KEKB / SuperKEKB The Luminosity Frontier (number of events/unit time) = (cross section) X (luminosity) Katsunobu Oide (KEK) April 17, 2006 @ CERN http://kekb.jp
KEKB = Asymmetric Double-Ring Collider for B-Physics 8 GeV Electron + 3.5 GeV Positron Superconducting cavities (HER) 1989: Design work started. Belle detector 1994: Approval of the budget, e- construction started. June 1995: KEKB Design Report KEKB B-Factory e+ Sep. 1997: Commissioning of the injector Linac started. ARES copper Dec. 1998: First beam at HER. cavities (HER) Jan. 1999: First beam at LER. May 1999: Belle roll-in. ARES copper June 1999: First event at Belle. cavities (LER) Apr. 2001: World record of the TRISTAN luminosity, 3.4 /nb/s. tunnel Oct. 2002: World record of the integrated luminosity, 100 /fb. May 2003: Exceeded the design 8 GeV e- luminosity, 10 /nb/s. 3.5 GeV e+ Linac Feb. 2004: Exceeded 12 /nb/s & 200 /fb. e+ target Oct. 2004: 13.9 /nb/s & 300 /fb. May 2005: 15.3 /nb/s & 420 /fb. Dec. 2005: 16.3 /nb/s & 528 /fb. … continues rewriting own records …
Nikko Mt. Tsukuba Belle KEKB Rings KEK Site Linac
10 34 cm -2 s -1 600 /pb/day Achieved >500 /fb in 6.5 years. (Initial Goal: 100 /fb in 3 years.)
10 34 The best 24 hours > 1.2 /fb
54 /fb/mo Next Milestone We are here 27 /fb/mo. Crab Cavity Beam Test
SuperKEKB, The Next Step 10 36 10 36 Luminosity (cm -2 s -1 ) SuperKEKB 10 35 10 35 Integrated Luminosity KEKB design KEKB ILC PEP-II 10 34 10 34 CESR 10 33 10 33 Data doubling time LEP-II DAFNE 10 32 10 32 PEP TRISTAN DORIS BEPC LEP 10 31 10 31 PETRA VEPP-2M VEPP-4M SPEAR 10 30 10 30 ADONE 2 2 3 3 1 1 10 10 10 10 10 10 Shutdown for upgrade CMS Energy (GeV) • SuperKEKB is a natural extension of KEKB, the world leader in the luminosity frontier. • 8 × 10 35 cm -2 s -1 will be available with technologies proven at KEKB, together with a few modifications.
β * y = σ z = 3 mm Crab cavities will be SuperKEKB installed and tested with e- 9.4 A beam in 2006. e+ 4.1 A The state-of-art ARES The superconducting cavities will be copper cavities will be upgraded to absorb more higher-order upgraded with higher mode power up to 50 kW. energy storage ratio to support higher current. * I ± ξ ± y 1 + σ y R L L = γ ± * * 2 er R y σ x β y e The beam pipes and all vacuum components will be replaced with will reach 8 × 10 35 cm -2 s -1 . higher-current-proof design.
Three factors to determine luminosity: Stored current: Beam-beam parameter: 1.36/1.75 A (KEKB) 0.059 (KEKB) → 4.1/9.4 A (SuperKEKB) → >0.24 (SuperKEKB) Lorentz factor * I ± ξ ± y 1 + σ y R L L = γ ± * * 2 er R y σ x β y e Geometrical reduction factors due to crossing angle and hour-glass e fg ect Classical electron radius Beam size ratio Vertical β at the IP: Luminosity: 6.5/5.9 mm (KEKB) 0.16 × 10 35 cm -2 s -1 (KEKB) → 3.0/3.0 mm (SuperKEKB) 8 × 10 35 cm -2 s -1 (SuperKEKB)
New Parameter Set for 8 × 10 35 -- by K. Ohmi • Good parameters are not yet found with crab waist. 10
Why was higher luminosity made possible? • 8 × 10 35 cm -2 s -1 is achievable with same beam currents, beta, bunch length as 4 × 10 35 cm -2 s -1 . • The simulation was improved by more longitudinal slices to reduce the numerical noises and the instability, using a new supercomputer at KEK. • A new choice of parameters with smaller emittance ratio or smaller horizontal emittance. • Crab crossing is necessary. • No crab waist, travel focus are needed for luminosity, but may help the lifetime. 11
Increase number of longitudinal slices in the simulation ε x =18nm, ε y =0.09nm, β x =0.2m β y =3mm σ z =3mm Lower coupling gives higher luminosity, but numerical instability occurs with less number of slices. K. Ohmi 5 slices 10 slices
Smaller emittances K. Ohmi 1e+36 8e+35 10 slice 6e+35 L 4e+35 2e+35 ex=9nm 0 0 0.02 0.04 0.06 0.08 0.1 ey (nm) ex = 18 nm ex = 9 nm • For ex = 18 nm, smaller ey gives higher luminosity. • For ex = 9 nm, luminosity is high up to ey/ex < 1%.
