investing in transport infrastructure in east asia
play

Investing in Transport Infrastructure in East Asia: Lessons from the - PowerPoint PPT Presentation

Investing in Transport Infrastructure in East Asia: Lessons from the Philippines and Korea 22 February 2005 1. Introduction 2. Case study 1 : Manila North Tollway Project (the Philippines) 3. Case study 2 : Daejon Riverside Expressway (South


  1. Investing in Transport Infrastructure in East Asia: Lessons from the Philippines and Korea 22 February 2005

  2. 1. Introduction 2. Case study 1 : Manila North Tollway Project (the Philippines) 3. Case study 2 : Daejon Riverside Expressway (South Korea) 4. Principal issues and hurdles to achieve PPP structures 5. Conclusions 1

  3. 2. Case Study: Manila North Tollway Corporation – Project Phase 1 : Rehabilitation and widening North Luzon Expressway (approx. 80km) – Grantor : Toll Regulatory Board – Sponsors : Lopez Group/Egis/ Leighton/PNCC – Concession period : 30 years – Total project cost : USD 370m – Operating since February 2005 – Concession contract to international standards – Existing road was already tolled and operated by PNCC Source: Egis Projects SA 2

  4. 2. Case Study: Manila North Tollway Corporation Principal features and critical points : A 10-year long development. Time table was prolonged by materialised risks and other factors Date Events – Long negotiations to achieve international standards for the concession contract 1994 Beginning of the development of the NLE as a ROP Flagship project – A few legal challenges on the procurement process 1997 Signing of JV Agreement with PNCC – Asian financial crisis April 1998 Signing of the Concession Agreement – Long negotiations to achieve financial June 1998 Presidential Approval closing involving 3 multilateral agencies, 7 July 2001 Financial closing 2 export credit agencies and 7 other financial institutions February 2003 First draw down and Commencement – Major delays in land acquisition process of Works due to lack of funding from the February 2005 Opening government End of 2027 End of Concession – Hurdles were overcome by a strong team of sponsors with excellent local reputation. 3

  5. 2. Case Study: Manila North Tollway Corporation Principal features and critical success factors for the project – Acceptability � Level of service increase and standards commensurate to increase in toll rate � Information and transparency – Sustainability � Appropriate long term allocation of risks and responsibilities between private sector and public sector � Pre-adjustment mechanism in the concession contract dealing with inflation, exchange rate, Force Majeure etc. 4

  6. 2. Case Study: Manila North Tollway Corporation Principal features and critical success factors for the project – Bankability � Strong economic fundamentals: a brownfield project with strong existing traffic � Sound contractual structure � Appropriate support for government and direct political risk insurance or through involvement of multilateral agencies. 5

  7. 2. Case Study: Manila North Tollway Corporation A sophisticated but strong financing plan for USD 370m – Strong commitment from the shareholders � Debt/equity ratio of 68/32 � Pre-financing of development up to USD 60m – Loans arranged with � 2 multi-lateral agencies : ADB and IFC (direct and guarantees) � Political risk insurance : MIGA � Export credit agencies : COFACE and EFIC � 7 commercial banks providing covered loans 6

  8. 2. Case Study: Manila North Tollway Corporation A sophisticated but strong financing plan for USD 370m – Robustness of the case � Cover ratios above 2.0 � Sponsors support � Re-financing possibility for part of ADB loan in local currency 7

  9. 3. Case Study: – Project Phase 1 : Section 4, a 5.5km urban toll road – Grantor : Daejon Metropolitan City – Sponsors : Doosan-Egis-Singapore Piling – First BOT project with foreign investment successfully implemented under the Korean PPI Act – Concession period : 30 years – Total project cost : USD 130m – Operating since July 2004 Source: Egis Projects SA 8

  10. 3. Case Study: – Strong sponsors team : a mix of Date Events technical expertise, local knowledge and culture with project July 1998 Signing of a Cooperation Agreement with Daejon City finance expertise February 1999 Signing of the Concession Agreement – PICKO also developed a strong expertise January 2001 Approval by PICKO – Asian financial crisis 5 February 2001 Signing of Addendum ~2 to the – Long negotiations to achieve Concession Agreement financial closing 2 November 2001 Financial closing – Major changes of design requested 15 November 2001 Receipt of the bonds proceeds by by the Grantor after the start of DRECL construction which resulted in 20 December 2001 Commencement of Works some claims August 2004 Opening – Major delays in land acquisition End of 2031 End of Concession process 9

  11. 3. Case Study: A sophisticated financing plan for USD 130m – Strong support from the Korean I R SPC B ISH H B K O N D H O L D E R S A N A A N Proceeds of G uarantee Authorities required since the G uarantee the Bonds underlying project (traffic risk) was Loan K RW Bank Loan new to JPY bond holders in this D aejeon M etropolitan K IC G F environment C ity – Multi currency financing: JPY, D R E C L USD and KRW Equity – Major issues with the termination provisions, exchange risk and indemnity agreements. S S H A R E H O L D E R 10

  12. 4. Principal Issues and Hurdles to Achieve PPP Structures – Procurement � The initial definition of the project by the Grantor could be more successful with the help of reputable advisors of the PPP market : understanding the consequences for the Grantor � A Transparent bidding process is often faster than a negotiated deal � A clear selection criteria 11

  13. 4. Principal Issues and Hurdles to Achieve PPP Structures – Contractual and legal environment � Stability of the contractual framework remains key to attract foreign investment � A single bad deal in one jurisdiction can affect its ability to attract investors for many years � Asia is generally competing with other regions where PPP programmes are very active and perceived risk is much lower 12

  14. 4. Principal Issues and Hurdles to Achieve PPP Structures – Financial environment � Country risk is often an issue in the region hence requiring stronger guarantees from Grantors or multi-lateral support � Appetite for long term lending is limited while short term loans do not generally fit the revenue profile of the projects 13

  15. 4. Principal Issues and Hurdles to Achieve PPP Structures –Risk Transfer and partnership � Find the right balance : signing a contract respecting international standards vs. providing strong Grantor support to make the contract bankable � Responsibilities and risk sharing mechanism need to be explicit � Traps that should be avoided to achieve a balanced partnership � “the private sector can pay”: over specify � “the private sector are all crooks”: over regulate � “ the private sector needs to be innovative”: impose level of service or performance not attainable 14

  16. 4. Principal Issues and Hurdles to Achieve PPP Structures – Community relations � Although a public hearing process may not always be enforced in the region, ignoring community related issues can be fatal to the project: � Expropriating squatters is not a sinecure � Environmental issues require the same care as anywhere else 15

  17. 4. Principal Issues and Hurdles to Achieve PPP Structures – Achieving a shared realistic view of the project fundamentals � Private sector expect returns related to country risk which often seem unacceptable to governments � Private sector’s motivation can sometimes be conflicting with long term goals (short term construction contracts) � Political “will” is often reluctant to admit that some projects do not meet the minimum macro economic returns � Independent advisors or institutions could help reaching a common view � Cross fertilization through global associations of governments or conferences are good but not sufficient 16

  18. 5. CONCLUSIONS – Lessons can still apply to many regions of the world other than Asia – It is difficult to generalise as each country in Asia requires a very specific approach and the PPP process is variably developed throughout the region : it makes it an onerous exercise to develop PPPs in the whole region – Both private and public sectors would see great benefits in cross fertilisation and standardisation of practice throughout the region 17

Recommend


More recommend