Alafaya Trail Project Update Avalon Park Boulevard to Mark Twain - PowerPoint PPT Presentation

Alafaya Trail Project Update Avalon Park Boulevard to Mark Twain Boulevard Mark Twain Boulevard Alafaya Trail 3.8 Miles Avalon Park Boulevard Board of County Commissioners Discussion Agenda Item # B-1 January 25, 2011 Alafaya Trail Project


  1. Alafaya Trail Project Update Avalon Park Boulevard to Mark Twain Boulevard Mark Twain Boulevard Alafaya Trail 3.8 Miles Avalon Park Boulevard Board of County Commissioners Discussion Agenda Item # B-1 January 25, 2011

  2. Alafaya Trail Project Update Avalon Park Boulevard to Mark Twain Boulevard  Project Mark Twain Boulevard History  Procurement and Construction Alafaya Trail  Action 3.8 Miles Avalon Park Boulevard Requested

  3. Alafaya Trail Project Update Avalon Park Boulevard to Mark Twain Boulevard  Project Mark Twain Boulevard History  Procurement and Construction Alafaya Trail  Action 3.8 Miles Avalon Park Boulevard Requested

  4. Project History Planning, Design & Right-of-Way  Identified in Comprehensive Plan  Public/Private Partnership Agreement Approved by BCC – Avalon & Associates: Design – Morgran: Up-Fronted Cash & Ponds  Construction Plans Finalized 2009  Right-of-Way Acquisition Completed August 2010

  5. Project History Design Elements  10 Stormwater Ponds  4 Travel Lanes  Raised Grass Median  12,000 Feet of Retaining Wall  Utility Work – Wastewater, Reuse, Water Mains (Pipe Size Varies from 24” to 36”)

  6. Project History Design Elements  3 Signalized Intersections (One New)  No Landscaping or Lighting Due to Budgetary Constraints New Signal Existing Stoneybrook Bv. Signal Upgrade Golfway Bv. Existing Signal Upgrade Innovation Way

  7. Alafaya Trail Project Update Avalon Park Boulevard to Mark Twain Boulevard  Project Mark Twain Boulevard History  Procurement and Construction Alafaya Trail  Action 3.8 Miles Avalon Park Boulevard Requested

  8. Procurement and Construction Construction  Anticipated BCC Approval - January 25, 2011  Anticipated Contract Execution - February 1, 2011  Anticipated Notice to Begin Construction - February 15, 2011

  9. Procurement and Construction Construction  Construction Duration 2-1/2 Years (August 2013)  County’s $19.6 Million Roadway Estimate: $11.1 Million Utilities $30.7 Million Total

  10. Procurement and Construction Construction Bids: Company Estimated Bid Amount Jr. Davis $30,203,373 Halifax $31,042,574 Prince $33,359,946 Ranger $34,610,030 County’s $30,700,000 Estimate

  11. Alafaya Trail Project Update Avalon Park Boulevard to Mark Twain Boulevard  Project Mark Twain Boulevard History  Procurement and Construction Alafaya Trail  Action 3.8 Miles Avalon Park Boulevard Requested

  12. Action Requested Approval to award Invitation for Bids Y11-708-CH, Alafaya Trail Widening Project (from Avalon Park Boulevard to Mark Twain Boulevard), to the low responsive and responsible bidder, Jr. Davis Construction Company, Inc., in the total estimated contract award amount of $30,203,372.92.