Lao Mekong Pak Beng Hydropower Project Table of content Project - - PowerPoint PPT Presentation

lao mekong pak beng hydropower project table of content
SMART_READER_LITE
LIVE PREVIEW

Lao Mekong Pak Beng Hydropower Project Table of content Project - - PowerPoint PPT Presentation

Lao Mekong Pak Beng Hydropower Project Table of content Project Brief Hydrology Sedimentation Geology and exploration Design Layout Dam safety Fish Pass facility Navigation Water quality Sustainable Operation


slide-1
SLIDE 1

Lao Mekong Pak Beng Hydropower Project

slide-2
SLIDE 2

2

Table of content

  • Project Brief
  • Hydrology
  • Sedimentation
  • Geology and exploration
  • Design Layout
  • Dam safety
  • Fish Pass facility
  • Navigation
  • Water quality
  • Sustainable Operation and Management
slide-3
SLIDE 3

3

Project Brief

CHARACTERISTIC OF PROJECT INSTALLED CAPACITY 912 MW NUMBER OF UNITS 16 AVERAGE ANNUAL OUTPUT 47.65x108 KWh ANNUAL OPERATING HOURS 5225 h TONNAGE OF SHIP LOCK 500t

slide-4
SLIDE 4

Project Brief

August 2007

  • MOU signed

December 2008

  • FS Report (FSL 345m, installed capacity 1230MW)

December 2012

  • PDA signed

March 2014

  • ESIA approved by GOL

July 2014

  • FS Report (FSL 340m, installed capacity 912MW)
slide-5
SLIDE 5

5

2 Hydrology

slide-6
SLIDE 6

Analysis of natural geography

Data collect

Meteorological data Hydrological data Data assessment Hydrology survey Analysis Climate condition Runoff characteristic Flood characteristic …….

Hydrology

calculate

Meteorological elements Runoff Design Flood Rating curve ……

slide-7
SLIDE 7

Hydrology

slide-8
SLIDE 8

Station Area(km2) Stage Flow Chiang Saen 189,000 1960-2014 1960-2014 Sop Kok 201,000 1972-1987 1972-1987 Chiang Khong 204,000 1972-2014 Pak Beng 218,000 1976-1981、1985、 1989-1990、1992- 1993、1999- 2006,2008-2014 2008-2014 Laungprabang 268,000 1960-2014 1960-2014

Hydrol rologi

  • gica

cal data avai aila labl ble e

Hydrology

slide-9
SLIDE 9

Gauge Station A Gauge Station B Gauge Station D Gauge Station C Discharge Measurement

300 305 310 315 320 325 1000 2000 3000 4000 5000 6000 7000 8000 H(m) Discharge(m3/s) Dischareg Measured in 2008 Discharge Measured in 2009 Discharge Measured in 2010 Discharge Measured in 2011 Dischareg Measured in 2012 Discharge Measured in 2013 Discharge Measured in 2014

Hydrology

slide-10
SLIDE 10

Measure discharge and water level longitudinal and cross section

Hydrology

  • Rating Curve
295 300 305 310 315 320 325 330 335 340 345 5000 10000 15000 20000 25000 30000 35000 H(m) Discharge(m3/s) Rating Curve at D Gauge Station Discharge Measured in 2008 Discharge Measured in 2009 Discharge Measure in 2010 Discharge Measured in 2011 Discharge Measured in 2012 Discharge Measured in 2013 Discharge Measured in 2014 300 305 310 315 320 325 330 335 340 345 5000 10000 15000 20000 25000 30000 35000 流量(m3/s) 水 位 (m)

Hydraulic

formula

Rating curve

Rating curve of Gauge station D Rating curve of dam site

slide-11
SLIDE 11

11

3 Sedimentation

slide-12
SLIDE 12

12

Sediment

  • Sedim

iment ent inve vest stig igati ation

  • n

KHIDI have carried out sediment investigation from Yunjinghong to Luang Prabang hydrological station, river diagram shows in the picture.

