fair phase 0
play

FAIR Phase-0 NUSTAR R3B Annual Meeting 2018 20180227-0302 - PowerPoint PPT Presentation

FAIR Phase-0 NUSTAR R3B Annual Meeting 2018 20180227-0302 2018/19 H. Simon GSI Darmstadt RB/LAND Setup evolves to RB/NeuLAND Setup + GLAD (kinematically complete) protons fragments Target detector: Gammas (t) Recoil


  1. FAIR Phase-0 NUSTAR R3B Annual Meeting 2018 20180227-0302 2018/19 H. Simon ● GSI Darmstadt

  2. R³B/LAND Setup evolves to R³B/NeuLAND Setup + GLAD (kinematically complete) protons fragments Target detector: • Gammas (t) • Recoil Protons (p,2p) 2 (x,y) • Recoil Neutrons (p,pn) neutrons (x,y,t) (Z,t) 2 (x,y) • particle identification • time of flight (8-12 m flight path) • deflection angle � relativistic four momentum vectors NUSTAR Annual 2018

  3. Starting point 2016 NUSTAR Annual 2018

  4. R 3 B (Status Phase-0 in 2018) Tracking L3T Si tracker NeuLAND ACTAF 2 (1 st stage) � 13 out of 30 double CALIFA barrel and fwd start version planes secured � >75% secured � 3 more expected � additional funding expected GLAD + vacuum chamber Proton Arm Spectrometer Tracking NUSTAR-DAQ (TDR accepted 02/2018) -Time stamps (first implementation)/local trigger logics/readout libraries -Online analyss R³B-Root � FAIR-Root NUSTAR Annual 2018

  5. All Infrastructure and magnet installed 2013-2016 Commissioning started NUSTAR Annual 2018

  6. R 3 B / GLAD 20180208 neutrons February 2016 g-rays @ CAVE C (02/16 � 11/16 ) protons Preparation for FAT , NCs removed • Cryo Line, Cryo plant, Power supply, and Quench Protection System all ok • Cooling down tests on going � final commisioning • Open Issues: Current lead foot cooling insufficient (20171115) • Tracking � Independend cooling of busbar and Detectors current lead prepared, new cl design in || current tests 20180222 heavy fragments � @3500A/0.28g/s (0.27 g/s calculated) (cl ok !) Modification in Satellite foreseen • decision on new cl‘s within next week… NUSTAR Annual 2018

  7. Worst Case Schedule (CEA, Ch. Mayri) March April May June 13.04 cl validation (ahead schedule � beginning of March ?) 1.5. new cl done Phase-0 experiment status : • Expected to be ready Q2/2018 NUSTAR Annual 2018

  8. R 3 B /L3T (Si- Tracker) is potentially delayed On going tests @ Daresbury: Full inner L3T layer in working condition • expected energy threshold of 100 keV in • verification (150keV achieved) neutrons Test bench running, first results • Tests with alpha-source and, • subsequently, cosmic rays g-rays � Outer layer to be mounted and tested protons L3T configuration -inner layer 6 detector ladders -outer layer 12 detector ladders (03-04/18) Double-sided micro-strip Si sensors wire bonded to a dedicated ASIC (RAL: 120’000 channels) + time stamped FPGA based readout Tracking Detectors TDR: L3T is a deliverable for the in-kind UK contribution. TDR is not need but R3B collaboration whish the presentation to ECE of an equivalent document protons including performance evaluation with up-coming tests light fragments Phase-0 experiment status : Expected a functional detector for Q2-3 /2018 NUSTAR Annual 2018

  9. R 3 B /NeuLAND neutrons simulation prediction: reconstruction efficiency of the NeuLAND Phase 0 Ok Q2-2018 g-rays order of 20% for 3 n, 10 % for 4 n 130 cm active depth • protons (600 MeV, preliminary) 2600 channels >40% detector • SAT test of in-house developed NeuLAND electronics Tracking underway: NeuLAND demonstrator back from Detectors multichannel front-end RIKEN after participation in 9 protons electronic card TAMEX experiments, incl. studies of light light fragments heavy fragments for high-resolution time exotic systems ( 4 n) up to EOS of and charge heavy tin systems measurements NUSTAR Annual 2018

  10. CALIFA start version: Calorimeter in-flight detection for γ -rays and LCP Start version: Full detector: NUSTAR Annual 2018

