Material Acceptance Requirements for Battery Energy Storage Systems - PowerPoint PPT Presentation

Material Acceptance Requirements for Battery Energy Storage Systems Alan Price, PE Director, Office of Technical Certification and Research NYC Department of Buildings Battery Energy Storage Systems What is a Battery Energy Storage System?


  1. Material Acceptance Requirements for Battery Energy Storage Systems Alan Price, PE Director, Office of Technical Certification and Research NYC Department of Buildings

  2. Battery Energy Storage Systems • What is a Battery Energy Storage System? – A battery energy storage system (battery ESS) stores energy through an electrochemical process for later use to supply the utility or local grids. – Other energy storage systems (ie flywheels) are not addressed in this presentation. • Applications for Battery ESS’s – Uses include peak shaving applications, storage with renewable energy systems, etc. build safe | live safe 2

  3. Battery Safety Concerns Source: DailyMail.com, Philadelphia Airport, February 2006 Source: Aircraft Interiors.com, July 22, 2015 Source: NBC29.com.com, December 14, 2015 build safe | live safe 3

  4. Battery Safety Concerns • Other Safety Concerns: – Ventilation – Explosion – Off Gassing build safe | live safe 4

  5. Code Requirements • Alternative to the Code. Battery ESS’s are alternative systems in accordance with 28-113.2.2. • Material Acceptance. Evaluations are performed under site-specific review only – OTCR2 Site-specific Application – Supporting documentation (checklist) • Applications. Interior and exterior applications build safe | live safe 5

  6. Material Acceptance OTCR Site-specific Review OTCR Site-specific Review Sustainability Material Boards Review* Acceptance FDNY Review* * OTCR Coordinates all reviews build safe | live safe 6

  7. Material Acceptance OTCR Site-specific Review • Site-specific Application. – Applicants submit OTCR2 form. – OTCR Checklist supporting documents • OTCR evaluates safety and performance issues build safe | live safe 7

  8. Material Acceptance OTCR Site-specific Review • Checklist items, including: – Listing certification (UL 1973, UL 1741) – Code Analysis (Ventilation, room separation, fire suppression, etc) – Risk Analysis (address hazard mitigation) – Maintenance procedures – System monitoring – Signage build safe | live safe 8

  9. Material Acceptance FDNY Review • Applicants should contact Technology Management • Review includes Hazmat evaluation build safe | live safe 9

  10. Material Acceptance Sustainability Boards Review • Battery ESS review required by BSB and IRB – BSB/Buildings Sustainability Board (Technical) – IRB/Innovation Review Board (Policy) – Exception: some battery chemistries no longer require BSB/IRB review (VRLA, Lithium-Ion) • Applicant presents at joint BSB/IRB meeting • BSB/IRB issue recommendations build safe | live safe 10

  11. Material Acceptance Criteria OTCR coordinates all evaluations: • OTCR satisfactory evaluation • FDNY Letter of No Objection • Letter of Recommendations from BSB and IRB build safe | live safe 11

  12. Permitting In addition to material acceptance requirements: • Permitting requirements: – Construction permit, if applicable – Electrical permit • Construction document approval/permit issued at the local borough/hub. • Material acceptance is required for project sign-off. build safe | live safe 12

  13. Inspections • Special inspections required – SIA required for applicable installations on the construction permit – TR1 Form completed by SIA build safe | live safe 13

  14. OTCR Contact Info Office of Technical Certification and Research (OTCR) 280 Broadway, 7 th Floor New York, NY 10007 Attn: Alan Price, Director, OTCR otcr@buildings.nyc.gov build safe | live safe 14