slide-13
SLIDE 13

13

Sediment

Main stream Branches Drainage area (km2) Referenced sediment transport modulus (t/km2.a) Adopted sediment transport modulus (t/km2.a) Yunjinghong - Pakbeng Intervals of Damsite (t/km2.a) Yunjinghong 149100 726 726 Nanban River 7679 747 750 350 Exit of Lancang River (Guanlei) 163000 250 Chiang Saen 189000 300~500 Nam Ing River 9750 53 Namtha River 8990 156 Pakbeng Damsite 218000 Nam OU River (Muong Ngoy) 19258 233

  • Sedim

iment ent inve vest stig igati ation

  • n
slide-14
SLIDE 14

14

Sediment

Sediment data of hydrological station Sediment investigation of mainstream and tributaries Data assessment WsJing Ms Calculated formula of Sediment amount of Pak Beng Dam Site Sediment Amount

  • Sediment Amount at the Dam site

Suspended load: 142.68×106t Bed Load: 4.28×106t Suspended load: 37.99×106t Bed Load: 1.034×106t Natural condition Consider US dam

slide-15
SLIDE 15

15

Sediment

  • Sediment sampling

Suspended load Bed load

slide-16
SLIDE 16

16

Sediment

  • Sediment Deposition

Siltation Period (Year) Incoming Sediment (106t) Siltation Amount (106t) Sediment Delivery Rate (%) Losing Rate of Storage below Normal Water Level (%) Losing Rate of Effective Storage (%) 5 195 42 78.59 5.15 0.49 10 390 81 79.22 9.77 1.23 15 585 117 80.03 13.87 2.11 20 780 148 81.07 17.35 3.05 30 1171 191 83.66 22.15 4.72 40 1561 224 85.64 25.72 6.06 50 1951 252 87.10 28.62 7.16 60 2341 272 88.36 30.77 8.07 70 2732 224 89.48 32.21 8.73 80 3122 298 90.44 33.27 9.30 90 3511 307 91.26 34.06 9.80 100 3901 314 91.95 34.69 10.24

slide-17
SLIDE 17

17

Sediment

  • Sediment Deposition

This shows the siltation thickness changes. Siltation thickness in front

  • f the dam increase year by

year when the power station putting into

  • peration.
slide-18
SLIDE 18

18

Sediment

  • Sediment Flushing

In order verify the flushing effect of the discharging sluicing gates, we simulate the Siltation thickness changes in the front of the dam before and after the gates open.

Plant operation for 5 years before discharging gates open Plant operation for 5 years after discharging gates open

slide-19
SLIDE 19

19

Sediment

  • Model test

Sediment before discharge sluices Sediment before powerhouse

slide-20
SLIDE 20

20

Sediment

  • Reservoir Operation Mode
slide-21
SLIDE 21

21

4 Geology and exploration

slide-22
SLIDE 22

22

Geology and exploration

No. Earthquake time Place name Magnitude Earthquake intensity in the project area 1 19251222 Laos 6.8 Ⅴ 2 19340212 West Laos 6 Ⅶ 3 19350513 At the border between Thailand and Laos 6.5 Ⅶ 4 19370921 Northwest Laos 6 Ⅴ 5 19961221 Thailand 5.6 Ⅴ 6 20000119 Laos 5.8 Ⅴ 7 20000331 Laos 5.4 Ⅴ 8 20070516 Vieng Phoukha, Laos 6.6 Ⅵ 9 20110324 Northeastern Myanmar 6.8 Ⅴ

Catalogue of Strong Earthquakes with Intensity ≥V Degree Occurred in the Project Area

  • Earthquake safety
slide-23
SLIDE 23

Earthquake

500 Km Orange area corresponds to Severe zone Yellow area corresponds to Middle zone Green area corresponds to Moderate zone water and blue area corresponds to Minor zone Nam Ngum 0.03 (Moderate Zone) Nam Leuk 0.10 (Moderate Zone) From the above maps, Source : International Seismological Centre (U.K.)

slide-24
SLIDE 24

Geology and exploration

24

Designed seismic dynamic parameter 50-year exceeding probability 100-year exceeding probability 10% 5% 2% Amax (gal) 154 209 365 β 2.0 2.0 2.0 Tg (sec) 0.25 0.25 0.25 ah (g) 0.157 0.213 0.372

