decc cc se seawall pr project ct
play

DECC CC SE SEAWALL PR PROJECT CT Duluth, MN CH CHAD S SCOTT, - PowerPoint PPT Presentation

DECC CC SE SEAWALL PR PROJECT CT Duluth, MN CH CHAD S SCOTT, P PE E CHASE D DEWHIRS RST, P PE AMI Consulting Engineers, PA - Multidiscipline Engineering Firm Marine Civil Structural Mechanical Environmental OWNE NER City


  1. DECC CC SE SEAWALL PR PROJECT CT Duluth, MN CH CHAD S SCOTT, P PE E CHASE D DEWHIRS RST, P PE AMI Consulting Engineers, PA - Multidiscipline Engineering Firm Marine Civil Structural Mechanical Environmental

  2. OWNE NER ∙ City of Duluth / DECC EN ENGINEER ER: ∙ Civil, Marine, Mechanical, Environmental – AMI ∙ Electrical – Gausman & Moore

  3. Limits of Construction: Inner End of MN Slip & STA 0+00 to 12+08

  4. GENERAL CONSTRUCTION OVERVIEW/CONT GENERAL C CONSTRUCTION ON OV OVERVI VIEW  ADDENNDUMS  Install New Epoxy Coated Seawall – 54,810 SF Bid form to include Electrical & Updated Quantities o 1,218 LF x 45’ Length SSP Documentation further explaining what is included in each bid item o o C12x30 Double Wale Final Construction Documents o o 1-3/4” Tierods Historical Documents o o Timber Rub Rails o  Install New Tieback System – 1,140 LF OWNER ER F FUR URNISHED ED M MATER ERIALS HP10x42 Piling o W14x120 Transfer Beam o  Two Request For Bids Currently Out Design Helical Anchors o Structural Steel (Bid Opening 10/31/17) o  Install New Bollards & Foundations – 8 EA  Steel Sheet Pile  Design & Install Camel System – 1 LS  HP10x42 Steel Piling for Tieback System  Demo portions of existing seawall  W14x120 Steel Transfer Beam for Tieback System  Demo Vista Fleet Building  3/8” Bent Steel Cap  Demo Vista Temporary Platform Application of High-Performance Coating (Bid Opening 11/7/17) o  Civil / Mechanical / Electrical Work  Alternatives ***All Owner furnished materials are based on Neat Line Quantities per the #1 – Curb & Gutter / Bike Path o Bid Form. The Contractor is responsible for any additional materials #2 – Remaining Concrete Flatwork & Sidewalks o including the installation of a high-performance coating on the steel sheet #3 – Mechanical Material Installation o piling per the technical specifications. #4 – Electrical Installation o BIDS D DUE 11/ 11/8/1 8/17 o

  5. SITE C CONDITIONS NS & & GENERAL I INFORMA MATION/CONT NT. SITE C CONDITI TIONS & & GENERAL AL I INFORMATI TION  Winter Work  Scope of Work Limits  Staging Areas MN Slip Inner End, and STA 0+00 to 12+08 o On-site – DECC o  Schedule Off-site o Substantial Completion by June 1, 2018  Permits o Final Completion by June 15, 2018 MPCA o o  Liquidated Damages Building Demo o $1,000 per Day after June 1, 2018 o Lane Closures o  Vista Fleet Building DNR, USACE – Pending o Asbestos o Underground Storage Tank o Electronics OWNER ER F FUR URNISHED ED M MATER ERIAL S SCHED EDUL ULE o  Contaminated Soils  Tight Work Area  City Council Meeting: November 20, 2017 May need to shore roadway during Helical  o Steel Sheet Piling & Cap, H Piling, W Beams Anchor Installation FOB DECC: December 18, 2017 o Work restricted within 30’ of existing retaining  o High-Performance Coating on Steel Sheet Piling structure FOB DECC: February 2, 2018 o  Wood Relieving Platform  One lane closure Harbor Drive

