CITY COUNTY DRAIN FLOOD MITIGATION PROJECT
OUTLINE 1 What Happened in 2018? 2 Overview of the Project 3 Challenges 4 Solutions 5 Construction Photos 2
Project Area Downtown Billings City County Drain CCD Project Area South Billings King Avenue Boulevard Interchange Interchange 3
What Happened in 2018? Significant Runoff in the Yellowstone River − Prolonged flows greater than 40,000 cfs (2-Year) − Erosion along the North Bank of the River Intense Rainstorm Occurring in Billings − Significant flows down City County Drain 4
2019 Conditions 2018 Conditions 5
Abrupt Change in Backwater Conditions City County Drain 2123.52 2133.28 Island Provides Bank Provides 2131.02 2-Year Protection 10-Year Protection 7.5’ 2.3’ 6
7
8
Challenges 1 Schedule – Provide Protection By Spring 2019 2 Conflicting Objectives A Prevent Backwater from Yellowstone River B Maintain Capacity in CCD for Storm Runoff 9
Alternative #1 Reconstruct New Drainage Ditch NOT SELECTED Right of Way Costs • Schedule • Grey Eagle Ditch • Crossing 10
Alternative #2 New RCB Storm Drain NOT SELECTED Cost • Schedule • Limited Room • 11
Recommended Solution Inlet Structure Flood Control Gate 12
Accelerate Schedule Construction Manager / General Contractor Contract (CMGC) Typical Design-Bid-Build Contract would not have met the schedule City of Billings requested proposals from Construction Contractors − COP Construction was selected Benefits − COP Construction provided Value Engineering recommendations for 30% Design − Early procurement of pipe allowed construction to begin before final design was completed − Contractor paid T&M plus an agreed-upon markup, with a maximum guaranteed price. − Allowed for efficient processing of minor field changes. 13
Construction All permits were in hand for February 2019 Start − 2 nd Coldest February in Billings History − 29.4” of Snow (3 rd Snowiest February in Billings) Construction − 4,250 LF 48” RCP Pipeline − Started 3-4-2019 and finished 4-15-2019 − Crest Gate Installed on 7-16-2019 (temporary sheet piling for water control) − Project Completed on 8-15-2019 14
48-inch RCP Pipeline
Yellowstone Outlet Structure
Pipeline Inlet Structure
Fish Bypass
Flood Control Crest Gate
Gate Automation
Gate Automation – Typical Position Yellowstone River WSEL Baseflow in CCD Through 48-inch Pipe
Gate Automation – Runoff From CCD Gate Lays Down Providing additional flow capacity for stormwater runoff Yellowstone River WSEL Baseflow
Gate Automation – Return to Typical Position Yellowstone River WSEL Baseflow in CCD Through 48-inch Pipe
Frozen Ground & Compaction 24
Groundwater 25
Backwater from Yellowstone River 26
City County Drain Stormwater Flows 27
Project is Completed Protected Upstream Residence from 2019 Runoff Condition Project came within the $2.85 million budget Gate Automation Provided Limited Work for the City Maintenance Staff 28
Questions? 29
Recommend
More recommend