From NW 89 Court to SR 826 (Palmetto Expressway FDOT FPN. No: 251185-1-52-01, 405665-1-52-01
NW 25 Street-West & Viaduct Construction Purpose The purpose of this project is to improve the flow of traffic on NW 25 Street and facilitate the movement of cargo in and out of the cargo facility at Miami International Airport (MIA). This segment of the project will connect the viaduct with the east segment viaduct and provide a direct connection to the cargo facility from NW 82 Ave.
Location Map NW 25 Street-West & Viaduct Construction N END BEGIN PROJECT PROJECT SR 826 NW 89 CT. NW 25 th Street NW 82 nd Ave. NW 87 th Ave. SR 826
NW 25 Street-West & Viaduct Construction Project Background: PD&E began in 1991 and was completed in 1997 Design Phase began in 2000 and was completed in 2007 Due to High Cost of Construction Project Was Split in two segments (East Segment From Palmetto Expressway to NW 67 Ave, and West Segment From NW 89 Ct to Palmetto Expressway) Construction of East Segment is Ongoing and Is Expected to be Completed in Summer 2011
NW 25 Street-West & Viaduct Construction Proposed Improvements: Reconstruct NW 25 Street at Grade (New Drainage, Lighting, Signals (NW 87 Ave, NW 84 Ave, NW 82 Ave and NW 79 Ave), Landscape and ADA compliance at all Intersection) Widening NW 25 St. from its existing configuration of five lanes undivided to six lanes divided with wide medians. Construct Final Segment of Viaduct Structure over NW 25 Street for truck traffic (T>15%) from NW 82 Ave. to Palmetto (SR 826) Total Project Length 1.206 Miles
NW 25 Street-West & Viaduct Construction BEGIN PROJECT NW 89 CT. NW 25 th Street From 89 Ct to West of NW 82 Ave,
NW 25 Street-West Viaduct Construction END PROJECT SR 826 NW 25 th Street Proposed Viaduct From NW 82 Ave to SR 826 Palmetto,
Typical Roadway Section Looking East at NW 87 Ave.
Typical Viaduct Section At NW 82 Ave.
Project Benefits: Project Benefits: Separation of Cargo Truck and Commuter Traffic Reduced Travel Time Direct Connection to MIA Cargo Area From NW 82 Ave Increased Turning Radius on major intersection
NW 25 Street-West & Viaduct Construction Project Issue: Plans were Updated in 2010 to Comply With Current FDOT Criteria All Plan Have Been Updated and Funding is in place to begin construction Final Plans Shall be submitted to the Department March 2011 Plans to Tallahassee in April 2011 Plan Letting is scheduled for July 2011 Expected Construction Duration is 1250 days or 3.5 years
NW 25 Street-West & Viaduct Construction Funding: Cost is estimated at $70.3 Million ($44.3 roadway + $26.0 viaduct) No Private-Private Partnership Traditional Bid Build No Stimulus Fund / Project does have ACNH Federal Funds
NW 25 Street-East Construction Update Project Update: Project is currently close to 90% complete Viaduct Substructure is 100% Viaduct Super-structure - all structural steel is in place - 36 deck pours remain to be competed Construction Completion Date is Scheduled for July 2011