CENTRAL FLORIDA EXPRESSWAY AUTHORITY CONSTRUCTION UPDATE: FEB. 2015 Ben Dreiling, P .E. | Director of Construction & Maintenance
CONSTRUCTION UPDATE Recent Accomplishments – SR 417 Partial Interchange w/ Florida’s Turnpike Work Underway – SR 417 Systems Interchange OIA (Boggy Creek) – SR 429 Schofield Interchange – SR 528 Airport Mainline Toll Plaza Demolition Looking Forward CENTRAL FLORIDA EXPRESSWAY AUTHORITY
SR 417 / FL Turnpike Partial Interchange 417-304
SR 417 / FL TURNPIKE Contract 429-304 Contractor Southland Construction Contract Amount $31,313,571 Start Date Sept. 3, 2013 Progress $ 99.4% Scheduled Completion Jan. 2015 CENTRAL FLORIDA EXPRESSWAY AUTHORITY
N
N
WORK UNDERWAY
CURRENT CONSTRUCTION PROJECTS 417-110 528-405 429-305 417-301C
SR 417 / OIA (Boggy Creek) Contract 417-301C Contractor SEMA Construction Company Contract Amount $70,900,000 Start Date January 9, 2014 Progress $ 68.9% Scheduled Completion January 2016 CENTRAL FLORIDA EXPRESSWAY AUTHORITY
SR 417 / OIA 80 70 60 50 Million $ 40 30 Average Actual (Early-Late) Cumulative 20 Budget 10 - CENTRAL FLORIDA EXPRESSWAY AUTHORITY
N CENTRAL FLORIDA EXPRESSWAY AUTHORITY
N CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
CENTRAL FLORIDA EXPRESSWAY AUTHORITY
LOOKING AHEAD
5 Year Look Ahead Project FY '15 FY '16 FY '17 FY '18 FY '19 Project Project Name Cost N o. 2015 2016 2017 2018 2014 2019 (thousands $) Existing System Improvements 417-110 SR 417 Widening Curry Ford Road - Lake Underhill Road 6,426 SR 408 Widening from Good Homes to East of Hiawassee 13,909 SR 408 Widening from SR 417 to Alafaya Trail 13,329 SR 528 / SR 436 Bridge Deck Replacement 4,632 599-777 SR 528 Econ River Bridge 1,416 599-126 SR 417 / SR 528 Ramp Improvements 1,555 429-538 SR 429 / CR 535 Southbound Off Ramp Improvements 1,022 Expansion Projects 429-202 Wekiva Parkway Section 1A 61,314 429-203 Wekiva Parkway Section 1B 61,036 429-204 Wekiva Parkway Section 2B 94,283 429-205 Wekiva Parkway Section 2A 44,406 429-206 Wekiva Parkway Section 2C 70,117 Wekiva Parkway Gantries 5,369 Interchanges 253F SR 408 / SR 417 Interchange (Phase I) 27,766 429-305 SR 429 / Schofield Road Interchange 10,428 417-301C SR 417/ Boggy Creek Interchange (Phase III) 44,646 417-304 SR 417 / Turnpike Interchange (Partial) 11,970 528-313 SR 528 / Innovation Way Interchange 53,086 Toll Facility Projects 528-405 SR 528 Airport Express Toll Plaza (Boggy Creek - CR 436) 39,872 Renewal & Resurfacing 599-731 SR 417 Resurfacing 7,920 SR 417 Resurfacing 26,886 408-720 SR 408 Resurfacing 3,348 SR 408 Resurfacing 15,774 SR 429 Resurfacing 13,200 SR 528 Resurfacing 7,808 Non-System Projects 800-903D Goldenrod Road Resurfacing 4,849