ami pilot project update
play

AMI Pilot Project Update Advanced Metering Infrastructure July 11, - PowerPoint PPT Presentation

AMI Pilot Project Update Advanced Metering Infrastructure July 11, 2017 Overview Review of AMI Beacon Cellular pilot Goals and objectives Criteria for success Pilot Update Construction Data/Analytics Speed bumps 2 of


  1. AMI Pilot Project Update Advanced Metering Infrastructure July 11, 2017

  2. Overview • Review of AMI Beacon Cellular pilot – Goals and objectives – Criteria for success – Pilot Update • Construction • Data/Analytics – Speed bumps 2 of 11

  3. Background Zone 3 Project What Why How Who • ISSD • Tech Services • Billing • CSR’s • Field • Water Efficiency • A- Team 3

  4. Pilot Goals and Objectives Original 1. Analyze pilot to determine what will help with future phases 2. Identify agency needs for future RFP and implementations 3. Assess value to the Agency 4. Improve understanding of consumption patterns 5. Determine if cellular is a viable option New 1. Is AMI an appropriate solution for PCWA’s goals 2. Will the new ERP (Cayenta) provide the same or higher level of analytics 3. Further identify cost benefit 4 of 11

  5. Criteria for Success • Volume of data and how staff will use it Data • Getting data in the hands of customers and evaluation of the analytics Customer Awareness • Leak volume, leak prioritization, leak detection and leak notification Alerts • Billing reads without rolling a truck and promptly addressing high, low, and zero use customers Billing 5 of 11

  6. Pilot Update- Construction Orion Cellular Endpoint 6 of 11

  7. AMR (old) and AMI (new) 8

  8. 9

  9. Current Status – 63% Complete As of 7/10/17: Figure shows that 63% (974 of 1542) endpoints have been installed and provisioned. 10

  10. Leak- 149 gallons per hour found with AMI on raw water account 11