Fauquier County Public Schools MIDDLE SCHOOL MODERNIZATION PLAN| COMMUNITY DIALOGUE #2 Community Dialogue #2 | Tonights Agenda 1. Welcome & Introductions 2. Present Options Packet & Questionnaire 3. Small Group Work: Individual


  1. Fauquier County Public Schools MIDDLE SCHOOL MODERNIZATION PLAN| COMMUNITY DIALOGUE #2

  2. Community Dialogue #2 | Tonight’s Agenda 1. Welcome & Introductions 2. Present Options Packet & Questionnaire 3. Small Group Work: Individual Questionnaire • Group Questionnaire • 2

  3. Options Committee Meeting | Oct 6th Division leadership • Advisory Committee representatives (3) • Board representatives (2) • Consultant team • Driving question Options Development •Over what period of time… •At what cost… •With what benefits and challenges… • Can current Taylor MS & Warrenton MS students learn in 21 st Century learning environments? 3

  4. Summary of options to consider PLEASE NOTE THESE FACTORS REGARDING ALL OPTIONS: 1. Each of the dollar figures below also include demolition of the existing building(s). 2. Because the future use of the original Warrenton building (which includes the library and auditorium) is unknown, the options do not include cost of repurposing these spaces. Proposed Capacity, Projected Enrollment & Utilization 2018-19 Combined Assumed / Proposed Projected Best Case Project Estimated Cost in Capacity of New Enrollment for Completion 2016 Dollars Construction Taylor MS & Warrenton MS Option 1: Build new schools for both Taylor MS & 1,300 889 January 2024 $98,194,263 Warrenton MS. Build the new Taylor MS first. Option 2A: Consolidate Taylor MS & Warrenton MS into 1,000 889 January 2021 $55,300,036 New MS at Taylor Site at 1,000 student capacity Option 2B: Consolidate Taylor MS & Warrenton MS into New MS at Taylor Site at 900 student capacity plus an 1,200 889 January 2021 $61,421,442 addition at Auburn MS (300) Current Combined Program Capacity of Taylor MS & Warrenton MS is 1,092 4

  5. Option 1| Rebuild both Taylor MS & Warrenton MS How long will it take to complete? 7.25 years Replace both schools at 650 What is the total project cost? $98 million capacity (includes escalation over time) each Current capacity between the two schools is 1,092 After the new Taylor is built, move Warrenton Rebuild Taylor students into current Taylor MS during construction of Warrenton. If Warrenton would be rebuilt first, MS first students would have to be housed in portables (a significant disruption and cost) Consider boundary adjustments There would likely be some Middle School boundary changes to best utilize both schools 5

  6. Option 2| Consolidate Taylor MS & Warrenton MS into a new MS on Taylor’s site How long will it take to complete? 4 years Taylor site is larger & 7.5 acres of the Build on the Warrenton site is currently occupied by the What is the total project cost ? $55-61 million Taylor site County. Students would stay in their current (includes escalation over time) facilities until construction is complete. 2A – Build at 1,000 capacity ($55 million) The new school on the Taylor site would include Honor historical references to honor Mr. Taylor and 2B — Build at 900 capacity plus 300 history Taylor MS. The original Warrenton MS building addition at Auburn MS ($61 million) would be retained and repurposed. Consider boundary There would likely be some middle school adjustments boundary changes with adjacent schools 6

  7. OPTION 1 (SUMMARY) Option 1 TWO NEW MIDDLE SCHOOLS Site Taylor Middle School (650) Warrenton Middle School (650) Anticipated Start Date July 2017 Anticipated Completion Date October 2024 Total Schedule 7 years, 3 months Total Project Costs (w/ Escal.) $98,194,263

  8. OPTION 1 Option 1 NEW MS CAPACITY (650) Site: Taylor Middle School Anticipated Start Date: July 2017 Schedule: 3 years, 10 months Escalation (5%): 2016 through 2019 Total Project Costs: New Taylor MS (w/ Escalation); $42,803,694 Taylor MS Demolition (w/ Escalation); $2,692,271

  9. OPTION 1 Option 1 NEW MS CAPACITY (650) Site: Taylor Middle School Benefits: - Potentially share bus drop-off w/ Brumfield ES - Ability to separate bus traffic from vehicle traffic - Room for updated playfields - Ability to relocate running track - Opportunity to optimize building orientation for daylighting - CD#1 results favor replacement - Students stay in current building while new one is being constructed Challenges: - Some playfields will be temporary unavailable during construction

