installation issues and solutions
play

Installation Issues and Solutions Andreas Agostin Industrial - PowerPoint PPT Presentation

Installation Issues and Solutions Andreas Agostin Industrial Network Sales Specialist Asia Pacific MTL Instruments Singapore, part of Cooper Crouse-Hinds 22.02.2012 Kuala Lumpur 1 1 Successful Implementation & Improved Operation


  1. Installation – Issues and Solutions Andreas Agostin Industrial Network Sales Specialist Asia Pacific MTL Instruments Singapore, part of Cooper Crouse-Hinds 22.02.2012 Kuala Lumpur 1 1 Successful Implementation & Improved Operation

  2. Introduction Fieldbus is in use since 1998 1 , yet still new for many customers today. This presentation will look at the installation issues and the “lessons learned”, so that you can benefits from their experience. 1 Shell Malampaya is one of the early, larger projects. 1600 FF instruments are in use. The project produced first gas in Oct 2001. Source: J. Seaver , Shell Philippines Exploration B.V., “ Malampaya Deep Water Gas-to-Power Project: Malampaya Subsea Development”, Offshore Technology Conference, 6 May -9 May 2002, Houston, Texas. 2 2 Successful Implementation & Improved Operation

  3. Introduction  The pictures you will see are collected from “real” projects; they are neither simulated nor “demo”.  We will look at – Control room: cabinet design and wiring – Field: Wiring, field junction boxes, field device installation.  Processes typically involve explosion protection methods “intrinsic safety” (I.S. / Ex i; energy limitation by a „barrier‟) or “explosion proof” (Ex d; protection by explosionproof enclosure). Many examples use “IS” as this is a key product of my company and that is where I get involved. 3 3 Successful Implementation & Improved Operation

  4. Disclaimer All products shown serve as EXAMPLE only. In particular, problems shown in conjunction with a product serve as example only. The brand/make/model of the product serving as example is IRRELEVANT . Problems highlighted serve as example only, are do in no way express problems with a particular product, model or brand. 4 4 Successful Implementation & Improved Operation

  5. The conventional system 5 5 Successful Implementation & Improved Operation

  6. Control room – Conventional wiring 2 nd level 1 st level Marshalling junction box Control system and barrier 6 6 Successful Implementation & Improved Operation

  7. Control room – Conventional wiring Marshalling: to group AI / AO / DI / DO / etc 7 7 Successful Implementation & Improved Operation

  8. Control room – Conventional wiring 8 8 Successful Implementation & Improved Operation

  9. Control room – Conventional wiring Long wires, standard length  Allows pre-fabrication of wire  (ferrules, mounting) Conventional signals (4-20mA,  RTD, thermocouple, 0- 5V/10V/24V) – slow, hardware filtered, length less important 9 9 Successful Implementation & Improved Operation

  10. Field – Conventional wiring  Quality (material)  Safety  Location / access  Weight/size, … 10 10 10 Successful Implementation & Improved Operation

  11. Fieldbus versus conventional 11 11 Successful Implementation & Improved Operation

  12. Control room – DCS wiring EXAMPLES Fieldbus Conventional 12 12 Successful Implementation & Improved Operation

  13. Control room – DCS wiring EXAMPLES Installations do not have to look messy. They can be very nice, too. Conventional Fieldbus 13 13 Successful Implementation & Improved Operation

  14. Control room – DCS wiring EXAMPLES Conventional Fieldbus 14 14 Successful Implementation & Improved Operation

  15. Control room – DCS wiring EXAMPLES Fieldbus Fieldbus 15 15 Successful Implementation & Improved Operation

  16. Control room – DCS wiring Important: do not use individual wires to wire cabinet. Use fieldbus cable and shield properly. Why? Higher signal frequency – protect ? them against disturbances. Individual wires will cause crosstalk from one wire to another – communication faults can occur. 16 16 Successful Implementation & Improved Operation

  17. Fieldbus Cable Recommended: Type A cable: Shielded twisted pair Other cable is possible, but there are limitations in terms of achievable cable distance and electromagnetic compatibility (EMC). Fieldbus is a digital “high speed” (31kBit/s) communication, a current modulated signal superimposed on the DC power. 17 17 Successful Implementation & Improved Operation

  18. Fieldbus Cable SWA Multi-pair SWA Shielded pair Foil Foil plus principle shield braided shield Multi-pair (multi-trunk) 18 18 Successful Implementation & Improved Operation

