evaluation of the impacts of geographically correlated
play

Evaluation of the Impacts of Geographically-Correlated Failures on - PowerPoint PPT Presentation

Evaluation of the Impacts of Geographically-Correlated Failures on Power Grids Andrey Bernstein 1,2 , Daniel Bienstock 3 , David Hay 4 , Meric Uzunoglu 1 , Gil Zussman 1 1 Electrical Engineering, Columbia University 2 Electrical Engineering,


  1. Evaluation of the Impacts of Geographically-Correlated Failures on Power Grids Andrey Bernstein 1,2 , Daniel Bienstock 3 , David Hay 4 , Meric Uzunoglu 1 , Gil Zussman 1 1 Electrical Engineering, Columbia University 2 Electrical Engineering, Technion 3 Industrial Engineering and Operations Research, Columbia University 4 Computer Science and Engineering, Hebrew University

  2. The Power Grid  A failure will have a significant effect on many interdependent systems - oil/gas, water, transportation, telecommunications  Extremely complex network  Relies on physical infrastructure  Vulnerable to physical attacks  Failures can cascade

  3. Large Scale Physical Attacks/Disasters  EMP (Electromagnetic Pulse) attack  Solar Flares - in 1989 the Hydro-Quebec system collapsed within 92 seconds leaving 6 Million customers without power Source: Report of the Commission to Assess the threat to the United States from Electromagnetic Pulse (EMP) Attack, 2008  Other natural disasters  Physical attacks or disasters affect a specific geographical area FERC, DOE, and DHS, Detailed Technical Report on EMP and Severe Solar Flare Threats to the U.S. Power Grid, 2010

  4. Related Work  Report of the Commission to Assess the threat to the United States from Electromagnetic Pulse (EMP) Attack, 2008  Federal Energy Regulation Commission, Department of Energy, and Department of Homeland Security, Detailed Technical Report on EMP and Severe Solar Flare Threats to the U.S. Power Grid, Oct. 2010  Cascading failures in the power grid  Dobson et al. (2001-2010), Hines et al. (2007-2011), Chassin and Posse (2005), Xiao and Yeh (2011 ), …  The N - k problem where the objective is to find the k links whose failures will cause the maximum damage: Bienstock et al. (2005, 2009)  Interdiction problems: Bier et al. (2007), Salmeron et al. (2009 ), …  Do not consider geographical correlation of initial failing links

  5. Power Grid Vulnerability and Cascading Failures  Power flow follows the laws of physics  Control is difficult  It is difficult to “store packets” or “drop packets”  Modeling is difficult  Final report of the 2003 blackout – cause #1 was “inadequate system understanding” (stated at least 20 times)  Power grids are subject to cascading failures:  Initial failure event  Transmission lines fail due to overloads  Resulting in subsequent failures  Large scale geographically correlated failures have a different effect than a single line outage  Objectives:  Assess the vulnerability of different locations in the grid to geographically correlated failures  Identify properties of the cascade model

  6. Outline  Background  Power flows and cascading failures  Numerical results – single event  Cascade properties  Vulnerability analysis and numerical results

