confinement and shielding
play

Confinement and Shielding: Intrabay Doors, Floor Valves and - PowerPoint PPT Presentation

Confinement and Shielding: Intrabay Doors, Floor Valves and Component Transfer Hatch Pit Lids Penetration Plugs Fire Suppression system COMMERCIAL | Critical Success Factors Affordable Economical design Value for money by delivering


  1. Confinement and Shielding: Intrabay Doors, Floor Valves and Component Transfer Hatch Pit Lids Penetration Plugs Fire Suppression system COMMERCIAL |

  2. Critical Success Factors Affordable – Economical design Value for money by delivering within budget and schedule Right, first time delivery during design, build, installation, testing, commissioning, and handover Meets or exceeds all minimum requirements Zero harm safety performance 2 COMMERCIAL |

  3. INTRABAY DOORS, FLOOR VALVES AND COMPONENT TRANSFER HATCH 3 COMMERCIAL |

  4. Project Scope Design Manufacture and testing Delivery to ESS Installation Commissioning System acceptance trials Training COMMERCIAL |

  5. Constraints/Notes/Exclusions • Constraints – Keep-in and Keep-out zone define the boundaries of the design – Embedment's are pre-cast to support equipment Sized based on concept • Notes – Mounting of radiological sensors and setting to work Sensors etc are free issued – Requirements are not prescriptive. Open to discuss other ways to address the needs – As built survey to be provided during contract • Exclusions – No requirement for: Radiological safety system is out of scope Limited to mounting of sensors etc. free issued to the contractor SIL Thermal assessment 5 COMMERCIAL |

  6. Lot 3. Floor Valves • Purpose – Protection of Workers outside ActCell in the High BAy – Enable docking of Cask & transfer of components into ActCell • Two identical FVs required (Approx 170t) – Shielding Door with portal frame shielding • Considerations – Recovery system – Confinement 6 COMMERCIAL |

  7. Lot 3: Upper & Lower Intrabay Door Purpose Protection of Workers in the Maintenance Cell Enable crane movements & waste package transfer Shield doors (~50t ea) Pivot “flap” mechanism (upper door rotated 90º) Sliding door mechanism Locking pin for Upper Door Considerations Recovery Confinement COMMERCIAL |

  8. Lot 2: Component transfer Hatch Purpose Protection of Workers in outside the ActC CTH performs nuclear safety function Enable transfer of small items into Cell Major Items Glovebox Bagging system Transfer system Tray from cold to hot Shield doors (~4T) Hot & Cold side doors Interlocked Considerations Interlocking Hot and cold doors Confinement recovery 8 COMMERCIAL |

  9. Status & Key dates Tender Action initiated PQQ Published Key Dates PQQ: Q2 2018 Contract Award: Q1 2019 Site Access: Q2/Q3 2021 Completion: Q3/Q4 2021 9 COMMERCIAL |

  10. PIT LIDS & PENETRATION PLUGS 10 COMMERCIAL |

  11. Project Scope Production Design, Manufacture and testing Delivery to ESS Installation SAT COMMERCIAL |

  12. Pit Lids Concrete Filled Purpose • – Protection of Workers in outside the ActC Major Items • – 10 off Pit Lids ( 26 sub- sections) Steel construction – Concrete filled Pit Lids – Steel Pit Lids Considerations • – Pit Cell Location features – O-ring Sealing face on external Pit Lids (WTH & PIE Cell). – Manufacturing tolerance 12 COMMERCIAL |

  13. 13 COMMERCIAL |

  14. Penetration Plugs Purpose • • Protection of Workers in outside the ActC Major Items • – ~42 off SS core (OD ~250mm) – SS Cap – O-ring Sealing face 14 COMMERCIAL |

  15. Aperture Plug Purpose Protection of Workers in outside the ActC Major Items 1 off Plug Considerations Installed in the Penetration Room (outside of the active cell) Equivalent to 1.3m HDC To fill aperture Removable from cold side 15 COMMERCIAL |

  16. Status & Key dates Tender Action – Not Started Key Dates Pit Lid Market Enquiry Published PQQ: Q3/Q4 2018 Plugs currently work in progress Contract Award: Q1/Q2 2019 Site Access: Jan 2020 Completion: Feb 2020 16 COMMERCIAL |

  17. FIRE SUPPRESSION SYSTEM 17 COMMERCIAL |

  18. Project Scope Design Production Design, Manufacture and testing Delivery to ESS Installation Commissioning COMMERCIAL |

