4 hearn avenue interchange phase 3
play

4 Hearn Avenue Interchange Phase 3 Project Status December - PowerPoint PPT Presentation

4 Hearn Avenue Interchange Phase 3 Project Status December Project Approval & Environmental 2016 - Document Completed January Design Complete 2021 February Ready to List - Construction 2021 Hearn Avenue Interchange Phase 3


  1. 4

  2. Hearn Avenue Interchange Phase 3 Project Status December Project Approval & Environmental 2016 - Document Completed January Design – Complete 2021 February Ready to List - Construction 2021

  3. Hearn Avenue Interchange Phase 3 Funding - Design APPROPRIATED REIMBURSED LOCAL FUNDS $2.13M $800,078 $800,078 Total Cost to Date: $1,600,156

  4. Hearn Avenue Interchange Phase 3 Funding - Right of Way APPROPRIATED REIMBURSED LOCAL FUNDS $800K $91,464 $91,464 Total Cost to Date: $182,928

  5. Hearn Avenue Interchange Phase 3 Funding - Construction PROJECT COST MEASURE M NEED ESTIMATE $23.85M $3.45M $24.0M

  6. 10

  7. Fulton Road Improvements Project Status August Environmental Document – 2017 Completed January Design – Begin 2018 December Design – Complete 2020 March Construction – Begin 2021

  8. Fulton Road Improvements Funding - Design APPROPRIATED REIMBURSED LOCAL FUNDS $1M $505,350 $1M Total Cost to Date: $1,505,350

  9. Fulton Road Improvements Funding - Right of Way APPROPRIATED REIMBURSED LOCAL FUNDS $200K $165,394 $200,000 Total Cost to Date: $365,394

  10. Project Status April Scoping/Environmental – Begin 2020 December Design – Begin 2020 April ROW – Begin 2021

  11. Funding - Scoping/Environmental LOCAL FUNDS PROGRAMMED REIMBURSED $52K $1,038 $167 Total Cost to Date: $1,205

Recommend


More recommend