Cornell NYC Tech Central Utility Plant Community Board 8 February 12, 2014 Community Board 8 Cornell NYC Tech Central Utility Plant February 12, 2014
N Community Board 8 Cornell NYC Tech Central Utility Plant Site Plan: CUP at North of Site February 12, 2014
Exec Ed Center Residential Exec Ed Center Residential Central Utility Plant (CUP) Community Board 8 Cornell NYC Tech Central Utility Plant Concept: CUP as a ribbon to connect the adjacent buildings February 12, 2014
Resi El. +275’ approx. Exec Ed El. +200’ approx. FAB El. +96’-7” CUP El. +40’-8” El. +23’-6’ El. +21’ El. +12.5’ El. +14’ El. +14’ Esplanade DOT R.O.W. Residential Central Utility Plant Exec Ed Center Entry First Academic Bldg + Entry Plaza DOT R.O.W. Esplanade Landscape Varies 50’ 20’ 40’ 210’ 87’ 95’ 50’ Varies 552’ Community Board 8 Cornell NYC Tech Central Utility Plant North Elevation: CUP in context of N Loop Road February 12, 2014
• 11,000 GSF • Un-Occupied Equipment Building • Not a Public Building / No Public Access Only Accessible by Con Ed and Authorized Cornell Personnel • Con Edison and Other Electrical Equipment to Serve Campus Buildings • Renewable Energy Equipment Rooms (Photovoltaic Cells, Future Fuel Cell) • Ancillary Equipment to Support the Building • Non-Occupiable Green Roof and Rooftop Equipment with Screen Community Board 8 Cornell NYC Tech Central Utility Plant Building Program February 12, 2014
Community Board 8 Cornell NYC Tech Central Utility Plant Photos ConEd utility louvers in NYC: Required per Con Ed Guidelines February 12, 2014
5 6 RESIDENTIAL BUILDING EXECUTIVE EDUCATION CENTER 4 7 8 9 10 11 3 15 14 13 2 12 1 16 181’ 210’ NORTH LOOP ROAD 1 Distribution Substation 6 Transformer Room 11 MDF Room 16 Resi Service Access 2 Transformer Rooms 7 DC Distribution Room 12 Fuel Oil Room 3 Network Compartment Rooms 8 Battery Room 13 Gas Meter Room 4 Switchgear Lineups 9 Battery Room 14 Water and Sewer Room N 5 Life Safety/ATS Room 10 Transfer Trip Room 15 Janitor’s Closet Community Board 8 Cornell NYC Tech Central Utility Plant Floor Plan February 12, 2014
SCALE 1 - SAWTOOTH OF BUILDING SCALE 2 - SAWTOOTH OF EACH BAY, 3’ WIDE PANEL SCALE 3 - SAWTOOTH OF FINS AT METAL PANEL Community Board 8 Cornell NYC Tech Central Utility Plant Sawtooth at Multiple Scales The building saw-soothes at three scales February 12, 2014
5 RESIDENTIAL BUILDING EXECUTIVE EDUCATION CENTER 5 4 3 6 1 Green Roof System 2 1 Green Roof System 2 Rooftop Enclosure - Wood Screen 3 Bulkhead 4 Fuel Cell 5 AHU 6 Generator N Community Board 8 Cornell NYC Tech Central Utility Plant Roof Plan: Majority of the roof is a green roof system February 12, 2014
GRAVELS - PATHWAYS OF CAMPUS LANDSCAPE METALS - BLACKENED STAINLESS STEEL ADJACENT QUEENSBORO BRIDGE BOULDERS AND GREENERY BENCHES - BLACK LOCUST The CUP emerges as a complement to the mineral material palette of the campus landscape and Queensboro Bridge Community Board 8 Cornell NYC Tech Central Utility Plant Campus and Context Material Palette February 12, 2014
FIRST ACADEMIC BUILDING METAL PANEL SAMPLE Community Board 8 Cornell NYC Tech Central Utility Plant FAB Material Palette: CUP material is complementary February 12, 2014
Community Board 8 Cornell NYC Tech Central Utility Plant Metal Material Precedent: Create visual interest with tone February 12, 2014
Summer Solstice The CUP receives direct sunlight only in warmer months. It receives ambient light the rest of the year. Winter Solstice N Community Board 8 Cornell NYC Tech Central Utility Plant Sun Path Diagram February 12, 2014
FIRST ACADEMIC BUILDING METAL PANEL SAMPLE CUP MATERIAL SAMPLE - VARIED PATINA AND REFLECTIVITY The metal panels will have a varied fjnish, in both color and refmectivity to provide visual interest along the North facade. Community Board 8 Cornell NYC Tech Central Utility Plant CUP Material Palette February 12, 2014
PHOTO 1 - VIEW LOOKING UP AT METAL PANEL SAMPLE PHOTO 2 - INDIRECT NATURAL LIGHT Community Board 8 Cornell NYC Tech Central Utility Plant Photos of metal panel sample in varied natural light conditions February 12, 2014
Community Board 8 Cornell NYC Tech Central Utility Plant Rendering of proposed metal panel fjnish February 12, 2014
Residential Exec Ed Center Community Board 8 Cornell NYC Tech Central Utility Plant North Elevation Rendering February 12, 2014
Residential Exec Ed Center CON ED REQUIRED STORM LOUVERS, CONCEALED BY METAL PANEL SYSTEM Community Board 8 Cornell NYC Tech Central Utility Plant ConEd required louvers outlined; to be behind metal panel system February 12, 2014
VERTICAL LED STRIP LIGHT Community Board 8 Cornell NYC Tech Central Utility Plant Lighting Analysis and Night Rendering February 12, 2014
Summer, Early Morning Community Board 8 Cornell NYC Tech Central Utility Plant View West on North Loop Road: CUP left, existing building right February 12, 2014
Community Board 8 Cornell NYC Tech Central Utility Plant North Facade: View looking at one bay of metal panel system February 12, 2014