Malaekahana State Recreational Area Kahuku Section Park Improvements Department of Land and Natural Resources
Project Background • 2009 cesspool violations • 2012 TLCG contracted by DLNR • LCC violations were addressed • Scope of work shift to facilities & infrastructure • Current project scope = “Park Improvements”
Friends of Malaekahana
Next Steps 1. 5-year concessionaire contract (pending) 2. Demolition (Fall 2014) 3. Environmental Assessment (DEA = 11/14) 4. Design recommended improvements 5. DLNR to develop funding strategies 6. Construction (as early as 2016) 7. Long- term concessionaire contract (2020’ish)
Contact Information Joe Kwan The Limtiaco Consulting Group (808) 596-7790