Jack Creek Park Capital Improvement Project Public Information Meeting October 2, 2017 Consultants & Designers, Inc. “Integrating Engineering and Environment” 7455 New Ridge Road, Suite T Phone: (410) 694-9401 Hanover, Maryland 21076 Fax: (410) 694-9405 1
Introduction Office of County Executive Steven R. Schuh • Michelle Corkadel, Constituent Services Officer Anne Arundel County Department of Public Works • Masoud Ghatineh, P.E., Project Manager Design Consultant – BayLand Consultants & Designers, Inc. • Sepehr Baharlou, P.E., Project Manager Meeting Purpose • Increase Community Awareness of the Project • Provide Project Overview and Status Update • Respond to Questions 2
Project Goals Protect park from shoreline erosion Enhance water quality of the Chesapeake Bay Address County MS4/TMDL permit requirements Improve public access to the waterway Support recreational boating dredging program 3
Project Overview Shoreline Protection • Living shoreline Waterway Access • Soft (natural) canoe/kayak launch Dredged Material Placement • Place dry material from Idlewilde DMP Site 4
Jack Creek Park 58 acres 5
Shoreline Protection 1994 Aerial Photo 6
Shoreline Protection 2014 Aerial Photo 7
Shoreline Protection 2014 VS 1994 Aerial Photo • 6 acres lost due to erosion 8
Shoreline Protection Existing shoreline conditions Bay Front Jack Creek 9 Along the Point
Shoreline Protection Living Shorelines • Controls shoreline erosion • Provides a productive, natural shoreline • Strategic placement of plants, stone, sand fill and other structural and organic materials • Implemented through a variety of shoreline protection methods 10
Shoreline Protection Stone structures provide erosion protection Sand fill provides planting terrace Marsh plantings provide flood protection and habitat enhancement 11
Shoreline Protection Protects 1,488 LF of shoreline Restores 58,811 SF of tidal marsh Preliminary Concept Plan 12
Waterway Access Parking Launch Area Access Road Preliminary Concept Plan 13
Waterway Access Launch Area • Soft (natural) canoe/kayak launch • Natural shoreline 14
Waterway Access Access shoreline through existing trail Provide ADA compliant surface Incorporate launch area into living shoreline design 15
Waterway Access Parking • 20 car parking spots (no trailers) • Permeable grass paving 16
Waterway Access Access Road • Follow existing gravel road • Gravel surface to the parking area • Trail to water will be permeable gravel (ADA compliant) • Controlled access (gate) will remain 17
Dredged Material Placement Place dry material from Idlewilde DMP Site 18
Dredged Material Placement Idlewilde DMP Site primarily used for South County recreational dredging projects such as: • Parish Creek (Federal and County channels) • Rockhold Creek Jetty • Broadwater Creek • Church Creek • West River, etc… All materials are tested before dredging • Metals • Pesticides & PCBs • Priority pollutants volatiles & semi-volatiles • Total of 149 parameters 19
Dredged Material Placement Jack Creek Park placement area 20
Dredged Material Placement Place dry material from Idlewilde DMP Site • 14,000 cubic yards • 3-acre area • Amend soil with lime and fertilizer • Cover with 6 inches of topsoil • Shape to form natural land features • Re-seed with meadow mix Create small wetlands (rain garden) Restore to existing use and vegetative cover 21
Dredged Material Placement Truck Route • Idlewilde Road to Snug Harbor Road – ½ mile 22
Dredged Material Placement Example During Placement After 23
Schedule Project has been split into two phases Phase 1: Dredged Material Placement • Under construction – to be completed in 2 months Phase 2: Living Shoreline & Waterway Access • Design completed • Federal, State and County permitting underway • To be constructed in 12 to 18 months 24
Discussion 25
Recommend
More recommend