Kirkman Road Update April 2018
Project Overview 21 miles in Orange and Seminole From Kirkman Road to SR 434 Complete reconstruction of existing lanes 15 major interchanges More than 140 bridges New pedestrian Bridges at Maitland Blvd, Kirkman Rd & Lake Lucerne SR 436 Pedestrian Tunnel Increase posted speed 55-60 mph 4 Express Lanes
Kirkman Road Interchange
Kirkman Road Interchange
Kirkman Road Interchange More traditional right hand exit ramps Grand National Drive overpass relieves east/west congestion at the Kirkman Road exits Direct Express Lane Connection eastbound onto I-4 and from westbound to Grand National Drive Additional ramps constructed but not opened for future expansion
Kirkman Pedestrian Bridge
Kirkman Pedestrian Bridge
Kirkman Pedestrian Bridge
Kirkman Pedestrian Bridge
Remaining Work Concrete supports Concrete ramps Place steel bridge structure Pour concrete deck Anticipated completion Fall 2018
Post Construction Aesthetics
Post Construction Aesthetics
Good Neighbor Outreach • Created and distributed 200 handouts at 2 traveling displays at Universal Studios • 27 posters established nearby – 14 hotels – Orlando Premium Outlets – Orlando Fire Station 10 – Lexus of Orlando – Starbucks
Digital Outreach • Kirkman Rd. database expanded to include Sand Lake Rd. contacts (total of 289 recipients of digital content) • Daily tweets scheduled – This week and next week – Shared with social media partners
Other content • Closure handout • News release • Lead article in February I-4 Ultimate newsletter
I4ultimate.com
Construction Map Planned Alerts Overnight Detours Live Construction & Traffic Cameras Construction Progress Photos Real Time Congestion & Crashes
Alert Notification I4Ultimate.com/Signup Advanced Alerts Twitter YouTube Monthly Newsletter Newsfeed
What’s Next?
Questions? David Parks Public Information Officer DavidParks@I4Ultimate.com 1.844.ULT.INFO (858.4636)