GLAST LAT Project GLAST Large Area Telescope: GLAST Large Area Telescope: Face to Face Managers Meeting Face to Face Managers Meeting Gamma- -ray Large ray Large Gamma I&T Readiness and Plans I&T Readiness and Plans Area Space Area Space August 11, 2004 August 11, 2004 Telescope Telescope Ken Fouts Ken Fouts Manager, I&T Engineering Manager, I&T Engineering SLAC SLAC 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 1
GLAST LAT Project LAT I&T Organization LAT I&T Organization 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 2
GLAST LAT Project Recent Accomplishments Recent Accomplishments • Management – Held 2 document reviews with NASA I&T. 12 I&T documents and procedures in approval cycle. • IFCT – JPL crimping training completed for two I&T mechanical technicians. – JPL connector mate/demate instructor training completed by I&T technician. – CAL metrology bay shimming training completed. • MGSE – 267 MGSE drawings complete or in final release cycle, 20 to go. 4x4 proof test weights are cut to size and are in final machining. – • Online – First online CCB meeting was held and action items established. – Held IRR peer reviews for Online (go to I&T website for details) – LATTE V 4.0 released upgrade for housekeeping. • SVAC – Held IRR Peer Reviews for SVAC (go to I&T website for details) • Particle Test Rebuilt Van de Graaff accelerator column – 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 3
GLAST LAT Project IFCT Organization IFCT Organization 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 4
GLAST LAT Project Facility Utility / Computing Infrastructure Facility Utility / Computing Infrastructure Facility utilities: • Building 33 power substation - ECD 4-Oct-04 • Building 33 backup generators – ECD 13-Aug-04 • Building 33 backup hot water boiler – ECD 30-Nov-04 • Building 37 Transfer switch – ECD 30-Sep-04 Computing infrastructure: � Firewall w/ private LANs for monitoring, online, data transfer. • SCS remote tape backup for monitoring system database 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 5
GLAST LAT Project Room 104 Clean Room Configuration Room 104 Clean Room Configuration • Draft Procedure available in LATDOCS. (LAT-DS-03281) • Some graphics improvements in work. • Space in room 104 is tight with limited parallel processing space available. – Only enough space for the LAT integration stand or the LAT Mock-up stand at one time. – Metrology bay must be moved out of room for ACD and X LAT plate installation. – LAT integration stand must be moved if rework of ACD required. – Unused MGSE must be stored outside room 104 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 6
GLAST LAT Project I&T Mechanical Training I&T Mechanical Training 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 7
GLAST LAT Project IFCT Electrical Training IFCT Electrical Training 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 8
GLAST LAT Project Summary and Concerns Summary and Concerns LAT I&T procedures (45 total) • 1 released • 30 procedures drafted and in review Training • Mechanical training 50% complete • Electrical training 20% complete Facility Ready for installation and test of EM2, flight grid, MGSE • Assembly, Online/EGSE. 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 9
GLAST LAT Project MGSE Readiness MGSE Readiness 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 10
GLAST LAT Project Drawing Release Plan & Status required to achieve production milestones Drawing Release Plan & Status required to achieve production mil estones • Total MGSE Drawing Sheet Count ~ 287 – 141 Drawing Sheets Released – 94 Drawing Sheets released on July 16 – 32 drawing Sheets in Release Cycle by July 30 – 267 Drawing Sheets Virtually Released • ( 141 + 94 + 32 = 267 ) – 20 sheets scheduled to be complete by Aug 30. – 1x4 Grid Update on Stop Work 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 11
GLAST LAT Project Online Readiness Online Readiness 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 12
GLAST LAT Project Roadmap Roadmap • LAT-TD-03075 Document written and agreed to February 2004 • Status of required elements follows • § 7 – Bonus items are not addressed • § 8 – Subsystem support is never ending 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 13
GLAST LAT Project 6.1 – – GASU GASU 6.1 � 6.1.1 – Trigger API � 6.1.2 – ACD script migration � 6.1.3 – EBF (now called LDF) package update • New request � ACD software counters 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 14
GLAST LAT Project 6.2 – – Hardware monitoring system Hardware monitoring system 6.2 • Development started by ELX for Test-bed needs FSW is developing a housekeeping telemetry server • � Released. Online needs training. • HskSvr usage will fit seamlessly into ELX monitor • Online is adding – Alarming – Alerting – Archiving – Trending LATTE 4.x preliminary version running in B33 for EM2. LATTE 4.x preliminary version running in B33 for EM2. 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 15
GLAST LAT Project 6.4 – – Event Event prescaling prescaling in in VxWorks VxWorks 6.4 • Needed to manage nominal or higher trigger rate testing � Completed However, new request: • Simple event data filtering – Requires FSW support � Delivery 15 August, 2004 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 16
GLAST LAT Project 6.5 – – Subsystem scripts Subsystem scripts 6.5 • Official deliveries needed prior to V&V phase • None yet received • Development snapshots stored in CVS • Online gaining experience with these snapshots • E2E scripts in progress (Lester, trigger group) 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 17
GLAST LAT Project 6.6 – – Security against unauthorized software changes Security against unauthorized software changes 6.6 • In the I&T testing phase (not commissioning phase), protection is needed against on-the-fly editing of code and configurations as the changes can’t reliably be tracked � Run reports indicate mismatches with released files � Kiosk mode � Read-only source files Available in LATTE 4.x and is being exercised in B33 during EM2 testing. Available in LATTE 4.x and is being exercised in B33 during EM2 testing. 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 18
GLAST LAT Project 6.7 – – Security against operator complacency Security against operator complacency 6.7 � Permission scheme set up � Operator authentication � Certain features are enabled or disabled according to operator permission level � Normally disabled for backward compatibility (e.g. during commissioning) � Core system modified to use it – Test scripts must use it for it to be effective • Operators must sign off on input parameters – Test scripts must use it for it to be effective. In Progress 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 19
GLAST LAT Project 6.9 – – Building 33 EGSE room 102 set Building 33 EGSE room 102 set- -up (1) up (1) 6.9 • Taken over by IFCT � Two PCs set up with four six (6) monitors • Online needs to practice in situ. In Progress on EM2 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 20
GLAST LAT Project 6.9 – – Building 33 EGSE room 102 set Building 33 EGSE room 102 set- -up (2) up (2) 6.9 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 21
GLAST LAT Project 6.10 – – Release mechanism for subsystem test Release mechanism for subsystem test 6.10 scripts to I&T scripts to I&T � Plan completed – Transfer scripts via CVS tag • New request: – Transfer scripts by DVD 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 22
GLAST LAT Project 6.11 – – Electronic logbook Electronic logbook 6.11 � Web based version completed (Oracle) � Stand-alone version completed (MySQL) • DB synchronization program still needed • New requests � Mate/Demate GUI changes – Component installation log – Software installation log – Configuration log Log book requirements to be documented by I&T. Log book requirements to be documented by I&T. 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 23
GLAST LAT Project 6.13 – – Validation & verification (1) Validation & verification (1) 6.13 • Subsystem test-stands – Many instances ( ~40 ) – Many hours of operation – Many people involved, each with a different approach • EM-1 and EM-2 tests with mini-tower – More complete with hand-off of persistent data to SVAC – But, less seat time and consequently less practiced • Full tower testing (no detectors) • Test-bed testing – In progress in ELX with LATTE 4.x – Hardware not yet fully functional • Standalone mode testing – Useful for developing code not requiring hardware interaction 4.1.9 - Integration and Test 11 Aug 04 Face to Face Meeting 24
Recommend
More recommend