Deltaport truck staging project Port Community Liaison Committee September 5, 2017 Gerry Fleming, Project Manager Deltaport Terminal, Road and Rail Improvement Project The Deltaport truck staging facility is one part of the Deltaport T


  1. Deltaport truck staging project Port Community Liaison Committee September 5, 2017 Gerry Fleming, Project Manager

  2. Deltaport Terminal, Road and Rail Improvement Project • The Deltaport truck staging facility is one part of the Deltaport T erminal, Road and Rail Improvement Project (DTRRIP) • DTRIPP is to increase movements of containers by 600,000 TEU up to 2.4 million TEUs per year at Deltaport 2

  3. Overview • Located at the intersection of Highway 17, 17A and Deltaport Way in Delta, British Columbia • Joint partnership with the Government of Canada, the Province, and the Port Authority • Port Authority will operate the facility 3

  4. Project Location 4

  5. Purpose • Address long-standing road safety concerns • Alleviate traffic congestion when port destined container truck queues reach more than 15 container trucks in length along Roberts Bank Way causeway 5

  6. Project Benefits • Improve efficiency of the multimodal transportation network • Decrease the impact of port-destined container truck traffic on the local community • Reduce engine idling and congestion • Improve road safety 6

  7. Facility details • Capacity for up to 140 trucks, including early arrivals • Secure vehicle access gate • Commercial Vehicle Safety and Enforcement area for truck safety inspections • Off-site construction of new cycling connections between Hwy 17, 64 Street and 28 Avenue 7

  8. Rendering - view from Hwy 17A looking north at approximately 10% utilization 8

  9. Project Status • Phase 1 construction starts week of August 21, 2017 until December 2017 • Site prep and preload • Monday to Saturday • 7 a.m. to 7 p.m. • Dump trucks delivering gravel and sand • Phase 2 anticipated to start in 2018 9

  10. 10

  11. Construction schedule 2 0 1 6 2 0 1 7 2 0 1 8 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 WE ARE RFP – Design Engineer HERE Engineering and Detailed Design ALC Application and Approval Tendering Period Stage 1 – Early Works Stage 2 – Re-Tender and Main Construction Substantial Completion Total Completion 11

  12. For more information & updates • Go to our website: portvancouver.com/truckstaging.com • Sign-up to the DTRRIP e-newsletter • Email us: deltaport.truckstaging@portvancouver.com • Call us: 604.665.9166 12