  6. Onsite Staging Area Limits of Construction: Inner End of MN Slip & STA 0+00 to 12+08

  7. MARINE W E WOR ORK

  8. MN SLIP INNER END  Existing Steel Sheet Pile  New Steel Sheet Pile Cap

  9. MN SLIP INNER END – Existing Steel Sheet Pile

  10. STA 0+00 to 6+02  Wakefield Piling  Pile Supported Concrete Dock Cap

  11. STA 0+00 to 6+02 – Wakefield Piling

  12. STA 0+00 to 6+02 – Pile Supported with Wakefield Piling

  13. STA 0+00 to 6+02 – Pile Supported with Wakefield Piling

  14. STA 6+02 to 9+00 & 9+25 to 9+85  Wood Relieving Platform  Partial Wall Demolition

  15. STA 6+02 to 9+00 & 9+25 to 9+85 – Wood Relieving Platform

  16. STA 6+02 to 9+00 & 9+25 to 9+85 – Wood Relieving Platform

  17. DOCK W WALL D LL DEMOLI LITION ∙ Demo Temporary Vista Platform ∙ Remove wood platform, Vertical Piling, portions of wall, and misc. debris as noted.

  18. DOCK W WALL D LL DEMOLI LITION  Demo Temporary Vista Platform  Remove wood platform, Vertical Piling, portions of wall, and misc. debris as noted.

  19. DOCK W WALL D LL DEMOLI LITION ∙ Demo Temporary Vista Platform ∙ Remove wood platform, Vertical Piling, portions of wall, and misc. debris as noted.

  20. STA 9+00 to 9+25  Slip Bridge Abutment

  21. STA 9+00 to 9+25 – Slip Bridge Abutment

  22. STA 9+00 to 9+25 – Slip Bridge Abutment

  23. STA 9+85 to 12+08  Crib Dock Wall

  24. STA 9+85 to 12+08 – Crib Supported Concrete Structure

  25. STA 9+85 to 12+08 – Crib Supported Concrete Structure

  26. OTHE HER R R REMA MARK RKS  Survey GPS Points for Seawall Example Shown at STA 6+02 o  Key Submittals Driving Logs & Alignment o Checks – SSP (Daily) Driving Logs & Alignment o Checks – H Piles (Daily) Experienced Surveyor o Helical Anchor Design o Camel System Design o  Irvin Cannot Leave Slip Prior to Dock Wall Rehabilitation  AMI Full Time Project Management

  27. QUESTIONS ON MARINE? Connect with us on:

  28. CIVIL / / ENV NVIRONM NMENT NTAL  Demolition  Grading  Concrete Flatwork  Concrete Sidewalks  Bike Path ELI R EL RUPNOW, P PE E AMI Consulting Engineers, PA

  29. CIVIL / / ENV NVIRONM NMENT NTAL  Demolition Base o  Vista Fleet Building  Irving Loading Platforms  Concrete flatwork, bollards, signage, and other misc. Items

  30. CIVIL / / ENV NVIRONM NMENT NTAL  Demolition Add Alt 1 o  1167 LF of Curb and Gutter  1200 SY of Concrete Pavement  Remove Storm Structure and Adjust Frame and Casting Add Alt 2 o ∙ Concrete Walks ∙ 400 SF

  31. CIVIL / / ENV NVIRONM NMENT NTAL  Site Base o  Vista Loading Ramps and Platform  Planter Boxes and Stairs  Irving Loading Platforms

  32. CIVIL / / ENV NVIRONM NMENT NTAL  Site Add Alt 1 o  1098 ft 8 in Curb  1208 LF of 10 ft Wide Bike Trail  6 Pedestrian Ramps  Storm Structure

  33. CIVIL / / ENV NVIRONM NMENT NTAL  Site Add Alt 2 o  10100 SF Concrete Sidewalk

  34. QUESTIONS ON CIVIL? Connect with us on:

  35. MECHAN ANICAL AL ADAM AM M MAR ARKSTE TEINER, PE AMI Consulting Engineers, PA

  36. MECHAN ANICAL AL ∙ Installation

  37. MECHAN ANICAL AL ∙ Installation

  38. QUESTIONS ON MECHANICAL? Connect with us on:

  39. ELECTR TRICAL AL ∙ Demolition ∙ Installation SCOTT H T HAEDTK TKE Gausman & Moore

  40. ELECTR TRICAL AL ∙ Demolition

  41. ELECTR TRICAL AL ∙ Installation

  42. ELECTR TRICAL AL ∙ Installation

  43. ELECTR TRICAL AL ∙ Installation

  44. ELECTR TRICAL AL ∙ Installation Details

  45. QUESTIONS ON ELECTRCAL?

  46. QUESTIONS Connect with us on:

Recommend


More recommend