fdot district 5 clyde morris boulevard sr 483
play

FDOT District 5 Clyde Morris Boulevard (SR 483) from south of - PowerPoint PPT Presentation

FDOT District 5 Clyde Morris Boulevard (SR 483) from south of Beville Rd (SR 400) to north of International Speedway Blvd (US 92/SR 600) FPID: 408178-1-32-01 Volusia County MPO BPAC Meeting January 13, 2010 Project Implementation PD&E


  1. FDOT District 5 Clyde Morris Boulevard (SR 483) from south of Beville Rd (SR 400) to north of International Speedway Blvd (US 92/SR 600) FPID: 408178-1-32-01 Volusia County MPO BPAC Meeting January 13, 2010

  2. Project Implementation PD&E Study Final Design Right of Way Construct Project

  3. SR 483 Design Phase • Detailed Engineering • Define: – Right of Way Needs – Anticipated Construction Costs • Continue: – Local Agency and Stakeholder Involvement – Public Involvement

  4. SR 483 – Project Limits Project Limit Project Limit

  5. Project Need - Safety

  6. SR 483 PD&E Study Proposed Typical Section Width of sidewalk adjusted to demand of pedestrian use near the educational institutions: • Continuous 5 foot sidewalks to be constructed at outer edge of pavement on both sides of roadway. • Eight foot sidewalk on west side of roadway between Hancock Blvd to Richard Petty Blvd. • Eight foot sidewalk on east side of roadway between Richard Petty Blvd to US 92/SR 600.

  7. Preferred Alternative Estimated Project Cost • Construction $ 33,700,000 • Engineering, CEI $ 6,750,000 • Utility Relocation $ 4,700,000 • Right-of-Way $ 15,000,000 Total $ 60,150,000

  8. Volusia County MPO Bicycle/Pedestrian Feasibility Study Completed in 2008 Analyzed 3 alternatives: • Option A ‐ 5 ‐ ft wide concrete sidewalk • Option B ‐ 10 ‐ ft wide concrete sidewalk • Option C ‐ 12 ‐ ft wide asphalt multi ‐ use trail

  9. Volusia County MPO Bicycle/Pedestrian Feasibility Study

  10. Questions? Brenda Young Design Project Manager 719 S. Woodland Boulevard Deland, Florida 32720 386-943-5645 brenda.young@dot.state.fl.us

Recommend


More recommend