  10. OPTION 1 Option 1 NEW MS CAPACITY (650) Site: Warrenton Middle School Anticipated Start Date: December 2020 Schedule: 3 years, 10 months Escalation (5%): 2016 through 2022 Total Project Costs: New Warrenton MS (w/ Escalation); $49,550,627 Warrenton MS Demolition (w/ Escalation); $3,147,671

  11. OPTION 1 Option 1 NEW MS CAPACITY (650) Site: Warrenton Middle School Benefits: - Creation of two entry / exit points - Can set the building back from the street - Ability to keep/repurpose original WPA building portion Challenges: - Relocation of lighted / loud playfield - Connecting new construction to original WPA building portion to remain - Keeping the green space close to the building - Requires movement of the school bus fleet and school facilities department for future ballfield - Cost to construct new ballfields - Time: Must wait until County’s Stafford property is approved, designed and constructed for relocation

  12. OPTION 2A (SUMMARY) Option 2A NEW CONSOLIDATED MIDDLE SCHOOL Site Taylor Middle School (1,000) Anticipated Start Date July 2017 Anticipated Completion Date June 2021 Total Schedule 3 years, 11 months Total Project Costs (w/ Escal.) $55,300,036

  13. OPTION 2A Option 2A NEW MS CAPACITY (1,000) Site: Taylor Middle School Anticipated Start Date: July 2017 Schedule: 3 years, 11 months Escalation (5%): 2016 through 2019 Total Project Costs: New Consolidated MS (w/ Escalation); $52,607,765 Taylor MS Demolition (w/ Escalation); $2,692,271

  14. OPTION 2A Option 2A NEW MS CAPACITY (1,000) Site: Taylor Middle School Benefits: - More efficient space - Keeps a MS in Warrenton Town limits - Two entry / exits to site - Less initial cost and time to project completion and lower operating costs - Taylor and Warrenton students get into new facility sooner than other options - Increased educational and extracurricular program opportunities - Potential transportation efficiencies - Current schools 1.5 miles apart; not a significant distance to change sites - Ability to keep/repurpose original WPA building portion Challenges: - Approx. 11% of Warrenton MS students walk to school - Uniting 2 school communities - May necessitate prof. development training to operate school within a school model - Creation of larger building than board planned in the past - Ability to keep/repurpose original WPA building portion ad additional cost

  15. OPTION 2B (SUMMARY) Option 2B NEW CONSOLIDATED MIDDLE SCHOOL + AUBURN MS ADDITION Site Taylor Middle School (900) Auburn MS Addition (300) Anticipated Start Date July 2017 Anticipated Completion Date June 2021 Total Schedule 3 years, 11 months Total Project Costs (w/ Escal.) $61,421,442

  16. OPTION 2B Option 2B NEW MS CAPACITY (900) Site: Taylor Middle School Anticipated Start Date: July 2017 Schedule: 3 years, 11 months Escalation (5%): 2016 through 2019 Total Project Costs: New Consolidated MS (w/ Escalation); $49,869,450 Taylor MS Demolition (w/ Escalation); $2,692,271

  17. OPTION 2B Option 2B NEW MS CAPACITY (900) Site: Taylor Middle School Benefits: - More efficient space - Keeps a MS in Warrenton Town limits - Two entry / exits to site - Less initial cost and time to project completion and lower operating costs - Taylor and Warrenton students get into new facility sooner than other options - Increased educational and extracurricular program opportunities - Potential transportation efficiencies - Current schools 1.5 miles apart; not a significant distance to change sites - Ability to keep/repurpose original Warrenton WPA building portion Challenges: - Approx. 11% of Warrenton MS students walk to school - Uniting 2 school communities - May necessitate prof. development training to operate school within a school model - Creation of larger building than board planned in the past - Ability to keep/repurpose original Warrenton WPA building portion at additional cost

  18. OPTION 2B AUBURN MIDDLE SCHOOL MS ADDITION / EXPANSION ADDITION / EXPANSION SITE PLAN CAPACITY (300) Option 2B Site: Auburn Middle School Anticipated Start Date: July 2017 Schedule: 2.5 years Escalation (5%): 2016 through 2019 Total Project Costs: Auburn MS Additions (w/ Escalation); $8,859,721