deep creek bridge replacement project overview
play

DEEP CREEK BRIDGE REPLACEMENT PROJECT OVERVIEW COL Patrick V. - PowerPoint PPT Presentation

DEEP CREEK BRIDGE REPLACEMENT PROJECT OVERVIEW COL Patrick V. Kinsman P.E. Commander, Norfolk District Date: 30 Jan 2020 2 DEEP CREEK BRIDGE REPLACEMENT PROJECT Existing Bridge Part of the Dismal Swamp Canal project authorized by


  1. DEEP CREEK BRIDGE REPLACEMENT PROJECT OVERVIEW COL Patrick V. Kinsman P.E. Commander, Norfolk District Date: 30 Jan 2020

  2. 2 DEEP CREEK BRIDGE REPLACEMENT PROJECT Existing Bridge • Part of the Dismal Swamp Canal project authorized by River & Harbor Acts of 25 Jul 1912, 3 Mar 1925 and 3 July 1930 • Built in 1934; two-lane drawbridge operating in conjunction with the Deep Creek Locks • Owned and operated by the Norfolk District, U.S. Army Corps of Engineers • Considered functionally obsolete since 1996 Initial Appraisal • Requires increasing maintenance and repair • Key hurricane evacuation route

  3. 3 DEEP CREEK BRIDGE REPLACEMENT PROJECT Proposed Replacement Bridge • Construction Authorized by Water Resources Development Act of 2007 (Public Law 110-114) • Five-lane drawbridge along existing alignment • Phased construction to accommodate traffic • Two-lane eastbound bridge built south of existing bridge • Traffic shifts; existing bridge demolished • Three-lane westbound bridge constructed • Project ties into existing city roadway improvements • To be built by Norfolk District, U.S. Army Corps of Engineers; upon completion, ownership and operation and maintenance responsibilities will be transferred to City of Chesapeake

  4. 4 DEEP CREEK BRIDGE REPLACEMENT PROJECT

  5. 5 BRIDGE REPLACEMENT PROJECT: TIMELINE 1996 2016 USACE – project funding - Initial Congressional Appropriation: $10M; Replacement Assessment complete USACE: real estate activities start USACE: Project agreement signed with 1998 City of Chesapeake Congressional Authorization & City agrees to provide $20M 2017 Funding for USACE – Bridge Replacement Feasibility study Congressional Appropriation: $12M 2003 Initial Meeting with Landowner’s Chief’s Report signed; submitted to OMB & Congress 2007 2018 Congressional Project Authorization Bridge Design Complete 100% Construction Cost Estimate: $37.2M Real estate offers started Right-of-way acquisition began 2008 Limited Congressional Funding & Citizen’s Information Meeting 2019 ongoing bridge design 2015 –90% design 2015 Update to Chesapeake City Council Construction Cost estimate updated: Construction Cost estimate updated: $48.7M $57.9M 2020

  6. 6 WHAT IS TAKING SO LONG? Bottom Line Up Front *Future Timeline Contingent on Real • All are frustrated with project delay Estate, Utility Relocations, & Funding 2020 • Key actions required for contract award: Real estate acquisition, utility relocations; receive additional funding  Complete acquisitions of land / easements *Advertise construction contract 2021  Ensure completion of utility relocations: *Award construction contract – Utility companies acquiring easements *Start construction – southern bridge – Equipment must be moved prior to advertising contract 2022 *Demolition of old Deep Creek bridge  Obtain additional funds: *Proposed traffic shift to new bridge – Overall project cost estimate increased 2023 – Need additional $3.5M to award and administer the *Construction of new northern contract, $9.2M total portion of bridge 2024 *Estimated construction complete

  7. 7 WHAT IS TAKING SO LONG? ANSWER: REAL ESTATE U.S. Government needs the lands and easements in order to award construction contract • 40 parcels- rights required (combo of purchase, temp/perm easements) • 32 parcels- rights acquired; one more likely soon • 7 parcels starting condemnation process: • Unable to reach agreement with landowners on “just compensation” (fair and reasonable) • Congressionally mandated condemnation process – estimate 6-9 months • Lengthier process; requires Department of Justice and Federal court Acquisition Type: Utility Relocation Agreements: Fee: .9155 Acres  Dominion Energy – signed Temporary Work Area Easement: 1.1605 Acres  Verizon – signed Drainage Ditch: .287 Acres  Columbia Gas – signed  Cox Communications – working Ownership City of Chesapeake owned: 14 24 Privately Owned Parcels: Chesapeake Public Schools owned: 1  16 signed by owner US Government owned: 1  1 active negotiation 19 other owners - privately owned: 24  7 in condemnation

  8. 8 2003

Recommend


More recommend