Lake Trafford Substation Construction Phase Two
Phase Two to include: • Ground grid
Ground Grid • 12,500’ of 4/0 copper • 515 ground rods • 1,407 exothermic welds
Phase Two to include: • Ground grid • Cabling
Cabling • 272’ of Trenwa • 3,400’ of 2” conduit • Over 21,000’ control cable
Phase Two to include: • Ground grid • Cabling • Concrete
Caissons and Pads • 43 caissons 714 cu. yds. of concrete • 7 pads 45 cu. yds. of concrete
Phase Two to include: • Ground grid • Cabling • Concrete • High-side breakers and bus
138kv Breakers and Bus • 4 - 138kv breakers • 580’ of 4” Al bus • 7 - 138kv disconnects • 14 bus-support structures
Phase Two to include: • Ground grid • Cabling • Concrete • High-side breakers and bus • 138kv capacitor bank
Capacitor Bank
Bid Results PowerTown Line Construction Tampa, FL $309,478.69 McLaren Construction Company West Palm Beach, FL -- Elite Construction of Ocala Ocala, FL -- Aubrey Silvey Carrollton, GA -- Kent Power Kent, MI -- Service Electric Company Chattanooga, TN --
PowerTown – LCEC Projects • Neutral grounding reactor (NGR) foundations – 2014 • Carnestown circuit addition – 2013 • North Trail below grade – 2013 • Carnestown transformer changeout – 2011 • Del Prado expansion – 2010
Action Requested We are requesting a motion to authorize the CEO to sign a contract with PowerTown Line Construction, LLC, for $309,478.69.