liaison group 18 june 2014 shirley kilcullen charging for
play

Liaison Group 18 June 2014 Shirley Kilcullen Charging for - PowerPoint PPT Presentation

Liaison Group 18 June 2014 Shirley Kilcullen Charging for Harmonics What is Connection Charging Recovery of shallow connection asset capital costs associated with customer connections. Focuses on transmission assets required


  1. Liaison Group – 18 June 2014 Shirley Kilcullen Charging for Harmonics

  2. What is Connection Charging • Recovery of “shallow” connection asset capital costs associated with customer connections. • Focuses on transmission assets required up to the meshed system. • Governed by a number of policy documents which set out high level principles for the assigning of costs.

  3. Connection Charging: Basics • Focus on determining causation and drivers of specific works. • Charging applied on an LCC basis. • Assets which are not driven exclusively by a given customer/subgroup are considered “deep” and recovered via TUoS tariffs. • Assets which are driven exclusively by a given customer/subgroup even if considered “deep”, should be paid for by the customer/subgroup. • Rebates - payable where customers connect to assets which were funded by pre-connected parties.

  4. Harmonics issues in a charging context • Per policy, customers should be charged for deeps required to mitigate against harmonic issues arising due to CP UGC. • If harmonic solutions are optimised on a geographic basis, are deep in the system and mitigate harmonics for a number of applicants, assigning causation and apportioning the cost of these solutions within SG’s is v difficult.

  5. Considerations • The charging approach needs to: – Be fair and proportional. – Send a signal about the cost that cable requests impose on the system and inform customer decision making on that basis. – Be relatively simple to apply - not requiring a suite of “charging” power quality studies. – Be robust and enduring - not just solve issues with current Offer Process modifications. – Protect the interests of the TUoS customer.

  6. Options being considered

  7. Option 1: Charge for the actual solution implemented • Actual solution implemented charged in its entirety on the basis of out-turn cost. Pro: • Entirely cost reflective – TUoS fully protected. Pro/Con: • Potential for optimisation but could impose undue inflexibility & cause delays. Cons: • Extremely complex - v difficult to assign causation. • Rebating issues. • In SG, if a party “falls away” – TUoS wouldn’t cover their share of charges for harmonics.

  8. Option 2: Apply a Least Cost approach • Apply an LCC type approach – e.g. std charge for a filter bank at the point of connection to the meshed system where the connection exceeds harmonics limits. Pros: • Consistent with the LCC principle, pay for the lowest cost solution to the problem, regardless of what is ultimately installed. • Charge more predictable. Pro/Con: • Same optimisation considerations as Option 1. Cons: • Same issues as for Option 1. • Potential TUoS exposure.

  9. Option 3: Apply a harmonics levy • Apply a levy on all customer requests for cable on a per km UGC basis. Pros: • Reflects that harmonics issues are cumulative. • Clear & transparent - avoids rebating and SG cost allocation issues. Cons: • Customers that request cable in an area of low underlying harmonics would pay the same as in high areas, unless a “postcode” approach was applied. • € per km levy = a function of a number of variables each of which has potential for inaccuracy. • V difficult to derive an accurate € per km levy without time limits for customer requests for UGC.

  10. Option 4: Recover via TUoS Pros: • Ease of implementation. • Recognises cumulative nature of harmonics issues. • No rebating required or issues with assigning causation. Cons: • Shields customers requesting UGC from full incremental cost. • Totally misaligned with principle of Clause 5.4 of the CMS.

  11. Proposed scope • Apply charging decision – – To all customers who have already been put on notice re this issue via holding statements in their connection agreements and – To all customers who request UGC after the date of publication of the harmonics consultation paper (13/06/14)

  12. Next steps Comments welcome re 4 charging options and any alternatives by 18/07/14

Recommend


More recommend