Alafaya Trail Project Update Avalon Park Boulevard to Mark Twain Boulevard Mark Twain Boulevard Alafaya Trail 3.8 Miles Avalon Park Boulevard Board of County Commissioners Discussion Agenda Item # B-1 January 25, 2011
Alafaya Trail Project Update Avalon Park Boulevard to Mark Twain Boulevard Project Mark Twain Boulevard History Procurement and Construction Alafaya Trail Action 3.8 Miles Avalon Park Boulevard Requested
Alafaya Trail Project Update Avalon Park Boulevard to Mark Twain Boulevard Project Mark Twain Boulevard History Procurement and Construction Alafaya Trail Action 3.8 Miles Avalon Park Boulevard Requested
Project History Planning, Design & Right-of-Way Identified in Comprehensive Plan Public/Private Partnership Agreement Approved by BCC – Avalon & Associates: Design – Morgran: Up-Fronted Cash & Ponds Construction Plans Finalized 2009 Right-of-Way Acquisition Completed August 2010
Project History Design Elements 10 Stormwater Ponds 4 Travel Lanes Raised Grass Median 12,000 Feet of Retaining Wall Utility Work – Wastewater, Reuse, Water Mains (Pipe Size Varies from 24” to 36”)
Project History Design Elements 3 Signalized Intersections (One New) No Landscaping or Lighting Due to Budgetary Constraints New Signal Existing Stoneybrook Bv. Signal Upgrade Golfway Bv. Existing Signal Upgrade Innovation Way
Alafaya Trail Project Update Avalon Park Boulevard to Mark Twain Boulevard Project Mark Twain Boulevard History Procurement and Construction Alafaya Trail Action 3.8 Miles Avalon Park Boulevard Requested
Procurement and Construction Construction Anticipated BCC Approval - January 25, 2011 Anticipated Contract Execution - February 1, 2011 Anticipated Notice to Begin Construction - February 15, 2011
Procurement and Construction Construction Construction Duration 2-1/2 Years (August 2013) County’s $19.6 Million Roadway Estimate: $11.1 Million Utilities $30.7 Million Total
Procurement and Construction Construction Bids: Company Estimated Bid Amount Jr. Davis $30,203,373 Halifax $31,042,574 Prince $33,359,946 Ranger $34,610,030 County’s $30,700,000 Estimate
Alafaya Trail Project Update Avalon Park Boulevard to Mark Twain Boulevard Project Mark Twain Boulevard History Procurement and Construction Alafaya Trail Action 3.8 Miles Avalon Park Boulevard Requested
Action Requested Approval to award Invitation for Bids Y11-708-CH, Alafaya Trail Widening Project (from Avalon Park Boulevard to Mark Twain Boulevard), to the low responsive and responsible bidder, Jr. Davis Construction Company, Inc., in the total estimated contract award amount of $30,203,372.92.