Seismic Dynamic Parameter Values

  • f Bedrock in the Project Area
  • Earthquake safety
slide-25
SLIDE 25

Geology and exploration

25

  • Exploration (Rock mechanics test)
slide-26
SLIDE 26

Geology and exploration

26

  • Exploration (Drill core)
slide-27
SLIDE 27

27

lock discharge sluice powerhouse Fish way

Design Layout

Project Layout

slide-28
SLIDE 28

28

Design Layout

Number of Units 16 Type of unit bulb Unit capacity 57MW Total capacity 912MW Height of plant 64m Length of plant 410m

  • Powerhouse
slide-29
SLIDE 29

29

Design Layout

  • Discharge sluices

Number of sluices 14 Type of weir broad-crested Size of gates 15m×23m Elevation of weir 317m Energy dissipation hydraulic jump Operation opened and closed in dynamic water

slide-30
SLIDE 30

30

Design Layout

Number of steps 1

  • Max. tonnage 500t
  • Max. working head 32.38m

Size of chamber 120m×12m×4m Total tonnage 1.5×106 t/year

  • Ship lock
slide-31
SLIDE 31

31

Design Layout

  • Fish way

Length 1.6km Slope 1.85% Width 10m

slide-32
SLIDE 32

32

  • Safe passage of flood

Flood Release Structures

8 sand outlets, size 2.5m×5m 14 sand outlets, size 15m×23m

Check flood 30200m3/s

Design flood 26800m3/s

Dam safety

slide-33
SLIDE 33

33

Dam safety(Construction)

  • Cofferdam safety

First-Stage Diversion Structures

include dry season cofferdam, longitudinal concrete cofferdam and R/B upstream and downstream transversal cofferdams .  protection against 20 years return period flood with discharge of 18,700 m3 / s

Construction period of First stage

foundation is 33 months, ranging from January of the Second year to December of the fourth year.

slide-34
SLIDE 34

34

Dam safety(Construction)

  • Cofferdam safety

Second-Stage Diversion Structures

include longitudinal concrete cofferdam ,L/B upstream and downstream transversal cofferdams

 protection against 50 years return

period flood with discharge of 21,100 m3 / s

Construction period of Second stage

foundation is 33 months, ranging from December of the fourth year to August

  • f the seventh year.
slide-35
SLIDE 35

35

Dam safety(Construction)

  • The slop Stability and seepage

stability of the first-stage and the second stage cofferdam have been

  • calculated. The results show that

they can meet the specification requirements.

USACE Slope Stability EM_1110-2-1902

  • Cofferdam safety
slide-36
SLIDE 36

36

7 Fish Pass facility

slide-37
SLIDE 37

37

Fish Pass facility

6 stations for survey, sampling and

  • bservation
  • Fish investigation

Ban Hom Xai Keng lae Ban Luang Tong Pak Beng Dam site Ban Pak Ngua Houay Kan

slide-38
SLIDE 38

38

Fish Pass facility

target fish Fish habits investigatio n

Upstream and downstream migration design

Monitoring

2 3 4 5

Fish investigatio n

1

  • Design Principle
slide-39
SLIDE 39

39

Fish Pass facility

  • Design Consideration( Upstream migration)

Fish way Navigation lock( part)

slide-40
SLIDE 40

40

Fish Pass facility

  • Design Consideration(Downstream migration)

Fish way Navigation lock (part) Sluice gate(flood season) Fish Friendly turbine

Certain size of fish can pass the turbine

slide-41
SLIDE 41

41

Fish Pass facility

Exit 2 Exit 1 Monitoring room Entrance Width :10m; Discharge flow:15~20m3/s Maximum length of fish :0.5m~0.6m

  • Design Consideration

Lure fish facility Automatic system

slide-42
SLIDE 42

Built bypass channel fish way on the world

42

Fish Pass facility

slide-43
SLIDE 43

43

8 Navigation

slide-44
SLIDE 44

44

Navigation

Based on complete hydrology data(1960→2014)and physical

experiments

Comparing different country’s standard to choose safe design

reference

Successful experience

  • Safety Design Consideration
slide-45
SLIDE 45

45

Navigation

Based on complete hydrology data(1960→2014)

  • Safety Design Consideration

Assurance rate Flow (m3/s) Water level (m) Head difference(m) P=95% 1630 309.29 30.71 P=98% 1260 307.62 32.38

slide-46
SLIDE 46

46

9 Water Quality

slide-47
SLIDE 47

47

Water quality

  • The status quo

After the detailed indoor work,

we conduct the water quality sampling.

