harbour green dock
play

HARBOUR GREEN DOCK Proposed Change of Use, Management & - PowerPoint PPT Presentation

HARBOUR GREEN DOCK Proposed Change of Use, Management & Maintenance Park Board Committee Meeting April 15, 2019 Purpose of Presentation T o provide an update to the Board on the history and current condition of Harbour Green Dock and


  1. HARBOUR GREEN DOCK Proposed Change of Use, Management & Maintenance Park Board Committee Meeting April 15, 2019

  2. Purpose of Presentation  T o provide an update to the Board on the history and current condition of Harbour Green Dock and issues that have contributed to its closure;  To present a proposal for the addition of limited commuter ferry services at the dock with the intent to transfer management and maintenance of the dock to Engineering Services;  To describe a public engagement plan;  To present an interim plan to address current safety concerns; and  To seek approval of a go-forward plan, starting with public engagement. 2

  3. Background 3

  4. Dock Development Overview  Contemplated through the ODP (1992) and rezoning (1996)  Intended to provide a waterside walkway and self-regulated transient moorage  Owned by the City on a designated road parcel (allocated for a floating walkway)  Maintained and managed by the Park Board following construction by local developer ▲ Marinas and water uses plan (Figure 6, Coal Harbour Official Development Plan, 1992) 4

  5. Construction, Inspection & Maintenance Timeline 2005 Sept 2017 Crew repairs Bracket repairs (based on inspection, within (had been an ongoing crew’s ability) issue since construction) 1992-2005 Coal Harbour Feb 2018 - Present Oct 2017 May 2016 Development Closure ENG Report Parks marine and (Marathon) (independent report, bridge inspection noted same issues, raised safety concerns) 2016 Feb 2018 Crew repairs Reassessment ($25k regular inspection 2002-2003 (further deterioration of & maintenance) Aug 2017 brackets, recommended Construction Detailed inspection closure) (stabilization issues (engineers found further noted during deterioration, identified construction) immediate repairs) 5

  6. Overview of Dock Components Gangway Pile bracket Pile Concrete float 6

  7. Current Dock Condition Pile Brackets Piles Floats Fixtures damaged/missing abrasion damage to the pile and blocking & UHMW rub pads the concrete float transition plates pile condition damaged and replaced failed anchor is unknown damaged railings with temporary brackets damaged cleats & failed rollers concrete damage loose caps bull rails caused by (added in 2005 as fix) improper moorage failed bracket 7

  8. Dock Design Issues  excessive movement Brackets have not performed as in all directions intended and repairs have been under normal wave conditions ineffective  No fender system was designed or berthing energy concentrated at installed to dissipate berthing energy piles  Vertical movement continues to be a no fenders problem (stabilizers may need repair)  Many vessels using dock exceed limited design vessel specified original design capacity (15,000 lbs & 35 ft) 8

  9. Environmental Challenges  Wave conditions are affected by high volume of harbour traffic  Location is not as protected as some other docks  Repair and restoration is subject to environmental regulations that change frequently  Located near busy seaplane and commercial shipping lane 9

  10. Previous Dock Usage Recreational Usage Ferry Operations   Unlike other Park Board facilities, Temporary ferry service was offered during Olympics to Bowen Island non-motorized vessels not allowed in Coal Harbour  Operators began to use dock without  Majority of users are recreational permit a few years later boaters  In 2017 services were shutdown, but caused concern with commuters in Other Uses Gibsons and Bowen Island  A variety of other vessels (many  exceeding dock capacity) have Limited operations continued until berthed at the dock closure in February 2018 10

  11. Design Vessel Exceedance Incidents 11

  12. Management & Enforcement Challenges Harbour Green Dock is unique in the region  No moorage fees or permits required  No dedicated enforcement staff  Has largest uninterrupted berthing face (2.5 times next largest dock)  Located in busy waterfront with variety of vessels and commercial operations having open and unregulated access  Never intended for the type of usage and vessels it has received 12

