Large Synoptic Survey Telescope Project Ranpal Gill Head of Communications Getting Ready for LSST: SMW1.4 19 th September 2019 #ranpalgill #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 1
Overview LSST’s mission is to build a well-understood system that provides a vast astronomical dataset for unprecedented discovery of the deep and dynamic universe. #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 2
Large Synoptic Survey Telescope A ground based 8.4m optical telescope Located in Chile on Cerro Pachón Site construction began April 2015 10 year survey starting 2022 Construction budget of US$671,000,000 Total Solar Eclipse over Cerro Pachon, July 2, 2019 Photo: K. Reil LSST/DOE/SLAC #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 3
Four Science Goals #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 5
LSST’s survey will be a 10-year log of half the sky LSST will image the entire Southern sky (18k sq deg) every few nights, taking an image every ~40 seconds, for 10 years. The result: an 825-frame 3.5 degrees movie in 6-filter technicolor of every (Full moon is 0.5 degrees) object present #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 6
To build an observing facility, conduct 10-year survey, process, archive, and serve images and data products Peta-scale Data Management + 8.4m Telescope 7 Science and Public user Interfaces 3.2Gpix Camera #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 7
Mirrors M1M3 Mirror Polishing Completed in 2015 Mirror in Summit Storage May 11, 2019 M2 Optic coated with Science-Grade final coating #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 8
Telescope mount assembly development by Empresarios Agrupados / Asturfeito On the summit since Saturday! #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 9
A Camera to Capture 3.5 degrees of Sky Camera Parameters Property Value 15 years 14.2 o -23.6 o Incident half-angle in air Focal plane diameter 634 mm Maximum mass 3060 kg Maximum diameter 1650 mm Total length 3732 mm #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 10
63 CM Diameter Focal Plane with 3.2 GigaPixels Raft Electronics Board (REB) with Custom Integrated circuits make a 144M Pix Raft camera Sensor Assembly ! e n o t s e l i M 189 sensors packed in 21 4K x 4K rafts of 9 sensors Science Sensor #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 11
Filter Exchange Systems − Collaboration with IN2P3 labs in France for key Camera elements − Filter Autochanger, Manual loader (6 th filter) and carousel completed & being tested Filter loader on Filter Autochamber Shutter prototype transport cart 5 Filter capacity carousel #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 12
Science themes Online investigations for formal education. • Surveying the Solar System : Students make observations of newly-discovered solar system objects using an orbit visualizer to determine the object type. • Hazardous Asteroids : Students evaluate the potential threat of an Earth impact by making repeated observations of a newly- discovered Near-Earth Object. #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 13
Data Product Categories #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 14
Data Rights & Data Access − Alert stream immediately public (60 seconds after observation) − Small bodies data -> Minor Planet Center (MPC) − All data public after two years − Data rights for in-kind contributors: – Funding agencies (NSF and DOE) have committed to fully support LSST operations BUT have given guidance to LSST to seek international partners. • LSST has produced high level models/menu of options for in-kind operations offsets . • Host of “really good to have” added value options being considered #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 15
Large Synoptic Survey Telescope (LSST) Status 2019 September 2012 Rendering #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 16
Project & Community 2019 10-14 August 2020 in Tucson! Next meeting: Come along! #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 17
On schedule for First Light in 2021 and start of 10-year Survey in 2022 Overview #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 18
Keep in touch with us! Subscribe to our “Newsletter” communications-team@lists.lsst.org @myLSST lsst-digest-join@lists.lsst.org Send blank email to: @lsst lsst_astronomy http://ls.st/z6u large-synoptic-survey-telescope-lsst- www.lsst.org community.lsst.org #ranpalgill EPSC-DPS Joint Meeting 2019 • Geneva, Switzerland • 19 September, 2019 19