SFS SYSTEM CONSTRUCTION NEW SHORING – FOUNDATION SYSTEM DEVELOPED BY SFS STRUCTURES LTD.WITH COLLABORATION OF SCHEMATIC PRESENTATION
SFS SYSTEM • THE FIRST STEP IS TO DRILL ALL HOLES FOR COLUMNS / PILING
SFS SYSTEM • AFTER DRILLING HOLES COLUMNN / PILES ARE CENTERED, ALIGNED AND PLACED IN POSITION.
SFS SYSTEM • THIS HOLE DRILLING AND COLUMN / PILING PLACING TAKES PLACE PRIOR TO MASS EXCAVATI ON.
SFS SYSTEM • PERIMETER COLUMNS / PILES ARE PLACED ON SITE AND CENTRAL COLUMNS / PILES ARE PLACE D AT THE SAME TIME.
SFS SYSTEM • DETAIL OF A CENTRAL PILE AFTER INSTALLATION.
SFS SYSTEM • EXCAVATION DOES NOT COMMENCE UNTIL AFTER ALL COLUMNS / PILES ARE INSTALLED INTO THEIR EXACT LOCATION.
SFS SYSTEM • CONCRETE WALL PANELS ARE INSTALLED AS EXCAVATION PROCEEDS
SFS SYSTEM • VIEW OF FIRST ROW OF CONCRETE PANELS IN PLACE. AT THIS POINT EXCAVATION TO THE DEPTH OF 1.5 METRES IS COMPLETED.
SFS SYSTEM • AT THIS TIME THE BEAM SYSTEM INSTALLATION IS PERFORMED, CONECTING PERIMETER COLUMNS WITH CENTRAL COLUMNS (FOR EACH LEVEL OF PARKADE).
SFS SYSTEM • GENERAL VIEW OF CONDITION PREVIOUS TO INSTALLATIO N OF SECOND ROW OF CONCRETE WALL PANELS.
SFS SYSTEM • GENERAL VIEW OF CONDITION WHEN SECOND CONCRETE PANEL ROW IS COMPLETED . EXCAVATION IS NOW 3.0 METRES IN DEPTH AT THIS POINT.
SFS SYSTEM • INTERIOR VIEWPOINT AFTER SECOND ROW OF CONCRETE PANELS IS COMPLETED. ALSO SHOWS COLUMN AND BEAM SYSTEM.
SFS SYSTEM • EXTERIOR VIEWPOINT ( FROM STREET LEVEL ) WITH FIRST LEVEL OF PARKADE COMPLETED.
SFS SYSTEM • GENERAL VIEW OF THE ENTIRE SYSTEM INCLUDING CONCRETE AT THE BASE OF EACH COLUMN / PILE. SUPERSTRUCT URE COLUMNS AND BEAMS ALSO SHOWN INSTALLED.
SFS SYSTEM • PERSPECTIVE VIEW FOR THE ENTIRE SYSTEM.
SFS SYSTEM • PANORAMIC VIEW FROM STREET LEVEL.
SFS SYSTEM • INTERIOR VIEW OF ENTIRE SYSTEM FROM A LOWER ANGLE.
Recommend
More recommend