Ethel M. Burke Elementary School Classroom Restoration / Renovation Project AGENDA 1. Fire Damage Photos July 3, 2018 2. Scope of Work 3. Demolition Floor Plans 4. Renovation Floor Plans 5. Project Schedule 2 11-12-18
Ethel M. Burke Elementary School Classroom Restoration / Renovation Project Fire Damage Photos July 3, 2018 3 11-12-18
Ethel M. Burke Elementary School Classroom Restoration / Renovation Project Fire Damage Photos July 3, 2018 4 11-12-18
Ethel M. Burke Elementary School Classroom Restoration / Renovation Project Fire Damage Photos July 3, 2018 5 11-12-18
Ethel M. Burke Elementary School Classroom Restoration / Renovation Project Fire Damage Photos July 3, 2018 6 11-12-18
Ethel M. Burke Elementary School Classroom Restoration / Renovation Project Scope of Work Restoration of the original eight (8) classroom school building damaged by lightning and fire Demolition of limited interior walls, doors, ceilings, HVAC equipment, fixtures and finishes throughout the 1 st and 2 nd floors Renovated areas will receive new doors and frames, hardware, floor and wall finishes, casework and built-in cabinets, lay-in ceilings and LED lighting, display boards, HVAC equipment and systems as well as electrical and fire alarm systems Renovation of two (2) existing toilet rooms including expansion of the boy’s toilet room, new plumbing fixtures and piping, toilet accessories, lay-in ceilings, lighting and new ceramic tile finishes Limited new finishes and air conditioning in the basement 7 11-12-18
Ethel M. Burke Elementary School Classroom Restoration / Renovation Project Demolition Floor Plans 2nd Floor Demolition Plan 1st Floor Demolition Plan 4,409 sq.ft. 4,409 sq.ft. 8 11-12-18
Ethel M. Burke Elementary School Classroom Restoration / Renovation Project Renovation Floor Plans 2nd Floor Proposed Plan 1st Floor Proposed Plan 4,409 sq.ft. 4,409 sq.ft. 9 11-12-18
Ethel M. Burke Elementary School Classroom Restoration / Renovation Project Project Schedule The Time Schedule for the project is as follows: Wednesday 10/31/18 Bid packages available for Pick-up Wednesday 11/07/18 Pre-bid meeting at 3:30 P.M. at the Ethel M. Burke Elementary School, located at 112 South Black Horse Pike, Bellmawr, New Jersey 08031. Attendance at the Pre-Bid meeting is not mandatory, but strongly recommended. Tuesday 11/13/18 Deadline for Questions to Garrison Architects at 5:00 P.M. Wednesday 11/14/18 Addendum Faxed to Bidders (If Necessary) Tuesday 11/27/18 Bids Due at 3:30 P.M. at the Ethel M. Burke Elementary School, located at 112 South Black Horse Pike, Bellmawr, New Jersey 08031 Friday 07/12/19 Project Completion 10 11-12-18