Hearn Avenue Interchange Phase 3 Project Status December Project Approval & Environmental 2016 - Document Completed January Design – Complete 2021 February Ready to List - Construction 2021
Hearn Avenue Interchange Phase 3 Funding - Design APPROPRIATED REIMBURSED LOCAL FUNDS $2.13M $800,078 $800,078 Total Cost to Date: $1,600,156
Hearn Avenue Interchange Phase 3 Funding - Right of Way APPROPRIATED REIMBURSED LOCAL FUNDS $800K $91,464 $91,464 Total Cost to Date: $182,928
Hearn Avenue Interchange Phase 3 Funding - Construction PROJECT COST MEASURE M NEED ESTIMATE $23.85M $3.45M $24.0M
10
Fulton Road Improvements Project Status August Environmental Document – 2017 Completed January Design – Begin 2018 December Design – Complete 2020 March Construction – Begin 2021
Fulton Road Improvements Funding - Design APPROPRIATED REIMBURSED LOCAL FUNDS $1M $505,350 $1M Total Cost to Date: $1,505,350
Fulton Road Improvements Funding - Right of Way APPROPRIATED REIMBURSED LOCAL FUNDS $200K $165,394 $200,000 Total Cost to Date: $365,394
Project Status April Scoping/Environmental – Begin 2020 December Design – Begin 2020 April ROW – Begin 2021
Funding - Scoping/Environmental LOCAL FUNDS PROGRAMMED REIMBURSED $52K $1,038 $167 Total Cost to Date: $1,205