Bear Road Elementary School Additions and Renovations
Tasks Underway • Foundations for Area A addition are currently underway, backfill expected to start next week • Asbestos Abatement • Courtyard site work has begun • Demolition in various areas • Photos • Top: Courtyard site work • Bottom: Foundations in Area A
Status of • Area C asbestos abatement is underway, expected to be completed in the first week Asbestos of August • Area A asbestos abatement is complete Abatement • Additional ACM discovered in exterior walls
Status of Demolition • Area A Demolition Complete • Area C Demolition 50% complete • Crawlspace mechanical, electrical and plumbing demolition is underway • Photos: • Top left and bottom: taken during Area A demolition • Top Right: taken during crawlspace demolition
Bus Loop Mock-Up / Transportation • July 15 th this area was simulated in the M&O parking lot • Drivers navigated the proposed route and provided comments • Overall route is feasible though several concerns were raised • A/E is reviewing and will share possible solutions at next project meeting
Wetlands Work • Storm drainage improvements from the school to the wetlands will be taking place this summer • Photos • Top: existing conditions at storm drain outlet • Bottom: Proposed site grading plan from Appel Osborne
• Structural Steel erection in Area A expected early August Upcoming • Plumbing rough in of Area A Work • Excavation of crawl space • Roofers expected to begin work by mid August
Potential Roadblocks • COVID-19 impacts on material deliveries • Shortage of manpower due to private/public work restarting simultaneously
Where We Expect to be • Steel super structure complete at the Kindergarten wing Come • Roofing over Kindergarten wing September • Corridor between Area A and Area B complete • Wetlands / drainage improvements complete
Brick Work at Junior/Senior High School • Brick work at flashings, expected to be complete in approximately 2 months
Playground Work • Main St. Playground demo scheduled for next week • Installation only a few weeks away • Bear Rd Playground design completed, many thanks to committee members for all of their input and assistance • Virtual tour is available on district website https://www.youtube.com/watch?v=vliRBWy2AqM&feature= youtu.be
Recommend
More recommend