  7. Power Flow Equations - DC Approximation  Exact solution to the AC model is infeasible 2 𝑕 𝑗𝑘 − 𝑉 𝑗 𝑉 𝑘 𝑐 𝑗𝑘 sin 𝜄 𝑗𝑘 𝑄 𝑗𝑘 = 𝑉 𝑗 𝑘 𝑕 𝑗𝑘 cos 𝜄 𝑗𝑘 − 𝑉 𝑗 𝑉 2 𝑐 𝑗𝑘 + 𝑉 𝑗 𝑉 𝑘 𝑕 𝑗𝑘 sin 𝜄 𝑗𝑘 𝑅 𝑗𝑘 = −𝑉 𝑗 𝑘 𝑐 𝑗𝑘 cos 𝜄 𝑗𝑘 − 𝑉 𝑗 𝑉 and 𝜄 𝑗𝑘 = 𝜄 𝑗 − 𝜄 𝑘 .  Non – linear, non-convex, intractable, 𝑘  May have multiple solutions  We use DC approximation which is based on: 𝑉 𝑗 ≡ 1, ∀𝑗 𝑘 𝑦 𝑗𝑘 𝑔 𝑗 , 𝑒 𝑗 sin 𝜄 𝑗𝑘 ≈ 𝜄 𝑗𝑘 𝑗 𝑄 𝑗 = 𝑔 𝑗 − 𝑒 𝑗  𝑉 𝑗 = 1 𝑞. 𝑣. for all 𝑗 𝑉 𝑗 , 𝜄 𝑗 , 𝑄 𝑗 , 𝑅 𝑗  Pure reactive transmission lines – each line is characterized only by its Load ( 𝑄 𝑗 , 𝑅 𝑗 < 0 ) reactance 𝑦 𝑗𝑘 = −1/𝑐 𝑗𝑘 Generator ( 𝑄 𝑗 , 𝑅 𝑗 > 0 )  Phase angle differences are “small”, implying that sin 𝜄 𝑗𝑘 ≈ 𝜄 𝑗𝑘

  8. Power Flow Equations - DC Approximation 𝑉 𝑗 ≡ 1, ∀𝑗 𝑘 𝑦 𝑗𝑘 𝑔 𝑗 , 𝑒 𝑗 sin 𝜄 𝑗𝑘 ≈ 𝜄 𝑗𝑘 𝑄 𝑗 = 𝑔 𝑗 − 𝑒 𝑗  The active power flow 𝑄 𝑗𝑘 can be found by solving: + 𝑒 𝑗 for each node 𝑗 𝑗 + = 𝑔 𝑄 𝑄 𝑘:𝑄 𝑘𝑗 >0 𝑘𝑗 𝑘:𝑄 𝑗𝑘 >0 𝑗𝑘 𝑘 𝜄 𝑗 −𝜄 𝑘 𝑦 𝑗𝑘 for each line (𝑗, 𝑘) 𝑄 𝑗𝑘 =  Lemma (Bienstock and Verma, 2010) : Given the supply and demand vectors {𝑔 𝑗 } and {𝑒 𝑗 } 𝑗 with 𝑔 for each connected component = 𝑒 𝑗 𝑗 𝑗 𝑗 of the network, the above equations have 𝜄 𝑗 , 𝑔 𝑗 unique solution in {𝑄 𝑗𝑘 , 𝜄 𝑗 } Load ( 𝑒 𝑗 > 0 ) Generator ( 𝑔 𝑗 > 0 )  Known as a good approximation  Frequently used for contingency analysis  Do the assumptions hold during a cascade?

  9. Line Outage Rule  Different factors can be considered in modeling outage rules  The main is thermal capacity 𝑣 𝑗𝑘  Simplistic approach: fail lines with 𝑄 𝑗𝑘 > 𝑣 𝑗𝑘 Not part of the power flow problem constraints  More realistic policy: 20 Compute the moving average 15 𝑗𝑘 ≔ 𝛽 𝑄 𝑗𝑘 𝑄 𝑗𝑘 + 1 − 𝛽 𝑄 10 ( 0 ≤ 𝛽 ≤ 1 is a parameter) Fail lines (possibly randomly) 5 𝑗𝑘 /𝑣 𝑗𝑘 is close to or above 1 if 𝜊 𝑗𝑘 = 𝑄 0 1 2 3 4 5 6  In the following examples - deterministic outage rule: 𝑗𝑘 𝑄 Fail lines with 𝑣 𝑗𝑘 > 1  More generally: 𝑗𝑘 /𝑣 𝑗𝑘  Each line (𝑗, 𝑘) is characterized by its state 𝜊 𝑗𝑘 = 𝑄  An outage rule 𝑃 𝜊 𝑗𝑘 ∈ [0,1] specifies the probability that (𝑗, 𝑘) will fail given that its current state is 𝜊 𝑗𝑘