Based on the lab results, the

surface water’s quality is as good as classes three.

St.1 Represent upstream area, at Ban Hom Xai , 2198405N,0677224E

  • St2. Represent upstream area, at Keng Lae, 2200078 N, 0696791 E

St.3 Represent upstream area, at Ban Lang Tong , 2199461N, 0701673 E St.4 Proposed dam site area, Don Thek , Ban Pak Gnei 2195623N, 0708542 E St.5 Downstream area, Houay Kan (Pak Kan). 2195317N, 0716325E. St.6 Downstream area, Pak Beng town . 2200813N, 0722957E.

Sampling Station

slide-48
SLIDE 48

48

Water quality

  • Untreated wastewater and sewage will change the water quality index such

as PH, SS, BOD, COD, Oil and so on in the surface water, which will affect the water quality.

slide-49
SLIDE 49

49

Water er qual ality ity Mitig igation tion Measure ure

  • Mitigation Measures

Water treatment Reservoir bottom clearing

slide-50
SLIDE 50

50

11 Sustainable Operation and Management

slide-51
SLIDE 51

Sustainable Operation and Management(Hydrology)

Storm characteristic Forecast Scheme in construction &

  • peration

Main tributaries distribution Network Flood characteristic Hydropower characteristic Sensible factors …… Forecasting Water Level Discharge

  • Automatic system of hydrologic data collection and transmission
slide-52
SLIDE 52

52

  • Sediment Monitoring System

Sediment Monitoring System Water and sediment in/out the reservoir Water surface line of the front dam and tail section Sedimentation in the reservoir area Sedimentation in the project area Before the Dam In approach channel Downstream river course Bank deformation in the reservoir area

Sustainable Operation and Management(Sedimentation)

slide-53
SLIDE 53

Single beam sounding system Multi beam sounding system

Underwater data acquisition

53

  • Sediment Monitoring equipment

Sustainable Operation and Management(Sedimentation)

slide-54
SLIDE 54

54

Sustainable Operation and Management(Sedimentation)

  • Sediment management Brochure

Sedimen ment t managemen gement t Sediment releasing facilities of the power station Reservoir operating modes Control of the reservoir sedimentation Sedimentation control before the dam Sediment deposition in the approach channel Downstream channel scouring Bank erosion Eco-friendly flushing Monitoring and management

slide-55
SLIDE 55

55

Sustainable Operation and Management(Monitoring)

Monitoring system maintenance Automatic monitoring Data compilation Data analysis Working state evaluation

slide-56
SLIDE 56

56

Organization chart

Sustainable Operation and Management(Environmental management)

slide-57
SLIDE 57

Louangtong 47 Households 232People Homxai 18 Households 126People Houay Chiko 12 Households 84People Houay Khoun 4 Households 28People Houay Moong 12 Households 72People Pak Khob 21 Households 132People Pak Xo 18 Households 120People Kiengphaak 17 Households 102People Hatdonkeo 19 Households 114People Damsite

THE FIRST STA THE FIRST STAGE GE START: JAN IN START: JAN IN THE FIRST YE THE FIRST YEAR AR COMPLETE : D COMPLETE : DECEMBER IN TH ECEMBER IN THE SECOND YEAR E SECOND YEAR NUMBERS:93 HO NUMBERS:93 HOUSEHOLDS 542 USEHOLDS 542 PEOPLE PEOPLE THE SECOND ST THE SECOND STAGE AGE START: JAN IN START: JAN IN THE THIRD YE THE THIRD YEAR AR COMPLETE: OC COMPLETE: OCTOBER IN THE TOBER IN THE FOURTH YEAR FOURTH YEAR NUMBERS:75 HO NUMBERS:75 HOUSEHOLDS 468 USEHOLDS 468 PEOPLE PEOPLE

THE SK SKETC TCH M MAP OF OF RE RESSE SETTLEM EMENT NT PR PROCESS SS FO FOR P PAK PE PENG G HPP PP

slide-58
SLIDE 58

58

  • Resettlement

condition in Nam Ou river (designed by KD)

Sustainable Operation and Management (resettlement)

slide-59
SLIDE 59

59

Thank you for your attention!