AHTD Job 061275 Arkansas River Str. & Apprs. (Broadway) (LR/NLR) P.E. Public Officials Meeting February 7, 2012 Location Map Location Map South Side of River North Side of River Lane Configuration Typical Section Bridge Selection


  1. AHTD Job 061275 Arkansas River Str. & Apprs. (Broadway) (LR/NLR) P.E. Public Officials Meeting February 7, 2012

  2. Location Map

  3. Location Map

  4. South Side of River

  5. North Side of River

  6. Lane Configuration

  7. Typical Section

  8. Bridge Selection Study Goal of Study – Develop bridge types that accomplish two main objectives: • Minimize Bridge Closure Time • Most Cost Effective Structure Type

  9. Bridge Selection Study

  10. Bridge Selection Study

  11. Bridge Selection Study

  12. Bridge Selection Study

  13. Bridge Selection Study

  14. Bridge Selection Study

  15. Bridge Selection Study

  16. Bridge Selection Study Road User Cost The financial impact of the bridge closure on the traveling public. • Takes into consideration expense of traffic delays and additional miles traveled on alternate routes

  17. Bridge Selection Study

  18. Bridge Selection Study

  19. Bridge Selection Study

  20. Bridge Aesthetics

  21. Pedestrian Underpass at Ballpark

  22. Concept 1A

  23. Concept 1A – Closed Barrier

  24. Concept 1A – Open Rail

  25. Concept 1B

  26. Concept 1B – Closed Barrier

  27. Concept 1B – Open Rail

  28. Concept 2

  29. Concept 2 – Closed Barrier

  30. Concept 2 – Open Rail

Recommend