  19. Concept Overview Purpose ActC Asset Protection Major Items Piping and water mist system Conventional piping water mist system to extinguish a fire Fire Detection in-cell VESDA system draws air from cells to detect smoke Rate-of-heat rise sensor detects heat rise within the cell Pump Skid Located outside of the Active Cell, in the surrounding technical galleries. Includes, bunded skid consisting of pumps, a water tank and leak detectors Fire Control Panel Integrate with ESS fire safety system and utilise the infrastructure supplied by UKAEA to distribute power and signalling 19 COMMERCIAL |

  20. Status & Key dates Tender Action – Not Started Key Dates Market Enquiry Published Q2/Q3 2019 Contract Award: Q4 2019 Site Access: Q2/Q3 2021 Completion: Q3/Q4 2021 20 COMMERCIAL |

  21. ESS – Active Cell Viewing System The active cells facility is a windowless hot cell operated from the remote control room. The operator views of the equipment and components in the cells are only through the Viewing System cameras. Hence the viewing system must be highly reliable and provide a combination of wide area views (safety) and operational views (inspection, process monitoring, etc.) Widely varying specs based on type of view and position: • A combination of high and low radiation tolerant cameras, B&W and Colour • Typical specification radiation tolerant from 10kGy to 1MGy TID(*) (1 � 10 Gy/hr) Tilt range Camera Pan & Tilt Units • Picture Resolution: from 576p to 1080p 90 º • Zoom Range: 70 º � 20 º (diagonal FoV) • Capable of being remotely handled by the ACF -70 º Robotic Handling system • Auto/Manual focus and iris capability • Capable of being mounted on wall brackets in -90 º (*) T otal I ntegration D ose over ESS lifecycle 90 º the cells or on moveable stands Pan range • Pan range � 90 ˚ COMMERCIAL | • Tilt Range -70 ˚ � 90 ˚

  22. ESS Active Cells Fabricated Assemblies 15/06/2018 22 COMMERCIAL | RACE-ESS-TEM-0038

  23. Fabricated Assemblies Procurement Procurement will consist of 3 main parts: • Waste Storage Baskets. • Target Station Component Support Structures. • Large lifting adaptors. The exact nature of the procurement has not been finalised, however at present it is expected that the scope will be for the design and manufacture of all the items based on provided requirements specification. A Negotiated procedure is expected, that will allow for the scope and risk profile of the procurement to be adjusted. If the scope can defined well enough that an Open procedure can be used, this MAY be done. 23 COMMERCIAL | RACE

  24. Waste Storage Boxes • A parametric design will be needed to allow a range of Waste Storage Boxes (WSBs) to be manufacture by ESS as they are needed. The boxes will be placed within an existing shielded container approximately 3mx2mx1m and will allow for: • A range of packing patterns from a single box up to six boxes. • Different shielding thicknesses ranging from 50mm up to 200mm. • A single WSB will be manufactured for use in the Acceptance Review of the Active Cells. • Expected requirements as follow: • When full, lifts from the lid using set twist lock pattern, • Removable sides. • Process to tilt onto one side when empty and back to vertical when full. • Maximum loaded weight is 25,000kg. • Stainless Steel Structure • No safety requirements in excess of those relating to standard lifting accessories. 24 COMMERCIAL | RACE

  25. Target Station Component Supports When Target Station components are introduced into the cell, a set of support structures are required to fix their location and provide stability. These include: • A receiving fixture to locate and support components as they are lowered into the cell. • Storage racks to support a number of Target Station components whilst they are waiting to be processed. General Requirements: • Interface with existing floor bolting pattern. • Stainless Steel construction (or very prescriptive painting rules). • Will have to support a maximum horizontal force TBD a fixed height from the floor 25 COMMERCIAL | RACE

  26. Lifting Adaptors A lifting adaptor to allow the lifting of a >8000kg section of target station component using the in cell Grapple. 26 COMMERCIAL | RACE

  27. Electrical Work Package Procurement Overview The Electrical Power and Signalling system is responsible for providing electrical services into the Active Cells from supplier control cubicles to supplier equipment. The Active Cells are a radiological area that will require a degree of radiation tolerance within the designed electrical system. The electrical system is a critical part of the operation of the Facility. Maintenance Process Cell Cell Active Cell Facility Overview COMMERCIAL | 27

  28. Purchasing Scope Free Issue Components for Manufacture • Suitable Remote Handling & Industrial Connectors à Band A/B • Suitable COTS Industrial Cabling à Band A • Specialist Radiation tolerant cabling >1M/Gy integrated gamma dose à Band A • Specialist Radiological lighting for Active Cells à Band A/B Purchasing Key Dates Purchasing Purchasing Value Band Value Band Contract Award: A B Q4 2018/Q1 2019 <£100K Completion: >£100K to <£500K Q3/Q4 2019 COMMERCIAL | 28

Recommend


More recommend