  19. Please not this way Images obscured – Brand is irrelevant. 19 19 Successful Implementation & Improved Operation

  20. Control room – DCS wiring 20 20 Successful Implementation & Improved Operation

  21. Fieldbus system – Field wiring ? • Parallel wiring (terminals) • special wiring blocks • (daisy chaining) 21 21 Successful Implementation & Improved Operation

  22. Fieldbus system – Field junction boxes Principle of wiring distribution in junction box: all devices are in parallel Source: FF AG 140 Rev. 1 22 22 Successful Implementation & Improved Operation

  23. Fieldbus system – Field junction boxes Please not this way 23 23 Successful Implementation & Improved Operation

  24. Fieldbus system – Field junction boxes Use dedicated wiring blocks with built-in electronic short circuit protection. LEDs: - built-in s/c protection 24 24 24 Successful Implementation & Improved Operation

  25. Good Wiring Practices  Test segment wiring before connecting components  Avoid damaging the wire when removing insulation  Ground the cable shield only at one point (at the control room end)  Insulate the ungrounded end of the cable shield (at the instrument)  Ground armor on both sides (potential equalization)  Use crimp ferrules – Ferrule diameter must fit wire – Crimp tool must fit ferrule – Ferrule must fit terminals  Maintain polarity and associated color codes throughout the segment 25 25 Successful Implementation & Improved Operation

  26. Good Wiring Practices Choose right size  Lessons learned:  Torque screwdriver  Wire end ferrules  Right (!) wire strippers  Fieldbus tester Harms wire strands 26 26 Successful Implementation & Improved Operation

  27. Fieldbus Design Tools (Examples) 27 27 Successful Implementation & Improved Operation

  28. Project Procedure Best practice:  Bench test Functional tests and interoperability test  FAT  SAT 28 28 Successful Implementation & Improved Operation

  29. Installation Guidelines  Cable Tests – Experience has shown that new cable irregularities are so infrequent that it is more efficient to check cable after installation  Cable Installation – Verify that cable is properly installed, bypassing impact from wiring components  Segment Checkout – Check of proper wiring of wiring components  Device installation – Check of proper device installation  Loop checkout – Functional test 29 29 Successful Implementation & Improved Operation

  30. Installation tools Portable fieldbus diagnostic test equipment (Handhelds)  Measures relevant fieldbus parameters  Establish baseline after commissioning 30 30 Successful Implementation & Improved Operation

  31. Handheld diagnostic tools 24VDC Host Device Coupler FF Power Supply Computer & Terminator FFPS & Conditioner T &Terminator T (non-IS) Spurs H1 Interface Handheld Diagnostic Tool Device 1 Device 2 Device 3 Connect at respective location to obtain accurate measurement. 31 31 Successful Implementation & Improved Operation

  32. Handheld diagnostic tools 24VDC Host Fieldbus barrier FF Power Supply Computer & Terminator FFPS & Conditioner T &Terminator Fieldbus barrier Fieldbus T barrier Intrinsically H1 Interface Safe Spurs Handheld Diagnostic Tool Device 1 Device 2 Device 3 To measure at fieldbus barrier/IS segments, Handheld needs to be Ex i approved. Important since the galvanic isolation of fieldbus barrier impacts on measurement. 32 32 Successful Implementation & Improved Operation

  33. Earthing/Grounding  Grounding in the control room  One point grounding only  Continuous shield from control room to the field  Shield not connected at the field instrument  Connect cable armor at both ends (potential equalization) 33 33 Successful Implementation & Improved Operation

  34. Earthing/Grounding 24VDC Host Wiring Block FF Power Supply Computer & Terminator FFPS & Conditioner T &Terminator T H1 Interface Device 1 Device 2 Device 3 34 34 Successful Implementation & Improved Operation

  35. Earthing/Grounding 24VDC Host Fieldbus barrier FF Power Supply Computer & Terminator FFPS & Conditioner T &Terminator Fieldbus barrier Fieldbus T barrier Intrinsically H1 Interface Safe Spurs Device 1 Device 2 Device 3 35 35 Successful Implementation & Improved Operation

  36. Local field junction box for 4 instruments. Rust prevented proper grounding, so that separate ground connection was required 36 36 Successful Implementation & Improved Operation

  37. Field – Fieldbus wiring Green: fieldbus Red: Power (Motors, etc) For easy maintenance 37 37 Successful Implementation & Improved Operation

  38. Troubleshooting 38 38 Successful Implementation & Improved Operation

Recommend


More recommend