  10. Cascading Failure Model  Input: Fully connected network graph 𝐻, supply/demand vectors with 𝑔 , lines states 𝜊 𝑗𝑘 = 𝑒 𝑗 𝑗 𝑗 𝑗  Failure Event: At time step 𝑢 = 0, a failure of a subset of lines occurs  Until no more lines fail do:  Adjust the total demand to the total supply within each component of 𝐻  Use the power flow model to compute the flows in 𝐻  Update the state of lines 𝜊 𝑗𝑘 according to the new flows  Remove the lines from 𝐻 according to a given outage rule 𝑃

  11. Example of a Cascading Failure 𝑣 13 = 1800 MW 𝑄 𝑄 13 = 3000 MW 13 = 1400 MW 1 𝑄 1 = 𝑔 1 = 2000 MW 𝑄 1 = 0 MW 3 𝑦 13 = 10 Ω 𝑄 3 = −𝑒 3 = −3000 MW 𝑄 3 = 0 MW  Until no more lines fail do:  Adjust the total demand to the total 2 supply within each component of 𝐻  Use the power flow model to 𝑄 2 = 0 MW 𝑄 2 = 𝑔 2 = 1000 MW compute the flows in 𝐻  Update the state of lines 𝜊 𝑗𝑘 Initial failure causes disconnection according to the new flows of load 3 from the generators in  Remove the lines from 𝐻 according the rest of the network to a given outage rule 𝑃 As a result, line 2,3 becomes overloaded

  12. Outline  Background  Power flows and cascading failures  Numerical results – single event  Cascade properties  Vulnerability analysis and numerical results

  13. Numerical Results - Power Grid Map  Obtained from the GIS (Platts Geographic Information System)  Substantial processing of the raw data  Used a modified Western Interconnect system, to avoid exposing the vulnerability of the real grid  13,992 nodes (substations), 18,681 lines, and 1,920 power stations.  1,117 generators (red), 5,591 loads (green)  Assumed that demand is proportional to the population size

  14. Determining The System Parameters  The GIS does not provide the power capacities and reactance values  We use the length of a line to determine its reactance  There is a linear relation  We estimate the power capacity by solving the power flow problem of the original power grid graph  Without failures – N -Resilient grid  With all possible single failures – ( N-1 ) -Resilient grid  We set the power capacity 𝑣 𝑗𝑘 = 𝐿𝑄 𝑗𝑘  𝑄 𝑗𝑘 is the flow of line 𝑗, 𝑘 and the constant 𝐿 is the grid's Factor of Safety (FoS) 𝑣 13 = 1680 MW 𝑄 13 = 1400 MW 𝑄 1 = 𝑔 1 = 2000 MW 𝑦 13 = 10 Ω 1 3 𝑄 3 = −𝑒 3 = −3000 MW 𝐿 = 1.2 We use 𝐿 = 1.2 in most of the following 2 examples 𝑄 2 = 𝑔 2 = 1000 MW

  15. Cascade Development – San Diego area N -Resilient, Factor of Safety K = 1.2

  16. Cascade Development – San Diego area

  17. Cascade Development – San Diego area

  18. Cascade Development – San Diego area

  19. Cascade Development – San Diego area

  20. Cascade Development – San Diego area 0.33 N -Resilient, Factor of Safety K = 1.2  Yield = 0.33 For ( N- 1) - Resilient  Yield = 0.35 For K = 2  Yield = 0.7 (Yield - the fraction of the demand which is satisfied at the end of the cascade)

  21. Cascade Development - 5 Rounds, Idaho-Montana-Wyoming border 0.39 N -Resilient, Factor of Safety K = 1.2  Yield = 0.39 For ( N- 1) - Resilient  Yield = 0.999 For K = 2  Yield = 0.999 (Yield - the fraction of the demand which is satisfied at the end of the cascade)

  22. Outline  Background  Power flows and cascading failures  Numerical results – single event  Cascade properties  Vulnerability analysis and numerical results

  23. Latest Major Blackout Event: San Diego, Sept. 2011 Blackout description (source: California Public Utility Commission)with the model

  24. Pacific Southwest Balancing Authority

Recommend


More recommend