Traveling waist • Particles with z collide with central part of another beam. Hour glass effect still exists for each K. Ohmi particles with z. • No big gain in Luminosity. ε x =24 nm ε y =0.18nm • Life time is improved. β x=0.2m β y =1mm σ z=3mm
Traveling of positron beam K. Ohmi
SuperKEKB R&D • Crab cavities • Vacuum components for high current: antechambers, coating, bellows, collimators, etc. • Superconducting quadrupole • High power RF components • Bunch-by-bunch feedback • C-band linac • Beam diagnostics
Crab crossing is coming soon @ KEKB! Crab crossing will boost the beam-beam parameter up to 0.19! K. Ohmi Head-on(crab) (Strong-strong simulation) crossing angle 30 mrad (at the optimum tune) Superconducting crab cavities are under development, and will be installed in KEKB in 2006 . Input Coupler I.R. 90 I.D. 120 I.D. 240 I.D. 188 I.R.241.5 Coaxial Coupler 866 I.R. 20 I.D. 30 Monitor Port 100 150 0 50 483 scale (cm) K. Hosoyama, et al
Crab cavity He jacket
Cryostat & couplers Input coupler was conditioned successfully. K. Hosoyama, et al
1. Beam Duct with Ante-chambers Beam duct with two antechambers (2005) Model: for wiggler section OFC( t 6), w 224, h 94, L 4.7 m Fabrication methods: Forming (from plates) Manufacturing was successful. Degree of accuracy should be Forming improved in future Inside view Final check 2006/3/21 2006 KEKB Review 20
2. Bellows Chamber and Gate Valve Application of Ver.2 to antechamber-type bellows Manufactured at BINP (2005) Copper cooling channel Improve cooling of teeth Two bellows chamber were installed into LER wiggler (2005). No problem was found up to 1.7 A. 2006/3/21 2006 KEKB Review 21
3. Vacuum Flange Application to bellows chamber and ducts (2005) MO-flange was applied to beam duct with ante-chambers and their bellows chambers, and installed into LER. No problem was found up to 1.7 A. Temperature of bellows was almost same to conventional ones (circular). ~30 ° C . SS flange Bellows chamber Cu gasket MO-type flange for beam duct with MO-type flange for bellows chamber antechambers for wiggler section 2006/3/21 2006 KEKB Review 22
4. Movable Mask Stealth type Ver.4 at present Has been studied since 2003 Features Ceramics support Little interference with beam Carbon head Head (C) Little damage by beam With HOM absorber (SiC) SiC R&D points (still preliminary) Trapped mode SiC Heating of head Charge up Support (ceramics) Beam Experimental demonstration Beam duct 2006/3/21 2006 KEKB Review 23
LC との連携(2)(加藤) In-situ Measurement System of Secondary Electron Yields at Positron Ring of the KEKB <Features> ★ In-situ Measurements of Secondary Electron Yields at Surfaces Exposed to Positron Beam of the KEKB ★ Primary Electron Beam : 50eV~5KeV, Beam Scan Capability ★ Quick Sample Exchanging Capability with Loadlock Chamber (N.A. @CERN) ★ Electron Activity Monitoring Close to Sample @ Beam Chamber <Achievement and Plan> ◆ PY2005 : designing and manufacturing of the system 1. installation of a copper beam chamber in a straight 2. Gate section at the KEKB. Valve Positron Beam a measurement system is being tested in a lab.. 3. Chamber the whole setup will be installed onto the chamber Electron 4. and the measurement will get started. Source ◆ PY2006 : Electron a series of the experiments 1. Sample Manipulator Monitor installation of a setup for short & long term exposure 2. capability installation of a setup for gas puffing capability ( H 2 , Loadlock Chamber 3. CO etc ) installation of a residual gas analyzer 4. Sample Manipulator
Construction of QCS R&D Magnet (2-4) 12 Cured Coils and curing 6 layer coils all at once (1) (1) 12 cured double pan-cake coils. (2) (2) Curing process of 6 layer coils. This process is necessary for improving the field quality in the
High power RF R&D • Upgrade of ARES with higher energy storage ratio. (left) • High power rf input couplers. • SiC dummy load with higher power capability (right).
Superconducting Cavity SuperKEKB challenges: Storing world’s highest beam current of 1.2A. The expected power load to the HOM Input coupler has been operated up to 380kW. absorber is 50 kW/cavity at 4.1 A, Ferrite Higher Order Mode (HOM) (even) with a larger beam pipe of 220 mm φ . absorber working at 10 kW (has achieved 12kW at 1.2 A). HOM damper upgrade may be needed.
A prototype of the new bunch-by-bunch feedback system (G-board / Gproto) was tested at KEKB and ATF. The results were quite successful. •Even in single-bunch mode, we observed a strong longitudinal instability at the ATF. •In multi-bunch mode, we observed a strong CBI. •Successfully damped the longitudinal CBI with the BxB feedback system using Gproto down to 1/10. •Successfully analyzed strongest coupled-bunch mode. (218+n*357 MHz) •For practical use, it will be necessary to build and install a good feedback kicker.
Recommend
More recommend