East Open House Laird Drive to Wynford Drive 1 East Tunnel - PowerPoint PPT Presentation

East Open House Laird Drive to Wynford Drive 1 East Tunnel Construction Timeline Contract award Construction of launch shaft 1 year Utility relocation at headwalls Construction of headwalls 6 to 8 months Construction


  1. East Open House Laird Drive to Wynford Drive 1

  2. East Tunnel Construction Timeline  Contract award  Construction of launch shaft – 1 year  Utility relocation at headwalls  Construction of headwalls – 6 to 8 months  Construction of extraction shaft at Yonge Street 2

  3. Tunnel Boring Machine  The construction of new tunnels under Eglinton Avenue is done by tunnel boring machines (TBMs).  Each TBM moves forward by pushing off against concrete segments.  The operator advances the machine as soil is removed from the TBM face through a conveyor system.  The launch pit remains active for removal of muck/spoils. 3

  4. Launch of the Tunnel Boring Machine  The Eglinton Crosstown tunnel will consist of side-by- side or twin tunnels.  Each tunnel will be 6.75 metres internal diameter.  Initially, one machine will begin excavation; the other will follow on a parallel course soon after. 4

  5. Launch Shaft Operations  To keep the tunnel safe for the crew a ventilation system pumps fresh air into the tunnel and exhaust air is moved out of the tunnel.  Cranes remain in position during the mining operation; muck will be hauled out and new concrete tunnel segments will be delivered. 5

  6. Tunnelling Begins  Tunnel boring machines work beneath Eglinton Avenue.  Business activities and traffic will continue with this method.  A single TBM will tunnel 75 metres per week.  Each machine is capable of moving 500 cubic metres of earth per day.  The machines are made in Toronto by Caterpillar Tunneling Canada Corporation, formerly LOVAT, a world leader in tunnel boring machine manufacturing. 6

  7. East Tunnels Launch Shaft To Leslie   To Brentcliffe 7

  8. Overview: Design Excellence at Metrolinx  Design excellence at Metrolinx refers to the successful interplay between:  Functionality  Durability  Beauty  Value 8

  9. Crosstown Principles of Design Excellence 1. A strong conceptual narrative vision across the system 2. Design that elevates the quality of the public transit experience 3. Civic caliber and scale of built form and materials 4. Clarity and simplicity of architectural expression through integrated design of building systems and elements 5. Responsiveness to contextual, local and future conditions 9

  10. 1. A Strong Conceptual Narrative Vision across the System A coherent and unified architectural strategy for the entire Crosstown line Clear strategy for consistent and variable elements 10

  11. 2. Design that Elevates the Quality of the Public Transit Experience Openness through optimal spatial Optimized daylight penetration penetration 11

  12. 3. Civic Calibre and Scale of Built Form and Materials Unified ground plane inside and Civic materials and character of open outside stations and at stops spaces 12

  13. 4. Clarity and Simplicity of Architectural Expression through Integrated Building Systems and Elements Integrated structural, mechanical, A clear hierarchy and plan for and electrical systems user-centred integrated information 13

  14. 5. Responsiveness to Contextual, Local and future Conditions Integration with historic elements Sustainability measures 14

  15. Crosstown Accessible Features: Stations  Accessible path from street to platform  Accessible routes identified  Station attendant  Platform edge tactile strip  Wayfinding tiles on platforms  Near level boarding of trains  Platform edge illumination  Audible messages throughout stations  Signage with accessible features  Designated Waiting Area  Colour contrast between station walls and floors  Equipment mounted at accessible heights  Benches 15

  16. Crosstown Accessibility Features: Stops  Platform edge tactile strip  Platform edge illumination  Colour contrast at between walls and platform  Equipment mounted at accessible heights  Sheltered benches  Sheltered wheelchair area  Passenger assistance intercom  Ramp access to platforms  Signage with accessible features 16

  17. Laird Station Local Context: Demand 17

  18. Laird Station Local Context: Land Use 18

  19. Laird Station Profile View 19

  20. Laird Station Longitudinal Section 20

  21. Laird Station Main Entrance 21

  22. Laird Station Secondary Entrance 22

  23. Brentcliffe Portal 23

  24. East Portal and Don West Bridge East Portal Don West River Bridge 24

  25. Leslie Stop Local Context: Demand Wynford Stop Ferrand Stop Don Mills Station Leslie Stop Laird Station 25

  26. Leslie Stop Local Context: Pedestrian Flow 26

  27. CP Rail bridge 27

  28. Don Mills Station Local Context: Demand 28

  29. Don Mills Station Local Context: Land Use 29

  30. Don Mills Station Primary Entrance 30

  31. Don Mills Station Secondary Entrance 31

  32. Don Mills Station Longitudinal Section 32

  33. Ferrand Portal Portal 33

  34. Wynford Stop Local Context: Pedestrian Flow 34

  35. Wynford Wynford Stop as Proposed in the RCD Final Stop Configuration to be determined during Detail Design Wynford Stop as Proposed in the EA 35

  36. New Approach: Alternative Financing and Procurement (AFP) Public Private Partnership models have been underway in Canada for 20 years  165 projects  21 transportation projects  $51 billion total project value Canada-wide examples  Canada Line rapid transit project (Vancouver)  Autoroute 25 (Montréal)  Trans-Canada Highway (Atlantic Canada) Ontario examples  Pan Am games athletes village  Ottawa Light Rail Transit  Highway 407 East Phase 1  The Rt. Hon. Herb Gray Parkway (Formerly the Windsor Essex Parkway 36

  37. Owner’s Role Changes with AFP 37

  38. New Approach: Advantages of (AFP)  Increased capacity to bring projects to market  Transfer of risk  Appropriate risks transferred to private sector to ensure “on time, on budget” delivery and offer value for money  Design, construction, cost escalation, schedule delays, operations, maintenance, life cycle, financial risk  Cost certainty  Optimal cost combination: combines capital, maintenance and life cycle costs  Integration of design and construction 38

  39. New Approach: Roles and Responsibilities in the Design Build Finance Maintain model Metrolinx Role: Design Finance  Overall scope (inclusion of maintenance,  Project Budget operations, etc.)  With Infrastructure Ontario run a competitive  Project-Specific Output Specifications procurement process; select the winning (with Consultant team) contractor  Real Estate Acquisition (with City of Maintain Toronto)  Testing & Commissioning (with Toronto Build Transit Commission)  Oversee Construction Phase  Safety Certification and Project Acceptance  Quality Assurance TTC to operate  Integrated with existing TTC system 39