable: Flow and head height v Access, connection to grid, heritage etc.

  3. • Developer UK Hydro, Planning and EA licence consented • Issues - CRT only own half weir, limited access rights to 2018 • Construction due to commence Summer 2015

  4. • Developer UK Hydro • EA application submitted however, Issue with pollution dilution and depleted reach • Looking at other options rather than Fishponds weir

  5. • Developer Yorkshire Hydro • EA licence consent • Failed planning due to flood risk and visible appearance. Have now reached agreement with EA on how to overcome the flood risk

  6. • Developer UK Hydro • Planning and EA consents, awaiting FPP approval • 3 turbines generating 450kw

  7. • Existing hydro scheme, not on C&RT land • Developer wishes to add another screw and canoe slalom course • EA licence variation submitted

  8. • Developer UK Hydro • Planning and EA licence consent • One Archimedean screw generating100kw • Construction due to commence Summer 2015

  9. • Developer Barn Energy • Kaplan turbine, generating 500kw • Mainly on Wakefield Council land, long access track • EA and Planning consented • Due to start construction Summer 2015

  10. • 50/50 with Greene King (Ship Inn) • Got planning permission awaiting EA consent, due end of May • Small scheme (100kw) but relatively easy build • Due to start construction Autumn 2015

  11. • Started Construction February • Due to complete 11 th September 2015 • Generation approx. 280kw

  12. • Following sites are currently at Pre-app stage, planning & EA: • Horbury Junction, River Calder, 100kw • Knottingley, River Aire, 500kw • Rotherham Weir, River Don, 220kw

Recommend


More recommend