LSST System Verification and Commissioning Chuck Claver System Scientist & Commissioning Manager LSST2018 Project & Community Workshop Monday, August 13, 2018 #lsst2018 #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 1
LSST Project Schedule – 8.5 Months Contingency Data Management Final DRP Release Telescope & Site Facility Support Pre Commissioning Preparations Early Integration & Testing Com Cam on Summit Engineering First Light Camera MIE to Ops CD-4 NSF MREFC Full Integration & Verification System First Light +8.5 DOE MIE Schedule Contingency Operational Readiness Review Commissioning Full Operations Pre- Operations Construction Critical Path Full System Science Now Start Integration “Start” Operations Start 8 Dec 2017 #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 2
Verification and Validation Process has Started We are here! Integrate Design Build #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 3
Interface Verification is Underway LSE-80 LSE-64 LSE-18 #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 4
Cam-Tel Utility Interface #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 5
Telescope Top End & Utilities TMA - Camera utility interface Telescope Mount Assembly in Factory Acceptance Testing – completion scheduled for the end of September. #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 6
Early Integration Activities EIA Activities related to Auxiliary Telescope - Key activity of Phase 0: Pre-Commissioning - Involves interaction between all principal subsystem control software Mainly focused on software, but hardware - becoming involved - Performs interface testing - Designed to clarify and solidify those interfaces - Used to identify areas of deficiency and EIA Activities related to Main Camera address those issues - Exercises build on the work of previous ones - Test early, test often! - Reduces verification risk by doing early testing EIA Status Details – Physical & Functional Integration Breakout #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 7
Some Recently Completed Exercises - 1 Visit Night with Images AuxTel • First test of Auxiliary Telescope APIs • Ran through AuxTel nominal visit cadence - Manual Control of Multiple Physical Devices AuxTel First test of hardware control for monochromator • calibration - FITS File Assembly at NCSA • Test for correct image assembly for single CCD - MCM/OCS Bridge Integration Test • Control AuxTel Spectrograph sensor and Dewar to produce images • Tests ACCS, AT Header Service and AT Archiver #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 8
ComCam is coming together This image cannot currently be displayed. This image cannot currently be displayed. Feb. 2019: ComCam Cyostat delivered to Tucson Feb. - July 2019: ComCam Integration and Test Aug. 2019: ComCam ready to ship #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 9
Commissioning Team working with DM on SW Tooling Automated scripted analysis through LSST Science - Tucson based weekly “Stack Club” + periodic Platform JupyterLab interface running at NCSA. “boot camps” with DM, T&S and Commissioning. Example is QA for galaxy identification. - B uilding experience and expertise with data analysis tools - Scripted data analysis tooling with LSST SW Stack - Interactive image analysis tooling - Deployment of early Camera DAQ -CCS instances for cross - subsystem integration tests Interactive image analysis tooling #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 10
LSST Science Platform Comes to Life! Commissioning t eam developing procedures within LSST stack in LSP #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 11
DM SQuaSH Extension for System Verification #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 12
On-Sky Data Planning for Science Validation Critical sky positions where some form of “truth” is known have been identified. #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 13
Commissioning Data Release Policy Early Operations Team will commit to supporting the following: Images from a given commissioning phase will be released aftera 3 - - months following that phase’s conclusion Catalogs will be released 3 - months thereafter - Principal Commissioning Phases Includes: - AuxTel Integration: March 2019 - ComCam- Tel. Integration: July 2020 - LSSTCam- Tel. Integration: September 2020 - ComCam Sustained Observing: October 2020 - LSSTCam Sustained Observing: July 2021 - Operations Readiness mini- Surveys: September 2021 #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 14
Recommend
More recommend