  13. Management & Repair Options 13

  14. Repair/Restoration Options  Extensive damage to mooring brackets, float transitions and some of the concrete floats  Cost to restore to prior condition is $350K+ (at least 12 months to complete)  Recommended to add fenders and redesign ▲ Proposed float mooring solution (hybrid mooring and replace all mooring brackets (at least chain and cushion roller fender bracket) $200K+ in addition to above amount)  Full rebuild may be required to accommodate larger vessels (order of magnitude cost of approximately $2M+)  Without regulation of vessels, future damage ▲ Proposed fender system along the berthing face is highly likely 14

  15. Physical Berthing Barriers/Restriction Options  Options to physically restrict usage to original design vessels explored by marine engineering consultant ▲ Option 1: Floats in a finger arrangement ▲ Option 2: Floating barrier  Option 3 (attaching camels) is the most feasible and would cost $650K + (in addition to the repair costs)  Implementation on hold due to high cost and need for engagement and decision for future dock use ▲ Option 3: Interrupted berthing face with floating removable camels 15

  16. Review of Management Models Models for transient moorage Review Results   All docks have a fee structure Previous attempts show location is based on duration of moorage, challenging to regulate length of vessel, type of use and  Moorage fees will not cover cost of season management, enforcement and  Enforcement varies: in all cases maintenance involve dedicated staff who  Revenues from limited ferry regularly patrol and vessel operations could subsidize registration schemes recreational usage and reduce  List of facilities review provided in regulation overhead Appendix C of Board Report 16

  17. Discussion 17

  18. Addition of Limited Commuter Ferry Service  Continue to provide recreational General Ferry Operation Parameters boating and pedestrian access (to be verified through stakeholder and public engagement)  Provide opportunity for alternate  Sailings during peak morning & mode of transport (Transportation afternoon hours (15-20 minute docking 2040) at each sailing)  Respond to concerns of municipal  30 to 60 ft. vessels transporting 10 to 60 passengers per sailing leaders of neighboring communities  Operators selected through an open  Upgrade and increase resilience of bidding process the dock with better safety features  Tour boats, tugs, and harbour cruise  vessels continue to be restricted from Accommodate larger emergency berthing vessels (VPD & VFRS) 18

  19. Public Engagement  Public engagement is recommended to gather feedback about the proposed change of use Engagement Objectives  Engagement process will be a joint  Confirm current usage for pedestrians effort with Engineering Services and recreational boating  Engagement activities targeted to  Gauge interest in limited commuter services start in the summer 2019 to coincide with boating season and will include  Seek input on operating model and online surveys, social media functional requirements outreach and on-site open house(s)  Report back to the Board is targeted for the fourth quarter of 2019 19

  20. Proposed Transfer to Engineering Services If dock will include limited ferry services:  Transfer management and Principle for Future Operation maintenance to Engineering  Maintain public access as a  Manage as part of Boating & pedestrian walkway Blueways portfolio (incl. 8 public  Ensure availability of public docks in False Creek) recreational boating   Allow limited use of the dock for Ensure better alignment with core ferry services mandate and expertise of Park Board  and Engineering Protect the dock through appropriate monitoring and enforcement  Negotiated transfer terms will be captured in MoU between Park Board and Engineering General Managers 20

  21. Process & Timeline  Limited ferry services may require ODP and zoning amendments  Design and construction require independent marine structural engineer  Construction is regulated by Port of Vancouver and Transport Canada and may be subject to environmental and transport review and permitting  Depending on usage, funding must also be allocated for the repairs, upgrades, management, and operation 21

  22. Interim Removal and Storage  Eliminates risk and liability from continued unauthorized access  Prevents further damage to dock due to pre-existing damage and site wave conditions  Allows public engagement before further investment in the dock  Can be completed at minimal cost within month of approval  Gangways and concrete floats will be dismantled and transported offsite for storage 22

Recommend


More recommend