fort hills project
play

Fort Hills Project September 2015 Mining and Bitumen Extraction - PowerPoint PPT Presentation

Fort Hills Project September 2015 Mining and Bitumen Extraction Process 1 Process Technology High temperature paraffinic froth treatment provides about 20% partial upgrading advantage over other more convention bitumen production processes


  1. Fort Hills Project September 2015

  2. Mining and Bitumen Extraction Process 1

  3. Process Technology High temperature paraffinic froth treatment provides about 20% partial upgrading advantage over other more convention bitumen production processes via reduced product carbon residue, sulphur, and other elements 2

  4. Project Status and Progress 13 million Safety and Environment construction hours without a reportable environmental or continued positive performance regulatory non-compliance 0.35-0.45 recordable injury frequency per 200,000 exposure hours 90% engineering complete Project Progress as at August 2015 continues to track positively within 40% construction complete project sanction cost and schedule expectations as at August 2015 global fabrication, module and logistics program performing well to date, delivering positive results all critical schedule milestones have been achieved to date supporting target 2017 first oil

  5. Construction Productivity Fort Hills construction productivity has improved over previous regionally executed projects since the launch of a formal productivity improvement program Improved productivity level has been reflected in the sanction estimate and schedule Improved construction productivity serves to de-risk project execution and contributes to on-plan schedule and on-budget cost attainment 4

  6. Site Workforce Profile Site resourcing continues to meet plan with increasing access to Western Canada based resources due to current market conditions 6000 4000 2000 0 Jan-14 Mar-14 May-14 Jul-14 Sep-14 Nov-14 Jan-15 Mar-15 May-15 Jul-15 Sep-15 Nov-15 Jan-16 Mar-16 May-16 Jul-16 Sep-16 Nov-16 Jan-17 Mar-17 May-17 Jul-17 Sep-17 Nov-17 5

  7. Pipe and Module Fabrication, Korea 6

  8. Structural Steel Fabrication, China 7

  9. Piping Fabrication, India 8

  10. Mining Development, Looking NE 9

  11. Main Plant Site Looking NW 10

  12. Ore Preparation, Looking NE 11

  13. Ore Preparation, Crusher Plant 12

  14. Ore Preparation, Surge Bin 13

  15. Ore Preparation, Rotary Breakers 14

  16. Ore Preparation 15

  17. Hydro Transport Corridor 16

  18. Extraction and Tailings, Looking NE 17

  19. Extraction and Tailings 18

  20. Extraction and Tailings, Thickener 19

  21. Secondary Extraction, Looking West 20

  22. Secondary Extraction 21

  23. Secondary Extraction 22

  24. Secondary Extraction 23

  25. Utilities, Looking NW 24

  26. Utilities, Process Water Tanks 25

  27. Utilities, Cogen-GTG Building 26

  28. Utilities Recycle Water Pond, Looking SE 27

  29. River Water Intake, Looking NE 28

  30. Raw Water Pond, Looking NE 29

  31. Operations Lodge 30

  32. Maintenance Shops 31

  33. Main Substation 32

  34. Tank Farm 33

  35. Gate 9, Looking East 34

Recommend


More recommend