High Voltage Pad-mount Transformer SEPTEMBER 5 - 7, 2018
What is the High Voltage Padmount Transformer(HVPT) Substation? Traditional substation vs. HVPT SEPTEMBER 5 - 7, 2018
HVPT History • In order to reduce its outlay in distribution, Manitoba Hydro investigated alternative solutions that would save in capital costs and land use while increasing reliability and safety. • Manitoba Hydro was also facing the need to replace/refurbish many substations reaching their End of Life. • The idea to make a High Voltage “Distribution Style” transformer was explored. SEPTEMBER 5 - 7, 2018
HVPT History • Working with Partner Technologies Inc., Manitoba Hydro researched and created the HVPT to realize their objectives. Transformer Sizes Different Primary Different Secondary Voltages Voltage 1.5 MVA to 20 MVA Up to 138 kV 5 to 34.5 kV • Can be larger, however loses some of the benefits • In Research: 230 kV Primary Voltage. Can be done but hasn’t been yet. SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
HVPT Details • A HVPT has no energized external parts. • No fencing required. • Suitable for any climate; environmentally friendly. • Utility, residential, commercial and industrial applications. All station components separate – i.e. • regulators, switch gear, capacitors, and station service transformers. SEPTEMBER 5 - 7, 2018
Benefits – Land Savings • Up to 75% in land savings. No need for a large station structure, station yard and fencing. • In an industrial setting, the HVPT transformer can be installed in spaces as small as 20 sq. meters. SEPTEMBER 5 - 7, 2018
Benefits - Reliability • Smaller than your conventional substation, HVPT stations can be installed closer to your site. Shorter feeders, minimize voltage drops and losses and increase • reliability. • Lack of External Bushings and Parts reduces Wildlife Outages SEPTEMBER 5 - 7, 2018
Benefits - Safety • The transformer comes with a tamper resistant enclosure to ANSI C57.12.18 standards. This ensures the transformer is safe from damage from elements, humans, and wildlife. • The public is also protected without the need for fencing. • The grounding designs exceed the requirements of IEEE 80 to ensure public safety. SEPTEMBER 5 - 7, 2018
Benefits - Theft Manitoba Hydro has seen a decrease in copper theft at HVPT Substations. SEPTEMBER 5 - 7, 2018
Benefits – Weather • Storm resistant - covered in dry nitrogen, no on-load tap changer, no conservator, sealed tank, no fans. • Operating Temperature Range (for MH) is -40C to +40C(-40F to 104F) • Can be operated outside of this range SEPTEMBER 5 - 7, 2018
Benefits – Installation & Maintenance • The HVPT station fits onto a trailer and can be shipped completely assembled to your site. • No on site ‘dressing’ of transformer required. • The transformer can then be simply removed and transferred to different locations. • Only routine condition monitoring is required. • Transformers can be “swapped out” and in operation in 24 hours SEPTEMBER 5 - 7, 2018
Benefits - Timeframe • An HVPT Substation’s Design is very simple (7 – 12 drawings vs 50) • Construction can take less than 2 weeks (including verification testing • ~26 to 30 weeks from inception to install • Long lead items SEPTEMBER 5 - 7, 2018
Benefits - Cost • Installation costs up to 50% less than a conventional substation while providing full functionality. • Cost savings include: • Less land procurement • Less additional materials (no fencing, ancillary parts) • Quicker installation • Defer Capital costs • Avoid stranded assets SEPTEMBER 5 - 7, 2018
Disadvantages • Data – Switchgears, ACRs, Regulators • Lack of Fans (ONAN/ONAF) • Onboard tap changer - Regulators SEPTEMBER 5 - 7, 2018
Innovative Supply Options • Use of the HV Padmounts provides a cost effective solution able to accommodate the quickly changing demands of the developer/customer • Flexibility and short lead times avoids stranded assets • Incorporating automation eliminates concerns regarding multiple smaller supply sites allowing for the distributed station concept to be viable • “Building Block Approach” SEPTEMBER 5 - 7, 2018
Innovative Supply Options SEPTEMBER 5 - 7, 2018
Innovative Supply Options • Waverley West subdivision is approximately 2600 acres • Expected to accommodate 40,000 residents in 13,000 homes • Expected to be completely developed in 10 to 30 years • Load estimates vary between 70 and 110 MVA • High level of uncertainty as to load growth rate and horizon load SEPTEMBER 5 - 7, 2018
Case Study – Modular Employment • Instead of two 60-MVA substations taking up 8 acres of land, Manitoba Hydro installed ten 10-MVA HVPT stations surrounding the new 13,000 lot Waverley West development. • Drastically increased the utilization rate (N-1). (60% to 90%) • Initial savings per station amounted up to $1 million with total net present value savings between $13 and $15 million. SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
10 MVA Site SEPTEMBER 5 - 7, 2018
2x 10 MVA Site SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
Installation of an HVPT SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
Dead-Front Terminations Solid Dielectric Primary Connections SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
Thank you! Q & A SEPTEMBER 5 - 7, 2018
Recommend
More recommend