  11. CALIFA : Calorimeter in-flight detection for γ -rays and LCP • CsI (Tl) range between 15-22 cm long CsI(Tl)+LAAPD • Packed in groups of four (VM2000 and Carbon fiber) • APD collecting area 10x20 mm 2 2464 units (full detector) Polar angle 20-140 0 Good ∆ E/E ~6% @ 1 MeV for g • and 2 % for p up to 320 MeV • PID and E determination based on two different intrinsic times of CsI up to 700 MeV ∆ E/E ~ 5% • Background rejection • LaBr 6 cm and LaCl 8 cm long • Packed in groups (Al cane) Very good ∆ E/E ~ 3% @ 662 keV • PM 1.5 ¨ diameter • for γ • E determination based on two different time decay of LaBr/LaCl LaBr/LaCl+PM ∆ E/E ~ 5% • Good timing 96 units • Background rejection Polar angle 7-20 0 NUSTAR Annual 2018

  12. NUSTAR Annual 2018

  13. Commissioning: L 3 T with CALIFA Demonstrator L3T : L amp shape L ow mass L ight particle T racker CALIFA : CAL orimeter for the I n F light detection of γ -rays and light charged p A rticles Existing setup: Geometry from Geant4 implementation : animation 3D cut along the beam L3T: (risk to be delayed) Full coverage of solid angle Full inner and outer plane Full readout system. CALIFA demonstrator: 4 single petals 2 double petals 28 o < Θ < 78 o 50% Φ coverage + CEPA first segment Full readout system. NUSTAR Annual 2018 NUSTAR beamtime preparation meeting (GSI) 15.11.2017

  14. Comm: Proton Energy in CALIFA 2018 Pulse shape analysis (PSA) cleans up the Simulated reactions in the active material signal of 500MeV Protons up to 285MeV are protons in stopped in 22cm CsI, ∆ E/E < 1% 22 cm CsI iPhos PSA for larger energies Probability to detect true proton energy NUSTAR Annual 2018 NUSTAR beamtime preparation meeting (GSI) 15.11.2017

  15. Comm: 12 C Beam Commissioning of GLAD, FAT 2018/19 Measurement with 12 C: 400,600,800,1200 AMeV @ 10 5 1/s GLAD field map probed over a wide range of p/Q and large acceptance high res: 2018/9 (EOS, fission runs) NUSTAR Annual 2018 NUSTAR beamtime preparation meeting (GSI) 15.11.2017

  16. Comm: Tracking Detectors 2018/19+ LOS PSP GLAD 200 µ m square fiber for FIB4a 200/500 µ m round fiber FIB4b/5 FIB (3x) TOFD T PAS PASTOF 10 x 10 cm 2 σ E < 1% Z separation σ t < 10ps A separation Rate 1 MHz Proton Arm Spectrometer σ E < 0.5% Z separation σ x < 100 µ m Position x y Rate 0.1 MHz/strip σ E < 1% Z separation σ t < 38ps A separation Rate 1 MHz/strip NUSTAR Annual 2018 NUSTAR beamtime preparation meeting (GSI) 15.11.2017

  17. Commissioning beam time: red. request beam E rate Nr of Goal comments (AMeV) (1/s) shifts 10 5 light 400 -800 5p start up detectors, electronics, trigger distributed in time 12 C, 18 O. system, rough timing adjustment, first over a full week . set of GLAD with beam (2018) 10 7 p 500 3+6p L3T site acceptance test, 4 shifts to collect proton response CALIFA (2018/19) statistics, 1 shift for BG evaluation 12 C 10 7 500 2p CALIFA Doppler correction. rate test of tracking Background comp. to prev. run detectors. normal/inverse kinematics (2018/19) 12 C 10 5 400, 700, 9+6p Commissioning of GLAD, (2018/19) L3T under realistic 1200 Systematic Doppler studies in CALIFA (p,2p) conditions. 2 H 10 5 400, 800 4 1n response of NeuLAND, (p,2p) (2019, energy response in L3T + CALIFA beam driven) 197 Au 10 5 400 6p ASY-EOS II detector test S464 (LoI), Tbd. Not all tests can be done still in 2018 NUSTAR Annual 2018 NUSTAR beamtime preparation meeting (GSI) 15.11.2017

  18. Experiments proposed in phase-0: Summary A 2018/9 p,2p not reasonable without commisioned L³T 2018 A- (accepted change) NeuLAND characterisation (2018) A- (potential fall back) High rate tracking 2019 requires calorimetry 2019 p,2p 2018/9 partly p,2p NUSTAR Annual 2018

  19. NUSTAR Annual 2018

Recommend


More recommend