Design Development Table of Contents I. Project Team II. Conceptual Design Graphics III. Program Spaces Tabulation IV. Program Data Sheets V. Opinion of Costs VI. Project Schedule
PRELIMINARY ALTERNATE LIST 12 ‐ 15 ‐ 2014 Item Add Alternate Estimated Cost Backstops Concrete base wall with netting $95,000 Masonry construction $60,000 Dugouts Masonry base with wood Press boxes $7,500 construction Black vinyl coated $45,000 Fencing Wind screens Add Alternate $25,000 Electrical Line 24 th Street Bury line +/- $100,000
Next Steps: 50% Construction Documents to FC: December 19 Distribution only 75% Construction Documents to FC: January 14 95% Construction Documents to FC: January 21 100% Construction Documents to FC: February 4 100% Construction Documents to Board: February 9 Bidding & Negotiation: February 10– March 5 Board Bid Acceptance: March 9 Start Construction: April, 2015