Limerick Landfill Closure Plan PRESENTED TO: MAYOR AND MEMBERS OF COUNCIL, MUNICIPALITY OF SOUTHWEST MIDDLESEX PRESENTED BY: FABIANO GONDIM, M.ENG., P.ENG. May 27, 2020
AGENDA Key Activities Completed to Date Closure Plan Summary Implementation: Landfill Closure Works Ministry’s Approval Summary ___ 2
Key Activities Completed to Date Feb. 2018 - Council’s motion to close the Limerick Landfill Oct. 2018 - Topographic survey completed ___ 3
Key Activities Completed to Date (Cont’d) Nov. 2018 – City staff and Golder met with the Ministry of the Environment, Conservation and Parks (“Ministry”), London District Office to discuss the monitoring program Dec. 2018 - Installation of monitoring wells ___ 4
Key Activities Completed to Date (Cont’d) Jan. 2019 - Groundwater, surface water and methane gas sampling completed by Golder ___ 5
Key Activities Completed to Date (Cont’d) Jan. 2019 - Water samples were analysed by an independent laboratory and results sent to Golder Jun. 2019 - City staff and Golder met with the Ministry’s London District Office to discuss monitoring results and status of the closure plan. Mutual collaboration continued ___ 6
Key Activities Completed to Date (Cont’d) Dec. 2019 - Golder prepared the Closure Plan and submitted to the Ministry for approval (as required by O.Reg. 232/98) May 2020 – Ministry’s approval ___ 7
Closure Plan Summary Report that describes how the site will be closed and managed after closure Detailed description of the surface and subsurface conditions Historical operations Assessment of potential impacts to surface water and groundwater RECOMMENDATIONS Landfill closure works Monitoring program Post-closure inspections and maintenance ___ 8
Implementation: Landfill Closure Works C U R R E N T C O N D I T I O N S , 6 - H E C TA R E ( 1 5 - A C R E ) P R O P E R T Y ___ 9
Implementation: Closure Works (Cont’d) P R O P O S E D - O V E R A 4 - H E C TA R E ( 1 0 - A C R E ) A R E A Applies to ¾ of the site Regrade to improve surface water drainage Apply clay cover Revegetate Complete stormwater management works Other minor works ___ 10
Implementation: Closure Works (Cont’d) C O S T E S T I M AT E $900,000 75 cm (2’6”) thick cover The site does not have available soil for cover construction Soil would be imported Soil type requirement Clay soil to minimize water infiltration, which reduces the potential for landfill impact to groundwater ___ 11
Ministry’s Approval Summary R E Q U I R E M E N T S Requirements for closure works to be completed within 5 years Timing to complete closure works: one construction season and/or phased approach (Municipality’s discretion) Requirements (conditions) consistent with recent approvals for other ON landfills Additional future activities (included in the Ministry’s approval conditions) such as inspections, signage, staff training, nuisance control ___ 12
Thank you. Fabiano Gondim Senior Waste Engineer Golder Associates Ltd. fgondim@golder.com 905-567-4444