an experiment in takt time
play

An Experiment in Takt Time 16 th LCI Congress | San Francisco, CA | - PowerPoint PPT Presentation

An Experiment in Takt Time 16 th LCI Congress | San Francisco, CA | October 7-10, 2014 Introduction to Project 7,500 SF Gut and Remodel Downtown San Mateo, CA OSHPD Project Occupied Building/ Operational Hospital IFOA-IPD


  1. An Experiment in Takt Time 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  2. Introduction to Project • 7,500 SF Gut and Remodel • Downtown San Mateo, CA • OSHPD Project • Occupied Building/ Operational Hospital • IFOA-IPD Contract with Trade Partners • Last Planner • Pull Scheduling • BIM Modeling 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  3. Why Takt Time? • P2SL looking for small project • James Pease of Sutter Health recommended P2SL for Pankow 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  4. What is Takt time? • German word for beat • Match production rate to demand rate Takt time Cycle time Duration Operation 1 Operation 2 Operation 3 Operation 4 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  5. Takt Time 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  6. Takt-time planning process Data Collection Fine Zone / Work balancing definition Team Rough agreements balancing Adapted from Ballard and Tommelein (1998) white paper • on continuous flow 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  7. Flow Summary Fire sprinkler Duct Piping Drywall Electrical 4 3 Are these work flows compatible? 2 1 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  8. Takt-time planning process Data Collection Average Activity Durations Updated Durations Sequence Details: 10 10 - Rough in electrical before top of 9 9 8 8 wall drywall 7 7 Fine Zone / Work 6 6 5 5 balancing definition 4 4 - “I can install prefab walls in 4 3 3 2 2 days, but only if entire space is 1 1 0 0 clear.” Operation Operation Operation Operation Operation Operation Operation Operation 1 2 3 4 1 2 3 4 Team Rough agreements balancing Adapted from Ballard and Tommelein (1998) white paper • on continuous flow 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  9. Line of Balance Scheduling • What is Line of Balance? • What does it have to do with Takt Time? 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  10. Line of balance scheduling • Optimize the schedule Zone 4 • Used it for pull planning Zone 3 • Did not use the full BIM, still improved the schedule significantly Zone 2 • Line of balance scheduling IS NOT Zone 1 takt-time planning Time 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  11. Dreams to Field • How did we implement Takt Time and Line of Balance in the field? 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  12. Overhead Phase LOB • Begins with Layout on the floor, ends with duct insulation, plumbing chlorinated and all overhead conduit installed. • 44 days total 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  13. 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  14. Individual Trade Workflows Piping Sequence: Duct Sequence: Electrical Sequence: 2,1,3,6,5,4 2,1,3,6,5,4 5,4,1,2,3,6 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  15. Overhead LOB 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  16. Controlling the schedule • Last Planner system • Visual plan system in the field • Goal: Communicate where people are actually working, how fast they are, and if they need to speed up or slow down 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  17. Communicating and controlling the space schedule Daily progress reports and space schedule displayed via whiteboard 16 th LCI Congress | San Francisco, CA | October 7-10, 2014 10/4/2014 17

  18. Interactive Daily Reports and Color Up 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  19. Continuous Improvement of the Plan • Initially structured with 4-day takt time, but this needed to be adapted. 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  20. Continuous Improvement of the Plan • Printed out 11x17 of the LOB schedule and worked with the trades to reschedule w/ a pencil and ruler • Took out 8 days in the schedule due to changing the sequence and crews 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  21. Current Inwall Phase LOB • Now: 29 day sequence. (initially 37 with 4-day takt). 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  22. Overhead Phase Summary Takt Time Planning Results • 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible moment to speed up or slow down • “9/10 when we accelerate, this costs us money. We’ve gone so much faster on this job and it hasn’t cost us a dime”- PM Jeff Stewart of Southland 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  23. Trade Partners Panel • Thoughts when first introduced to Takt Time and Line of Balance • Benefits and Draw Backs? • Opinion of Daily Color Ups and Reports • Effect on working conditions • Ownership of space/ cooperation • Crew Sizes/ Hours Spent compared to original estimate • Material Management 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  24. 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  25. Final Thoughts and Lessons Learned • Data of Findings (PPC) • Success of Project • Calculated Risk • Final Perspective of Takt Time • Incorporating Owner Change Order and saving time 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  26. Questions? P 2 SL 16 th LCI Congress | San Francisco, CA | October 7-10, 2014