fabec operations
play

FABEC Operations From a project-driven approach to continuous - PowerPoint PPT Presentation

FABEC Operations From a project-driven approach to continuous operational improvements Andreas Ptzsch Chairman FABEC Operations and DFS Director En-route and Approach. Madrid, 07 March 2017 0 FABEC at a glance 6 states 7 ANSPs


  1. FABEC Operations From a project-driven approach to continuous operational improvements Andreas Pötzsch Chairman FABEC Operations and DFS Director En-route and Approach. Madrid, 07 March 2017 0

  2. FABEC at a glance § 6 states § 7 ANSP’s § 5 Military partners § 14 ACC’s § Traffic : ~ 5.7 Mio Flights/ Year more than 50 % of European air traffic § Airspace : 1,7 Mio km² § Service at 240 Airports 1 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  3. ACC‘s and UAC‘s 14 Centres with different organisational structures UACs ACCs 2 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  4. FABEC Focus until 2014 / 2015 § Establish FABEC governance and structure on ANSP and States side § Establish complex processes to steer common work § Concentrate on large scale airspace design projects, involving numerous stakeholders from both civil and military ANSP’s 3 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  5. FABEC Airspace Design Projects 4

  6. FABEC Focus until 2014 / 2015 § Establish FABEC governance and structure on ANSP and States side § Establish complex processes to steer common work § Concentrate on large scale airspace design projects, involving numerous stakeholders from both civil and military ANSP’s § Distinguish between local / national projects and FABEC projects 5 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  7. FABEC projects until 2014 / 2015 § AMRUFRA cross border airspace redesign R § Night Network / City Pairs R § FAAP: ASM / FUA improved civil military coordination R § FRA: FABEC Free route project – ongoing R XMAN: Extended Arrival Management – ongoing § R § CBA Land / CW: cross border airspace redesign – on hold § IP SE: cross border airspace redesign – on hold tbd § FOCS: cross border airspace redesign – under discussion 6 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  8. 2016-2019 Changing the focus Realism and Performance Combining realistic initiatives to an overarching planning based on performance needs and customer requirements. 7 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  9. FABEC Lessons Learned § Common processes and firm operational steering is needed § Alignment of Local/National and FAB strategies is required when building the FAB project portfolio § Large scale airspace redesign is not the answer anymore to fast changing traffic patterns and regulatory framework (e.g. PCP IR) § Stepwise approaches instead of big bang implementations § Ensure active involvement of all stakeholders § Ensure firm commitment of all partners § Address daily OPS requirements and stay in close contact with ACC’s 8 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  10. FABEC New OPS orientations (1) § Pursue performance driven approach (safety, capacity, environment, cost efficiency) 9 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  11. Holistic approach to FABEC performance 10 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  12. FABEC New OPS orientations (1) § Pursue performance driven approach (safety, capacity, environment, cost efficiency) § Subsidiarity principle (ACC-level, national level, FABEC-level) 11 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  13. ACC‘s and UAC‘s 14 Centres with different organisational structures UACs ACCs 12 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  14. FABEC New OPS orientations (1) § Pursue performance driven approach (safety, capacity, environment, cost efficiency) § Subsidiarity principle (ACC-level, national level, FABEC-level) § Adjustment of the FABEC OPS governance 13 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  15. FABEC SC OPS Working Organisation 14 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  16. FABEC New OPS orientations (1) § Pursue performance driven approach (safety, capacity, environment, cost efficiency) § Subsidiarity principle (ACC-level, national level, FABEC-level) § Adjustment of the FABEC OPS governance § Widening FABEC Ops scope (include local and bilateral initiatives) Close to daily operations (“2 nd pillar initiatives”, establishment of a Head of ACC group at § FABEC level) 15 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  17. FABEC: Weather induced delay MET Alliance conducts FABEC study about the impact of adverse weather conditions on ATM 16 January 2017.-; At the request of the FABEC air navigation service providers, MET Alliance, a consortium of leading European meteorological service providers, is investigating the possible effects of changes in weather behaviour on air traffic management and more generally the impact of adverse weather conditions on ATM. 16 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  18. FABEC New OPS orientations (1) § Pursue performance driven approach (safety, capacity, environment, cost efficiency) § Subsidiarity principle (ACC-level, national level, FABEC-level) § Adjustment of the FABEC OPS governance § Widening FABEC Ops scope (include local and bilateral initiatives) Close to daily operations (“2 nd pillar initiatives”, establishment of a Head of ACC group at § FABEC level) § Actively address OPS challenges (traffic volatility, capacity gaps etc., establishment of a FABEC OPS Development Group) § Set goals in dedicated OPS plans 17 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  19. FABEC Operational Planning Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  20. FABEC New OPS orientations (2) § Extended Arrival management (XMAN) and Free Route (FRA) remain backbone of OPS strategy 19 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  21. FABEC XMAN Project Plan 2017 London –ACC Brest: mid 2017 Munich – UAC Karlsruhe: end 2017 (extension to 220NM) Munich – ACC Vienna: end 2017 (extension to 220NM) Munich – ACC Zurich: end 2017 (extension to 220 NM) Munich – ACC Langen: end 2017 Frankfurt – MUAC: mid 2017 Frankfurt – UAC Karlsruhe: mid 2017 Frankfurt – ACC Munich: mid 2017 Frankfurt – ACC Bremen: end 2017 Zurich – UAC Reims: early 2017 Zurich – ACC Munich: early 2017 Zurich – ACC Langen: early 2017 20 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  22. FABEC Free Route Airspace Project § Stepwise approach § One common Concept of Operations § Incorporation of AU § Set-up States/ANSP FUA task force § Rolling UUP § InterFAB initiatives 21 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  23. FABEC New OPS orientations (2) § XMAN and FRA remain backbone of OPS strategy § Include Inter FAB OPS initiatives 22 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  24. FABEC InterFAB Initiatives - SESAR Optimized Descend Profiles - Long-Range DCT’s on SE axis - New DCT’s with Baltic FAB - XMAN adjacent to FABEC - ATM system groups, e.g. iTEC - Free Route extension SW FAB 23 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  25. FABEC New OPS orientations (2) § XMAN and FRA remain backbone of OPS strategy § Include Inter FAB OPS initiatives § Development of a FABEC OPS Performance Roadmap § Close cooperation with NM, close to network evolutions § Close cooperation with airspace users (Joint OPS/AOG, FABEC Customer Satisfaction Survey, etc.) § Involvement of social partners § Development of FABEC positions towards external stakeholders 24 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

  26. From FAB‘s to European Network – Joint efforts or blaming culture in European aviation? Who is to be blamed for what? § European ATM operational performance: not as efficient as US § EC: Regulatory framework not adapted to the network requirements § FAB’s: not delivering expected performance § ANSP’s: capacity gaps and high unit rates § Airlines: not using the shortest routes § CFSP’s: technically not up-to-date to support efficient flight planning § NM: not delivering network performance § Military airspace users: blocking large parts of European airspace § Airports: not prepared for special situations (e.g. winter operation) § Unions (ANSP and Airline): frequent strikes causing major disruptions § ???: Heavy thunderstorm season 2016 25 Andreas Pötzsch, CM FABEC Operations and DFS Director En-route and Approach, Madrid 07.03.2017

Recommend


More recommend